HomeMy WebLinkAbout01-00500272- 00075678TCC Subdivision Sanitary Sewer Oversize Participation Request: Engineer's Estimate 1 Mobilization 1 Ea. $10,000.00 $10,000.00 2 6" PVC Sanitary Sewer, Depth 0 -5' 612 L.F. $20.00 $12,240.00 3 6" DIP Sanitary Sewer 215 L.F. $35.00 $7,525.00 4 Piers 9 Ea. $3,000.00 $27,000.00 5 4' Diameter Manholes 4 Ea. $1,500.00 $6,000.00 6 Connect to Existing Manhole 1 Ea. $1,000.00 $1,000.00 7 Total 1 Ea. $1,000.00 $63,765.00 1 Mobilization 1 Ea. $10,000.00 $10,000.00 2 8" PVC Sanitary Sewer, Depth 0 -5' 328 L.F. $25.00 $8,200.00 3 8" PVC Sanitary Sewer, Depth 5' -10' 284 L.F. $30.00 $9,840.00 4 8" DIP Sanitary Sewer 215 L.F. $45.00 $9,675.00 5 Piers 9 Ea. $3,000.00 $27,000.00 6 4' Diameter Manholes 4 Ea. $1,500.00 $6,000.00 7 Connect to Existing Manhole 1 Ea. $1,000.00 $1,000.00 Total $71,715.00 r OF T``% t( . �.••• ... ...� F .r 9 �• S VERONICA J. B. MORGAIN 0o ;R 77689...... w E-**� 12 -(Ii - fll Mitchell and Morgan, LLP oversize participation cost estimate.xls i i i i i � i it O rol ♦ 0 0 r. O o o � A A p� ♦ S �W I AE q m ` \ / r 0 G c I -a. O J ♦ 6 1; S� V � ♦ S \ \\ _ s f a 1 4F v '•s Jas � ��\ Ff` 3jJ DO '."00 • rn X o :3 ' ✓' wto IFAI 0 � � I f w ® q m // p0 SANITARY SEWER OVERSIZED PARTICIPATION REQUEST CANYON CREEK TOWNHOMES MWW do Morgan, LLP. C— " "' E" On �t""t°" 511 Univers,ty tkiw Eost, Suite 204 Stotion, TX 77840 (406) 2W-UW sac (400) 260 -3564 l r r i ,Q,.., b : JJM Jw cheoM.a By! VJBM TCC Subdivision Oversize Participation Worksheet Flow Calculations 0.53 0.6% 317.0 313.0 3.5 YES 6 315.9 0.6% 312.5 309.0 3.0 NO 6 1.04% t . Sra Wo , 1.8 N/A Creek Crossing 6 Dbi in i' Awes ` t1.'UJO M ' WWW ` -0.8 N/A Creek Crossing �' lAVt#f fA#ajl " fA I U►�f ' � ► t1'�RKf Lot 1A 6 1.04% 0.6% 310.0 t -0.3 N/A Creek Crossing Lot 1A 95.8 0.21 0.014 6 0.17% 0.6% (Melrose) 5.15 24 123.6 115 2.7 38377.8 33388.69 0.03 26.7 3.6 95.8 Lot 2A 0.6% 320 317.2 2.8 NO 6 1.04% 0.6% 319.0 315.9 (Melrose) 6.6 24 158.4 115 2.7 49183.2 42789.38 0.04 34.2 3.5 120.6 1.4 N/A Creek Crossing 239.0 0.53 0.014 8 0.22% 0.4% 308.0 218.4 ' Rat'IA 42A VT'AL ROW TCC 5.953 N/A 26 115 2.7 8073 7023.51 0.01 5.6 4.0 27.8 'lW'tt)rtAi.lIM 6 0.53 0.6% 317.0 313.0 3.5 YES 6 315.9 0.6% 312.5 309.0 3.0 NO 6 1.04% 0.6% 311.0 308.7 1.8 N/A Creek Crossing 6 0.53 0.6% 308.0 308.3 -0.8 N/A Creek Crossing 312.5 310.3 1.7 NO 311.0 307.0 3.5 YES 6 1.04% 0.6% 310.0 t -0.3 N/A Creek Crossing Lot 1A 95.8 0.21 0.014 6 0.17% 0.6% 320 318.47 1.5 NO 308.0 309.2 -1.7 N/A Creek Crossing 320 317.2 2.8 NO Lot 2A 120.6 0.27 0 -014 6 0.26% 0.6% 320 317.2 2.8 NO 6 1.04% 0.6% 319.0 315.9 3.1 NO TCC 239.0 0.53 0.014 6 1.04% 0.6% 319.0 315.9 2.6 NO 239.0 0.53 0.014 6 1.04% 0.6% 317.0 313.9 2.6 NO 239.0 0.53 0.014 6 1.04% 0.6% 312.5 310.3 1.7 NO 239.0 0.53 0.014 6 1.04% 0.6% 310.0 309.8 -0.3 N/A Creek Crossing 239.0 0.53 0.014 6 1.04% 0.6% 308.0 309.2 -1.7 N/A Creek Crossing 1.04% 0.6% 317.0 312.2 4.3 YES 311.0 307.0 3.5 YES These elevations are unknown and are estimated from aerial topography. Their accuracy is significant when deciding if there is adequate depth for the sanitary sewer line. For Lots to and 2A adequate cover should be on the order of 5 feet because of the estimated topography. For the TCC Subdivision to accomodate Lots 1A & 2A, an 8" Pipe must be used thoughout the TCC subdivision to provide adequate cover & be deep enough for Lots to & 2A. "Depth of Cover is measured as the difference between top of ground and top of pipe elevation. 0 = highlighted area slope used in calculations 320 315.5 3.5 YES Lot 2A 120.6 0.27 0.014 6 0.26% 0.6% 319 315.5 3.5 YES 319.0 314.2 4.8 YES TCC 239.0 0.53 0.014 6 1.04% 0.6% 319.0 314.2 4.3 YES 239.0 0.53 0.014 6 1.04% 0.6% 317.0 312.2 4.3 YES 239.0 0.53 0.014 6 1.04% 0.6% 312.5 308.6 3.4 NO 239.0 0.53 0.014 8 0.22% 0.4% 310.0 308.1 1.4 N/A Creek Crossing 239.0 0.53 0.014 8 0.22% 0.4% 308.0 307.8 -0.3 N/A Creek Crossing 311.0 307.0 3.5 YES Lot 1A 95.8 0.21 0.014 6 0.17% 0.6% 320 313.26 67 YES 320 312.0 7.0 YES Lot 2A 120.6 0.27 0.014 6 0.26% 0.6% 319 312.0 7.0 YES 319.0 310.7 8.3 YES TCC 239.0 0.53 0.014 8 0.22% 0.4% 319.0 310.7 7.8 YES 239.0 0.53 0.014 8 0.22% 0.4% 317.0 309.8 6.7 YES 239.0 0.53 0.014 8 0.22% 0.4% 312.5 308.4 3.6 YES 239.0 0.53 0.014 8 0.22% 0.4% 311.0 308.1 2.4 N/A Creek Crossing 239.0 0.53 0.014 8 0.22% 0.4% 308.0 307.8 -0.3 N/A Creek Crossing 311.0 307.0 3.5 YES These elevations are unknown and are estimated from aerial topography. Their accuracy is significant when deciding if there is adequate depth for the sanitary sewer line. For Lots to and 2A adequate cover should be on the order of 5 feet because of the estimated topography. For the TCC Subdivision to accomodate Lots 1A & 2A, an 8" Pipe must be used thoughout the TCC subdivision to provide adequate cover & be deep enough for Lots to & 2A. "Depth of Cover is measured as the difference between top of ground and top of pipe elevation. 0 = highlighted area slope used in calculations