Loading...
HomeMy WebLinkAbout01-00500272- 00075674Case file #1- 500272 STAFF REVIEW COMMENTS NO. 1 Project: TCC SUBDIVISION (FP) -FINAL PLAT (1- 500272) ENGINEERING 1. Everything looks fine. Reviewed by: Ted Mayo Date: 01/04/02 ELECTRICAL 1. Developer installs conduit as per city specs and design. 2. Developer installs street lighting as per city specs and design. 3. Developer provides temporary blanket easement for construction purposes. 4. Developer provides digital of plat and /or site plan for AutoCAD 14. Email to rbolin(a-ci .college - station.tx.us 5. Developer provides easements for electric infrastructure as installed (including street lighting). 6. Upon completion of project surveyed sealed meets and bounds descriptive easements are necessary to release temporary blanket easement. Reviewed by: Ronnie Bolin Date: NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. 2 of 3 INFRASTRUCTURE AND FACILITIES Water: This project will construct a 12" waterline from The Exchange at Luther to their eastern property boundary. Eventually, this waterline will tie -in with the waterline along Holleman West. Sewer: This property is able to gravity feed sewer to the east to an existing manhole across the creek. This project will accommodate the City by constructing a sewer line connection to the north enabling several properties to gravity sewer, as well. Streets: All streets constructed for this project will be private. Except for width, all streets will be constructed to City standard. Off -site Easements: None required. Drainage: This project will provide detention. The majority of the onsite drainage will be to the unnamed channel on the eastern property line. All drainage is to the White's Creek. Flood Plain: Due to the fact that the creek along the eastern property boundary crosses FM 2818 by way of a culvert, there is the likelihood of rising water during a storm event. The Project Engineer performed an analysis of the situation and located the 100 -year floodplain line on the pre -plat. No lot is affected by the 100 -year flood. The floodplain will be dedicated to the City as Greenway. Oversize request: See Budgetary and Financial Summary Section. Impact Fees: N/A NOTIFICATION: None Required