STAFF REVIEW COMMENTS NO. 1
Project: TCC SUBDIVISION (FP) -FINAL PLAT (1- 500272)
ENGINEERING
1. Everything looks fine.
Reviewed by: Ted Mayo Date: 01/04/02
ELECTRICAL
1. Developer installs conduit as per city specs and design.
2. Developer installs street lighting as per city specs and design.
3. Developer provides temporary blanket easement for construction
purposes.
4. Developer provides digital of plat and /or site plan for AutoCAD 14. Email
to rbolin(a-ci .college - station.tx.us
5. Developer provides easements for electric infrastructure as installed
(including street lighting).
6. Upon completion of project surveyed sealed meets and bounds
descriptive easements are necessary to release temporary blanket
easement.
Reviewed by: Ronnie Bolin Date:
NOTE: Any changes made to the plans, that have not been requested by the City of College Station,
must be explained in your next transmittal letter and "bubbled" on your plans. Any additional
changes on these plans that have not been pointed out to the City, will constitute a completely
new review.
2 of 3
INFRASTRUCTURE AND FACILITIES
Water: This project will construct a 12" waterline from The Exchange at
Luther to their eastern property boundary. Eventually, this waterline will
tie -in with the waterline along Holleman West.
Sewer: This property is able to gravity feed sewer to the east to an
existing manhole across the creek. This project will accommodate the
City by constructing a sewer line connection to the north enabling
several properties to gravity sewer, as well.
Streets: All streets constructed for this project will be private. Except for
width, all streets will be constructed to City standard.
Off -site Easements: None required.
Drainage: This project will provide detention. The majority of the onsite
drainage will be to the unnamed channel on the eastern property line.
All drainage is to the White's Creek.
Flood Plain: Due to the fact that the creek along the eastern property
boundary crosses FM 2818 by way of a culvert, there is the likelihood of
rising water during a storm event. The Project Engineer performed an
analysis of the situation and located the 100 -year floodplain line on the
pre -plat. No lot is affected by the 100 -year flood. The floodplain will be
dedicated to the City as Greenway.
Oversize request: See Budgetary and Financial Summary Section.
Impact Fees: N/A
NOTIFICATION: None Required