HomeMy WebLinkAboutstaff commentsResponse to
STAFF REVIEW COMMENTS
Project: MEADOW CREEK - PHASE 4
ENGINEERING COMMENTS NO. 2
1. If you are planning to construct Phase 4B sanitary sewer lines with Phase 4B, we will need
additional PUEs. If not, please remove from plan set and include at MH 4 a joint of pipe stub
out for future extension of main.
The stub out was added at MH 4.
2. Inline blow off is shown within limits of pipe sleeve of W-4. Can this be constructed?
The inline blow-off valve was moved to outside of the pipe sleeve.
3. Please provide complete Drainage Report for this Phase.
The drainage report previously submitted was done so with an incorrect spreadsheet
in Appendix A. The correct sheet was added and will be submitted.
A\