HomeMy WebLinkAboutdetention pond analysisDetention Pond Analysis for Meadow Creek Subdivision Phases 4 & 5 Brazos County, Texas November 2008 Developer: Main Street Homes - CS, Ltd. 900 Congress Avenue, Suite L-100 Austin, Texas 78701 (512) 801-8832 Prepared By: Civil Development, Ltd. 2033 Harvey Mitchell Parkway South College Station, TeXas 77840 (979) 764-7743 0~- ~ Detention Pond Analysis for Meadow Creek Subdivision Phases 4 & 5 Brazos County, Texas November 2008 Developer: Main Street Homes - CS, Ltd. 900 Congress Avenue, Suite L-100 Austin, Texas 78701 (512) 801-8832 Pre ap red X. Civil Development, Ltd. 2033 Harvey Mitchell Parkway South College Station, Texas 77840 (979) 764-7743 II//Y /1110 U DETENTION POND ANALYSIS MEADOW CREEK SUBDIVISION - PHASES 4 & 5 INTRODUCTION The purpose of this report is to provide the hydrological analysis of the construction of the detention ponds for Meadow Creek Subdivision - Phases 4 & S, and to verify that the proposed detention system meets the requirements set forth by the Subdivision and Development Regulations of Brazos County. Phases 4 & 5 comprise the remainder of the Meadow Creek development. GENERAL LOCATION AND DESCRIPTION The project is located on a portion of a 75 acre tract located west of FM 2154 along the south side of Koppe Bridge Road approximately 1 mile from Wellborn, Texas. The site was cleared in 2005. The existing ground elevations range from Elevation 293 to Elevation 324. The general location of the project site is shown on the vicinity map in Exhibit A. FLOOD HAZARD INFORMATION The project site is located in the Peach Creek Drainage Basin. This entire site is located in a Zone X Area according to the Flood Insurance Rate Map prepared by the Federal Emergency Management Agency (FEMA) for Brazos County, Texas and incorporated areas dated July 2, 1992, panel number 48041 C0200-C. Zone X Areas are determined to be outside of the 500-year floodplain. DEVELOPMENT DRAINAGE PATTERNS Prior to development of the previous phases of the Meadow Creek Subdivision, the storm water runoff from this site flowed in a southeasterly direction and left the site in an existing drainage channel. This runoff flows into a tributary of Peach Creek and then into the main branch of Peach Creek. Runoff from the adjacent properties to the northeast, northwest and southwest also enter the Meadow Creek site. This runoff is accounted for in the design of the drainage structures for this project. After development, the runoff will be discharged at the same location as before the development. DRAINAGE DESIGN CRITERIA The design parameters for the storm sewer and detention facility analysis are as follows: • The HEC-HMS computer program was utilized to determine peak storm water runoff rates for the detention facility design. • Design Storm Frequency Detention facility analysis 2, 5, 10, 25, 50 and 100-year storm events Runoff Curve Number (CN) - Detention Pond The Brazos County Soil Survey shows the soils in the area to be classified as hydrologic Group C & D soils. The pre-development CN is based on no development on the site. The CN for the pre-development condition was determined to be 69.7, which is consistent with the design on previous phases in the subdivision. The post-development CN is based on development of Phases 1, 2, 3, 4 & 5 of the subdivision within the detention pond drainage area. The CN calculations are found in Appendix A. • Time of Concentration, tc - Calculations are based on the method found in the TR-55 publication. Refer to Table 1 for the equations and Appendices for calculations. The runoff flow paths used for calculating the post-development times of concentration for the detention pond analysis are shown on Exhibit B. TABLE I - Time of Concentration (tc) and Lag Time Equations The time of concentration was determined using methods found in TR-55, "Urban Hydrologyfor Small Watersheds. " The equations are as follows: Time of Concentration: Tc = Tt(sheet flow) + Tt(concentrated sheet flow) where: Tt = Travel Time, minutes For Sheet Flow: Tt = 0.007 (n L)" (PZ)o.s SOA where: Tt = travel time, hours n = Manning's roughness coefficient L = flow length, feet P2 = 2-year, 24-hour rainfall = 4.5" s = land slope, ft/ft For Shallow Concentrated Flow: Tt = L / (60*V) where: Tt = travel time, minutes V = Velocity, fps L = flow length, feet From tc, Lag Times for use in EEC-HMS are computed by: Lag = 0.6* t, Refer to Appendix A for calculations. TABLE 2 - Pre- & Post-Development Runoff Information - Detention Evaluation Dev. Scenario 1 Drainage Area # (acres) Area 1 (sq.mi.) CN j r Tc (min) Lai Time (min) (hr) Pre i 101 j 188.48 .2945 j 69.7 1 83.1 49.9 i 0.83 Pre 101 j 201.63 i .3150 69.7 I 83.1 49.9 0.83 Post 401 ; 32.79 j .0512 84.4 32.4 I 19.4 0.32 Post i 402 104.71 i .1636 1 76.9 80.1 i 48.1 0.80 Post j 403 1 1.56 1 .0024 ' 86.6 j 12.8 1 7.7 0.13 Post 404 1 17.27 1 .0270 79.1 1 61.0 1 36.6 0.61 Post 1 405 1 11.96 ' .0187 82.5 1 43.2 25.9 1 0.43 Post 1 406 i 15.3 .0239 1 88.2 i 29.6 17.8 1 0.30 Post 407 18.04 .0282 i 88.2 i 28.3 17.0 1 0.28 DETENTION FACILITY DESIGN Four detention ponds have been constructed for the Meadow Creek Subdivision for previous phases. An additional detention pond will be constructed and the size of one of the existing ponds will be increased to control the peak discharge from this development such that it is less than or equal to the pre-development peak discharge. No modifications are proposed for existing Ponds 3 & 4 with this project, but the data in the computer model has been adjusted to include as-built conditions so it accurately represents conditions in the subdivision. All of the ponds act together as a single system to control runoff from the site. The total pre-development drainage area used in the analysis of previous phases was 188.48 acres, which was determined using USGS maps that offered the best available topographic data at the time. Since then, newer and more accurate topographic maps from the City of College Station have become available that show 2-foot contour intervals. Using this more accurate information, the pre-development drainage area for the entire site is 201.63 acres. Both areas were analyzed for this report. The runoff rates for Pre and Post-Development Scenarios for the system are summarized in Table 3.1. TABLE 3.1- Pre- & Post-Development Peak Discharge Comparison Q? Qs Qio I Q~s Qso Qioo Meadow Creek Detention System cfs cfs cfs cfs cfs cfs Pre-Development-188.48 acres 82 I 195 j 254 i 338 405 j 474 Pre-Development - 201.63 acres 87 j 209 1 272 362 433 I 508 Post Development - at main outfall from Pond 1 69 ! 180 245 1 331 1 393 473 Decrease in Peak Discharge 188.48 acres 13 15 9 7 12 1 Decrease in Peak Discharge (201.63 acres) 18 29 j 27 31 40 35 Note: Pre and Post-Development flowrates are computed using a 12-hr storm duration with S minute computation intervals. The elevation-storage data and the storage-discharge data for the various ponds used in this analysis are provided in Appendix C. The grading for Detention Ponds 1, 2A & 2B are shown on Exhibits C & D. As seen in Table 3.1, the Post-Development outflow from Detention Pond No. 1 is less than the Pre-Development outflow for all storm events, even when compared to the smaller basin size used in the original report for the subdivision. Detailed pre- and post- development HEC-HMS outputs are provided in Appendices D through J. Pond 1 The pond outlet structure is a concrete channel that is 10' wide and has a control structure with 2 square openings that are 2' x 2' with a flowline elevation of 293.0. The control structure also has a top crest elevation of 296.5, which allows additional weir flow over the control structure. Also, there is an overflow spillway with a crest elevation of 297.5. This spillway channel has a bottom width of 20', 3H:1 V side slopes and is lined with rock riprap to prevent erosion of the channel. The top of the pond berm will be raised to Elevation 300.5. The outlet and spillway details are shown on the Grading Plan for the Phase 1 construction drawings. The outlet structure channel has dissipater blocks to reduce the velocity of the discharge and rock riprap is used to control erosion. Pond 2A The existing pond outlet structure consists of 2-36" HDPE pipes with an upstream flowline of 296.05. One of the 36" pipes will be capped at each end to reduce the amount of flow out of this pond. Also, there is an overflow spillway with a crest elevation of 298.5. This spillway channel has a bottom width of 10', 4H:1 V side slopes and is lined with concrete to prevent erosion of the channel. Details are shown in Exhibit C. The top of the pond berm will be raised to Elevation 303.5. The proposed grading to increase the size of the pond is shown on Exhibits C & D. The outlet and spillway details are shown on the grading plans for Phases 2 & 3. The outlet structure channel has concrete channel lining to prevent erosion. Pond 2B The pond outlet structure consists of 1-42" HDPE pipe with a concrete box riser structure on the upstream end. The top of the riser box is at Elevation 302. This structure has a 1'x1' opening at Elevation 298.5 and a 3.5' wide opening at Elevation 301.0. The discharge from Pond 2B is controlled by the 2 openings in the riser structure until the water surface in the pond reaches Elevation 302, at which point the 42" outlet pipe restricts the flow from the pond. Also, there is an emergency overflow spillway with a crest elevation of 304. This spillway channel has a bottom width of 120' and 4H:1V side slopes. The top of the pond berm is at Elevation 305.2. The proposed grading of the pond and the outlet and spillway details are shown on the Grading Plan, Exhibits C & D. The outlet structure pipe will have a concrete headwall with dissipater blocks to control erosion. Ponds 3 & 4 No modifications are proposed for existing Ponds 3 & 4, and these ponds will continue to function as previously designed. TABLE 3.2 - Detention Pond Levels and Freeboard for 100 yr Rainfall Events Pond 1 Pond 2A Pond 2B ioo post Dev. WSEL 299.6 ! 302.8 304.1 To of Berm 300.5 303.5 305.2 _ Freeboard (ft.) 0.9 0.7 1.1 CONCLUSIONS The five detention facilities analyzed in this report function together as a single system. When analyzed together, the ponds reduce the peak runoff from the entire development to levels below the peak flows for the pre-development conditions. APPENDIX A Detention Pond Design Data & Calculations: SCS Curve Number Data Meadowcreek Subdivision - Phase 1 SCS Curve Number Calculations Drainage Area -101 Area - Ac. 188.48 sq. mi. 0.2945 Tc = 83.1 Lag = L = 0.6Tc = 49.9 min = 0.831 hrs Weighted Land Use Soil Type Area - Ac. CN II CN Pasture (good) C 54.73 74 21.5 Pasture (good) D 26.62 80 11.3 Wooded (good) C 58.08 70 21.6 Wooded (good) D 39.87 77 16.3 Farmstead C 4.50 82 2.0 Road 2.36 98 1.2 Water 2.32 100 1.2 Total - CN II 188.48 75.1 Average Runoff condition CN = 69.7 CN I = 57.1 ARC CN = CN 1+ 0.70(CN 11 - CN 1) Meadow Creek Subdivision - Phases 4 & 5 SCS Curve Number Calculations Post-Development Drainage Area - 401 Area - Ac. 32.79 sq. mi. 0.0512 Tc = 32.4 Lag = L = 0.6Tc = 19.4 min = 0.324 hrs Weighted Land Use Soil Type Area - Ac. CN II CN Pasture (good) C 0.90 74 2.0 Pasture (good) D 0.00 80 0.0 Wooded (good) C 2.94 70 6.3 Wooded (good) D 1.37 77 3.2 Developed Area C 18.25 89 49.5 Developed Area D 4.48 91 12.4 Open Space C 4.85 74 10.9 Open Space D 0.00 80 0.0 Farmstead C 0.00 82 0.0 Road 0.00 98 0.0 Water 0.00 100 0.0 Total - CN II 32.79 84.4 Drainage Area - 402 Area - Ac. 104.71 sq. mi. 0.1636 Tc = 80.1 Lag = L = 0.6Tc = 48.1 min = 0.801 hrs Weighted Land Use Soil Type Area - Ac. CN II CN Pasture (good) C 49.34 74 34.9 Pasture (good) D 34.55 80 26.4 Wooded (good) C 11.10 70 7.4 Wooded (good) D 0.00 77 0.0 Developed Area C 1.98 89 1.7 Developed Area D 0.00 91 0.0 Open Space C 0.00 74 0.0 Open Space D 0.00 80 0.0 Farmstead C 4.64 82 3.6 Road 1.88 98 1.8 Water 1.22 100 1.2 Total - CN 11 104.71 76.9 Drainage Area - 403 Area - Ac. 1.56 sq. mi. 0.0024 Tc = 12.8 Lag = L = 0.6Tc = 7.7 min = 0.128 hrs Weighted Land Use Soil Type Area - Ac. CN II CN Pasture (good) C 0.00 74 0.0 Pasture (good) D 0.00 80 0.0 Wooded (good) C 0.00 70 0.0 Wooded (good) D 0.00 77 0.0 Developed Area C 0.00 89 0.0 Developed Area D 0.93 91 54.3 Open Space C 0.00 74 0.0 Open Space D 0.63 80 32.3 Farmstead C 0.00 82 0.0 Road 0.00 98 0.0 Water 0.00 100 0.0 Total - CN II 1.56 86.6 Drainage Area - 404 Area - Ac. 17.27 sq. mi. 0.0270 Tc = 61.0 Lag = L = 0.6Tc = 36.6 min = 0.610 hrs Weighted Land Use Soil Type Area - Ac. CN II CN Pasture (good) C 10.43 74 44.7 Pasture (good) D 0.00 80 0.0 Wooded (good) C 0.00 70 0.0 Wooded (good) D 0.00 77 0.0 Developed Area C 2.32 89 12.0 Developed Area D 1.26 91 6.6 Open Space C 0.15 74 0.6 Open Space D 0.73 80 3.4 Farmstead C 1.90 82 9.0 Road 0.48 98 2.7 Water 0.00 100 0.0 Total - CN 11 17.27 79.1 Drainage Area - 405 Area - Ac. 11.96 sq. mi. 0.0187 TC = 43.2 Lag = L = 0 6Tc = 25.9 min = 0.432 hrs Weighted Land Use Soil Type Area - Ac. CN II CN Pasture (good). C 0.00 74 0.0 Pasture (good) D 0.00 80 0.0 Wooded (good) C 1.70 70 9.9 Wooded (good) D 4.26 77 27.4 Developed Area C 0.23 89 1.7 Developed Area D 5.22 91 39.7 Open Space C 0.00 74 0.0 Open Space D 0.55 80 3.7 Farmstead C 0.00 82 0.0 Road 0.00 98 0.0 Water 0.00 100 0.0 Total - CN II 11.96 82.5 Drainage Area - 406 Area - Ac. 15.3 sq. mi. 0.0239 Tc = 29.6 Lag = L = 0.6Tc = 17.8 min = 0.296 hrs Weighted Land Use Soil Type Area - Ac. CN II CN Pasture (good) C 0.00 74 0.0 Pasture (good) D 0.00 80 0.0 Wooded (good) C 0.00 70 0.0 Wooded (good) D 0.00 77 0.0 Developed Area C 2.64 89 15.4 Developed Area D 9.43 91 56.1 Open Space C 0.24 74 1.2 Open Space D 2.99 80 15.6 Farmstead C 0.00 82 0.0 Road 0.00 98 0.0 Water 0.00 100 0.0 Total - CN 11 15.3 88.2 Drainage Area - 407 Area - Ac. 18.04 sq. mi. 0.0282 Tc = 28.3 Lag = L = 0.6Tc = 17.0 min = 0.283 hrs Weighted Land Use Soil Type Area - Ac. CN II CN Pasture (good) C 0.00 74 0.0 Pasture (good) D 0.00 80 0.0 Wooded (good) C 0.00 70 0.0 Wooded (good) D 0.00 77 0.0 Developed Area C 7.64 89 37.7 Developed Area D 5.92 91 29.9 Open Space C 3.62 74 14.8 Open Space D 0.86 80 3.8 Farmstead C 0.00 82 0.0 Road 0.00 98 0.0 Water 0.00 100 0.0 Total - CN 11 18.04 86.2 APPENDIX B Time of Concentration Data Meadowcreek Subdivision - Phase 4 & 5 Tc Calculations-Pre-Development Drainage Area #101 Sheet Flow: n= 0.24 (dense grass) P= 4.5 L= 300 Tt= 0.007(L*n)u-" = (P)0.5*(S)0.4 Concentrated Flow 1: V= L= 404 Tt= U(60*V) _ Concentrated Flow 2: V= L= 55 Tt= U(60*V) _ Flow Through Stream V= #1 Segment #1: L= 800 Tt= U(60*V) _ Flow Throuqh Stream V= #1 Segment #2: L= 1461 Tt= U(60*V) _ Flow Through Stream #3 Segment #1: L= 384 Tt= U(60*V) Flow Through Stream #3 Segment #2: L= 581 Tt= U(60*V) Elev,= 332.3 EIev2= 331.1 Slope= 0.0040 0.919 hours= 1 55.1 min I 2 fps (unpaved) Elev,= 331.1 EIev2= 3.4 min 3.8 fps (unpaved) Elev,= 326 EIev2= 0.2 min 2.02 fps (Manning's) Elev,= 323 EIev2= 6.65 min 1 2,49 fps (Manning's) Elev,= 313 EIev2= 9.8 min 1.51 fps (Manning's) Elevl= 297 EIev2= 4.2 min V= V= 2.57 fps (Manning's) Elev,= 296.5 EIev2= 3.8 min 326 Slope= 0.0126 323 Slope= 0.0545 313 Slope= 0.0125 297 Slope= 0.0110 296.5 Slope= 0.0013 293.5 Slope= 0.005 Tr= 83.1 min Meadow Creek Subdivision - Phases 4 & 5 Tr Calculations-Post-Development Drainage Area #401 Sheet Flow: n= 0.24 (dense grass) P= 4.5 L= 210 Slope= 0.0200 Tt= 0.007(L*n)u*" = 0.363 hours= 21.8 min (P)o.s*(S)o.4 Concentrated Flow 1: V= 2.42 fps (unpaved) L= 132 Slope= 0.0227 Tt= U(60*V) _ 0.9 min Gutter Flow 1: V= 1.85 fps (paved) m. L= 245 Slope= 0.0080 Tt= U(60*V) = 2.2 min Gutter Flow 2: V= 2.2 fps (paved) L= 300 Slope= 0.0123-- Tt= U(60*V) = 2.3 min Gutter Flow 3: V= 1.92 fps (paved) L= 59 Slope= 0.0090 Tt= U(60*V) _ 0.5 min Gutter Flow 4: V= 1.92 fps (paved) L= 341 Slope= 0.0090 Tt= U(60*V) _ 3.0 min Gutter Flow 5: V= 1.85 fps (paved) L= 119 Slope= 0.0080 Tt= U(60*V) 1.1 min Flow Through Pipe s: V= 4 fps (Manning's) L= 94 Slope= 0,0080 Tt= U(60*V) = 0.4 min Flow Through Pipe 7: V= 5 fps (Manning's) L= 35 Slope= 0.0100 Tt= U(60*V) = 0.1 min Flow Through Channel 6: V= 4 fps L= 35 Slope= 0.0100 Tt= U(60*V) = 0.1 min Tc = 32.4 min Drainage Area #402 (stopping at culvert) Sheet Flow: n= P= L= 300 Tt= 0.007(L*n)".d = 0.24 (dense grass) `4.5 Slope= 0.0100 0.637 hours= 38.2 min P)0.5*(S)0.4 Concentrated Flow 1: V= L= 330 Tt= U(60*V) _ 17 fps (unpaved) Slope= 0.0110, 3.2 min Concentrated Flow 2: V= L= 553 Tt= U(60*V) _ Concentrated Flow 3: V= L= 684 Tt= U(60*V) _ Concentrated Flow 4: V= L= 335 Tt= U(60*V) _ Culvert Flow: V= L= 50 Tt= U(60*V) _ Concentrated Flow 5_ V= L= 1135 Tt= U(60*V) _ Concentrated Flow 6: V= L= 497 Tt= U(60*V) _ Channel Flow 1: V= L= 152 Tt= U(60*V) _ 2.15 fps (unpaved) Slope= 0.0180 4.3 min 1.25 fps (unpaved) Slope= 0.0060 9.1 min 1.75 fps (unpaved) Slope= 0.0120 3.2 min 2.05 fps Slope= 0.0100 0.4 min 1.35 fps (unpaved) Slope= 0.0070 14.0 min 1.45 fps (unpaved) Slope= 0.0080 F 5.7 min 1.25 fps (unpaved) Slope= 0.0050 2.0 min Tc= 80.1 min Drainage Area #403 Sheet Flow: n= 0.24` (dense grass) P= 4.5 L= 80 Slope= 0.0200 Tt= 0.007(L*n)" = 0.168 hours= 10.1 min (P)0.5*(S)0.4 Concentrated Flow 1: V= L= 21 Tt= U(60*V) _ Concentrated Flow 2: V= L= 50 Tt= L/(60*V) _ Concentrated Flow 3: V= L= 258 Tt= U(60*V) 6 fps (unpaved) Slope= 0.2500 0.1 min 2 fps (unpaved) Slope= 0.0060 0.4 min 2 fps(unpaved) Slope= 0.0100 2.2 min Tc = 12.8 min Drainage Area #404 Sheet Flow: n= P= L= 300 Tt= 0.007(L*n)u-" _ 0.24 (dense grass) 4.5 Slope= 0.0080 0.697 hours= I 41.8 min P)0.5*(S)0.4 Concentrated Flow 1: V= L= 840 Tt= U(60*V) _ 1.45 fps (unpaved) Slope= 0.0080= 9.7 min Ditch Flow: V= L= 280 Tt= U(60*V) _ Pipe Flow: V= L= 40 Tt= U(60*V) _ Flow Through Channel #3: V= L= 143 Tt= U(60*V) Flow Through Pipe #3: V= L= 24 Tt= U(60*V) _ Flow Throu h Pipe #V= L= 31 Tt= U(60*V) _ Flow Through Pipe #1: V= L= 83 Tt= U(60*V) Flow Throuqh Pond #4: V= L= 459 Tt= U(60*V) _ 2.00 fps Slope= 0.0070 2.3 min 4.00 fps Slope= 0.0545 0.2 min 2.75 fps (Manning's) Slope= 0.0200 F0.9 min 6.37 fps (Manning's) Slope= 0.0100 F0.1 min 6.95 fps (Manning's) Slope= 0.0100 0.1 min 7.02 fps (Manning's) Slope= 0.0100 0.2 min 1.35; fps Slope= 0.0070 5.7 min Tc = 61.0 min Drainage Area #405 Sheet Flow: n= P= L= 300 Tt= 0.007(L*n)u," _ 0.24 (dense grass) 4.5 Slope= 0.0150-- 0.542 hours= 32.5 min (P)0.5*(S)0.4 Concentrated Flow 1: V= L= 139 Tt= U(60*V) _ 2.05 fps (unpaved) Slope= 0.0150 1.1 min Concentrated Flow 2: V= L= 882 Tt= U(60*V) _ Flow Through Channel #5: V= L= 86 Tt= U(60*V) - Flow Through Pipe #5: V= L= 30 Tt= U(60*V) _ Flow Through Pipe #4: V= L= 34 Tt= U(60*V) Flow Through Channel #4: V= L= 143 Tt= U(60*V) _ 1.80 fps (unpaved) Slope= 0.0130 8.2 min 2.78-fps (Manning's) Slope= 0.0191 0.5 min 7.12 fps (Manning's) Slope= 0.0100 0.1 min 6.08 fps (Manning's) Slope= 0.0060 0.1 min 3.44` fps (Manning's) Slope= 0.0060 0.7 min Tc = 43.2 min Drainage Area #406 (to outlet structure between ponds) Sheet Flow: n= 0.24 (dense grass) P= 4.5 L= 162 Slope= 0.0200 Tt= 0.007(L*n)" = 0.280 hours= 16.8 min (P)0.5*(S)0.4 Concentrated Flow 1: V= L= 888' Tt= U(60*V) _ Flow thru Pipe #10: Flow thru Pipe #11: Flow through Pond #2: V= L= 266 Tt= U(60*V) 1.75 fps (unpaved) Slope= 0.0120 8.5 min 0.1 min (from Manning's) 0.3 min (from Manning's) 1.15 fps (unpaved) Slope= 0.0050 3.9 min ITc= 29.6 min Drainage Area #407 Sheet Flow: n= P= L= 125 Tt= 0.007(L*n)" -a 0.24` (dense grass) 4.5 Slope= 0.0100 0.316 hours= 19.0 min P)0.5*(S)0.4 Gutter Flow 1: V= L= 397 Tt= U(60*V) _ 1.85 fps (paved) Slope= 0.0080' 3.6 min Gutter Flow 2: V= L= 350 Tt= U(60*V) _ Flow Throuqh Pipe 30: V= L= 40 Tt= U(60*V) _ Flow Through Pipe 29: V= L= 252 Tt= L/(60*V) _ Flow Through Pipe 28: V= L= 251 Tt= U(60*V) _ Flow Through Pipe 27: V= L= 191 Tt= U(60*V) _ Flow Through Pipe 26: V= L= 181 Tt= U(60*V) _ Flow Throuqh Pipe 25: V= L= 161 Tt= U(60*V) _ Flow Through Pipe 24_ V= L= 75 Tt= L/(60*V) _ 2.90 fps (paved) Slope= 0.0200 2.0 min 5 fps (Manning's) Slope= 0.1 min 5 fps (Manning's) Slope= 0.8 min 5 fps (Manning's) Slope= 0.8 min 5 fps (Manning's) Slope= 0.6 min 5 fps (Manning's) Slope= F0.6 min 5 fps (Manning's) Slope= 0.5 min 5 fps (Manning's) Slope= 0.3 min Tc = 28.3 min APPENDIX C Detention Pond Design Data & Calculations: Elevation-Storage-Discharge Data Meadow Creek Subdivision - Phases 4 & 5 Detention Pond No. 1 Area-Capacity Data V = H * {[A1 +A2 + (Al *A2)112] /3) V = volume, ft2 A = area, ft2 H = difference in elevation, ft POND NO. 1 Area - Capacity Data Elevation ft Depth ft Area ft2 Area acres Volume (ac-ft) Cumulative ac-ft 90% ac-ft 293.00 0.00 0 0.000 0.000 0.000 0.00 294.00 294.00 9,554 0.219 0.073 0.073 0.07 295.00 295.00 32,607 0.749 0.458 0.531 0.48 296.00 296.00 41,913 0.962 0.853 1.384 1.25 297.00 297.00 50,782 1.166 1.062 2.446 2.20 298.00 298.00 61,001 1.400 1.281 3.728 3.35 299.00 299.00 84,675 1.944 1.665 5.392 4.85 300.00 300.00 115,398 2.649 2.287 7.680 6.91 Detention Pond No. 1 Elevation Discharge Data POND NO. 1 Elevation Discharge Data Elevation 2-2.0' wide x 2- high openings L=4.0' A =8.0 sf 10' wide crest=296.5 Overflow Spillway 20" sw, 3H: IV side slopes Total Di h Elevation Weir Orifice Weir crest=297.5, n=0.030 sc arge ft , depth (ft) Q, cfs' h, depth (ft) Q, cfs2 , depth (ft) Q, cfs' , depth ft Q, cfs' Q, cfs (ft) 293.0 0.0 0.0 0.0 0.0 - - - 0 293.0 294.0 1.0 12.0 - - - 12 294.0 295.0 2.0 34.0 - - - 34 295.0 296.0 2.0 55.0 - - - - 55 296.0 297.0 - - 3.0 67.0 0.5 10.6 - 77 297.0 298.0 - 4.0 77.0 1.5 55.1 0.5 18.0 150 298.0 299.0 5.0 86.0 2.5 118.6 1.5 113.2 318 299.0 300.0 - 6.0 94.5 3.5 196.4 2.5 300.0 591 300.0 1. Weir Equation Q = 3.0 * L * y3/2 2. Orifice Equation Q = 4.82 * A. * h'12 3. Overflow Spillway - Mannings Equation Meadow Creek Subdivision - Phases 4 & 5 Detention Pond No. 2A Area-Capacity Data V = H * {[A1 +A2 + (Al *A2)1121 /3) V = volume, f:2 A = area, ft2 H = difference in elevation, ft POND NO. 2A Area - Capacity Data Elevation ft Depth ft Area ft2 Area acres Volume (ac-ft) Cumulative ac-ft 90% ac-ft 296.05 0.00 0 0.000 0.000 0.000 0.00 297.00 0.95 14,557 0.334 0.106 0.106 0.10 298.00 1.95 100,047 2.297 1.169 1.275 1.15 299.00 2.95 133,535 3.066 2.672 3.947 3.55 300.00 3.95 143,602 3.297 3.180 7.127 6.41 301.00 4.95 150,966 3.466 3.381 10.508 9.46 302.00 5.95 158,795 3.645 3.555 14.063 12.66 303.00 6.95 166,638 3.825 3.735 17.798 16.02 Detention Pond No. 2A Elevation Discharge Data POND NO. 2A Elevation Discharge Data Elevation 1-36" Pipe n = 0.012 10' wide Concrete Overflow Spillway Crest = 298.5 Total Dischar e Elevation HW, Depth TW, Depth Flow, Q n = 0.012 g ft ft ft cfs Depth, ft Flow, Q cfs' Q, cfs (ft) 296.05 0.00 0.0 0.0 - - 0 296.05 297.0 0.95 0.0 5.4 - - 5 297.0 298.0 1.95 0.0 18.8 - - 19 298.0 299.0 2.95 0.5 36.8 0.5 10.0 47 299.0 300.0 3.95 2.0 54.5 1.5 55.2 110 300.0 301.0 4.95 2.6 67.5 2.5 129.0 197 301.0 302.0 5.95 3.4 76.4 3.5 232.0 308 302.0 303.0 6.95 4.0 87.8 4.5 366.0 454 303.0 1. Overflow Spillway - Mannings Equation Meadow Creek Subdivision - Phases 4 & 5 Detention Pond No. 2B Area-Capacity Data V = H • {[A1+A2 + (A1'A2)1/) / 3) V = volume, ft2 A = area, ft H = difference in elevation, ft POND NO. 2B Area - Capacity Data Elevation ft Depth ft Area ft2 Area acres Volume ac-ft Cumulative Volume ac-ft 90% Volume (ac-ft) 298.5 0.00 0 0.000 0.000 0.000 0.00 299.0 0.50 12,630 0.290 0.048 0.048 0.04 300.0 1.50 65,655 1.507 0.819 0.868 0.78 301.0 2.50 83,526 1.917 1.708 2.576 2.32 302.0 3.50 88,165 2.024 1.971 4.546 4.09 303.0 4.50 92,893 2.133 2.078 6.625 5.96 304.0 5.50 97,729 2.244 2.188 8.812 7.93 305.0 6.50 103,025 2.365 2.304 11.116 10.00 Detention Pond No. 2B Elevation Discharge Data POND NO. 2B Elevat ion Discharge Data Elevation VW x 1'H opening Ao=1.0 sf 3.5' wide Opening & Outlet Structure Overflow L=3.5' Elev. 301 42" Pipe 120' wide Overflow Spillway 120' BW, 4H:1V side slopes Controlled Discharge Elevation Orifice Weir Invert = 298.5 crest=304.0, n=0.035 HW, depth TW, depth Q' , depth QZ HW, depth TW, depth Q , depth Q3 Q ft ft ft cfs ft cfs ft ft cfs ft cfs cfs (ft) 298.5 0 - 0.0 - - 0 0 - - 0 298.5 299.0 0.5 - 1.1 - - 0.5 - - 1 299.0 300.0 1.5 0.5 4.8 - - 1.5 - - 5 300.0 301.0 2.5 0.5 6.8 - - 2.5 - - 7 301.0 302.0 3.5 1.2 7.3 1.0 10.5 3.5 - - ] j 18 302.0 303.0 4.5 3.1 - - - 4.5 3.1 77.9 - 78 303.0 304.0 5.5 3.8 - - - 5.5 3.8 92.2 - 92 304.0 305.0 6.5 4.0 - - - 6.5 4.0 109.1 1.0 352.0 447 305.0 1. Orifice Equation C=0.6 2. Weir Equation Q = 3.0' L * y3/2 3. Overflow Spillway - Mannings Equation The outlet structure is a 4.5'x 4.5' concrete riser box with a 1' wide x 1' high opening at Elev. 298.5, a 3.5' wide weir opening at Elev. 301 and a top elevation of 302. The openings in the outlet structure control the rate of discharge until the pond level reaches Elev. 302, at which point the 42" pipe controls the discharge. Meadow Creek Subdivision - Phases 4 & 5 Detention Pond No. 3 Area-Capacity Data V = H * ([A1+A2 + (A1*A2)1121 /3) V = volume, ft2 A = area, ft2 H = difference in elevation, ft POND NO.3 Area - Ca aci Data Elevation ft Depth (ft) Area ft 2 Area acres Volume (ac-ft) Cumulative Volume ac-ft 90% Cumulative Volume ac-ft 308.00 0.00 0 0.000 0.000 0.000 0.00 309.00 1.00 5,530 0.127 0.042 0.042 0.04 310.00 2.00 13,441 0.309 0.211 0.253 0.23 311.00 3.00 16,180 0.371 0.340 0.593 0.53 312.00 4.00 19,019 0.437 0.404 0.997 0.90 Detention Pond No. 3 Elevation Discharge Data POND NO. 3 Elevation Discharge Data Elevation 15" Pipe n = 0.012 1.8' wide Concrete Overflow Spillway Crest = 310 Total Dischar e Elevation Depth, Flow, Q n = 0.014 g ft ft cfs Depth, ft Flow, Q cfs Q, cfs (ft) 308.0 0.0 0.0 0.0 0 0 308.0 309.0 1.0 3.1 - - 3 309.0 310.0 2.0 5.8 0.0 - 6 310.0 311.0 3.0 8.2 1.0 12 20 311.0 312.0 4.0 10.0 2.0 50.6 61 312.0 Meadow Creek Subdivision - Phases 4 & 5 Detention Pond No. 4 Area-Capacity Data V = H * ([A1 +A2 + (Al 'A2)'121 /3) V = volume, ft2 A = area, ft2 H = difference in elevation, ft POND NO. 4 Area - Ca aci Data Elevation ft Depth ft Area ft2 Area acres Volume ac-ft Cumulative Volume ac-ft 90% Cumulative Volume ac-ft 311.00 0.00 0 0.000 0.000 0.000 0.00 312.00 1.00 3,929 0.090 0.030 0.030 0.03 313.00 2.00 10,430 0.239 0.159 0.189 0.17 314.00 3.00 15,306 0.351 0.294 0.483 0.43 315.00 4.00 18,915 0.434 0.392 0.875 0.79 316.00 5.00 22,624 0.519 0.476 1.351 1.22 Detention Pond No. 4 Elevation Discharge Data POND NO.4 Elevation Discharge Data Elevation 15" Pipe n = 0.012 2.1' wide Concrete Overflow Spillway Crest = 314.0 Total Di h Elevation Depth, Flow, Q n = 0.014 sc arge ft ft cfs Depth, ft Flow, Q cfs Q, cfs ft 311.0 0.0 0.0 - - 0 311.0 312.0 1.0 3.1 - - 3 312.0 313.0 2.0 5.8 - - 6 313.0 314.0 3.0 8.2 - - 8 314.0 315.0 4.0 10.0 1.0 12.5 23 315.0 316.0 5.0 11.5 2.0 57.8 63 316.0 APPENDIX D Pre-Development HEC-HMS Output Data for 188.48 acres Project: Meadow Creek Simulation Run: Pre 2 yr 188 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 188 End of Run: 290ct2008, 13:15 Meteorologic Model: 2 yr 12 hr Compute Time: 04Nov2008, 14:54:36 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.2945 81.6 280ct2008, 20:05 0.90 Existing topo 0.2945 81.7 280ct2008, 20:05 0.90 Outfall 0.2945 81.7 280ct2008, 20:05 0.90 Project: Meadow Creek Simulation Run: Pre 5 yr 188 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 188 End of Run: 290ct2008, 13:15 Meteorologic Model: 5 yr 12 hr Compute Time: 04Nov2008, 14:55:44 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time.of Peak Volume (IN) 101 0.2945 195.1 280ct2008, 20:00 2.20 Existing topo 0.2945 195.0 280ct2008, 20:00 2.20 Outfall 0.2945 195.0 280ct2008, 20:00 2.20 Project: Meadow Creek Simulation Run: Pre 10 yr 188 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 188 End of Run: 290ct2008, 13:15 Meteorologic Model: 10 yr 12 hr Compute Time: 04Nov2008, 14:53:34 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.2945 254.2 280ct2008, 20:00 2.95 Existing topo 0.2945 254.1 280ct2008, 20:00 2.95 Outfall 0.2945 254.1 280ct2008, 20:00 2.95 Project: Meadow Creek Simulation Run: Pre 25 yr 188 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 188 End of Run: 290ct2008, 13:15 Meteorologic Model: 25 yr 12 hr Compute Time: 04Nov2008, 14:54:02 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.2945 337.9 280ct2008, 20:00 3.93 Existing topo 0.2945 338.0 280ct2008, 20:00 3.93 Outfall 0.2945 338.0 280ct2008, 20:00 3.93 Project: Meadow Creek Simulation Run: Pre 50 yr 188 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 188 End of Run: 290ct2008, 13:15 Meteorologic Model: 50 yr 12 hr Compute Time: 04Nov2008, 14:55:11 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.2945 404.4 280ct2008, 20:00 4.81 Existing topo 0.2945 404.8 280ct2008, 20:00 4.81 Outfall 0.2945 404.8 280ct2008, 20:00 4.81 Project: Meadow Creek Simulation Run: Pre 100 yr 188 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 188 End of Run: 290ct2008, 13:15 Meteorologic Model: 100 yr 12 hr Compute Time: 04Nov2008, 14:53:11 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.2945 473.9 280ct2008, 20:00 5.73 Existing topo 0.2945 473.9 280ct2008, 19:55 5.73 1 Outfall 0.2945 473.9 280ct2008, 19:55 5.73 APPENDIX E Pre-Development HEC-HMS Output Data for 201.63 acres Project: Meadow Creek Simulation Run: Pre 2 yr 200 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 200 End of Run: 290ct2008, 13:15 Meteorologic Model: 2 yr 12 hr Compute Time: 04Nov2008, 14:54:50 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.3150 87.2 280ct2008, 20:05 0.90 Existing topo 0.3150 87.4 280ct2008, 20:05 0.90 Outfall 0.3150 87.4 280ct2008, 20:05 0.90 Project: Meadow Creek Simulation Run: Pre 5 yr 200 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 200 End of Run: 290ct2008, 13:15 Meteorologic Model: 5 yr 12 hr Compute Time: 04Nov2008, 14:55:59 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.3150 208.7 280ct2008, 20:00 2.20 Existing topo 0.3150 208.5 280ct2008, 20:00 2.20 Outfall 0.3150 208.5 280ct2008, 20:00 2.20 Project: Meadow Creek Simulation Run: Pre 10 yr 200 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 200 End of Run: 290ct2008, 13:15 Meteorologic Model: 10 yr 12 hr Compute Time: 04Nov2008, 14:53:49 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.3150 271.9 280ct2008, 20:00 2.95 Existing topo 0.3150 271.7 280ct2008, 20:00 1 2.95 Outfall 0.3150 271.7 280ct2008, 20:00 2.95 Project: Meadow Creek Simulation Run: Pre 25 yr 200 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 200 End of Run: 290ct2008, 13:15 Meteorologic Model: 25 yr 12 hr Compute Time: 04Nov2008, 14:54:17 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.3150 361.4 280ct2008, 20:00 3.93 Existing topo 0.3150 361.5 280ct2008, 20:00 3.93 Outfall 0.3150 361.5 280ct2008, 20:00 3.93 Project: Meadow Creek Simulation Run: Pre 50 yr 200 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 200 End of Run: 290ct2008, 13:15 Meteorologic Model: 50 yr 12 hr Compute Time: 04Nov2008, 14:55:21 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.3150 432.6 280ct2008, 20:00 4.81 Existing topo 0.3150 433.0 280ct2008, 20:00 4.81 Outfall 0.3150 433.0 280ct2008, 20:00 4.81 Project: Meadow Creek Simulation Run: Pre 100 yr 200 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Pre Dev 200 End of Run: 290ct2008, 13:15 Meteorologic Model: 100 yr 12 hr Compute Time: 04Nov2008, 14:53:20 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 101 0.3150 506.9 280ct2008, 20:00 5.73 Existing topo 0.3150 507.7 280ct2008, 20:00 5.73 Outfall 0.3150 507.7 280ct2008, 20:00 5.73 APPENDIX F Post-Development HEC-HMS Output Data Project: Meadow Creek Simulation Run: Post 5 yr 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Post Dev End of Run: 290ct2008, 13:15 Meteorologic Model: 5 yr 12 hr Compute Time: 04Nov2008, 14:57:47 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 401 0.0512 93.3 280ct2008, 19:25 3.54 402 0.1636 146.0 280ct2008, 19:55 2.82 403 0.0024 6.5 280ct2008, 19:10 3.76 404 0.0270 30.4 280ct2008, 19:45 3.02 405 0.0187 28.3 280ct2008, 19:30 3.35 406 0.0239 49.7 280ct2008, 19:20 3.92 407 0.0282 57.3 280ct2008, 19:20- 3.72 Jct.3 0.0720 81.2 280ct2008, 19:25 3.43 Jct.4 0.2638 198.9 280ct2008, 19:55 3.08 Jct.5 0.3150 181.8 280ct2008, 20:15 3.16 Jct 1 0.0294 26.9 280ct2008, 20:00 3.08 Jct 2 0.0481 37.1 280ct2008, 19:40 3.19 Junction-1 0.0000 0.0 280ct2008, 13:00 Junction-2 0.0000 0.0 280ct2008, 13:00 Outfall 0.3150 180.2 280ct2008, 20:25 3.16 Pond1 0.3150 180.2 280ct2008, 20:25 3.16 Pond2A 0.2638 163.3 280ct2008, 20:20 3.08 Pond2B 0.0720 42.5 280ct2008, 20:15 3.43 Pond3 0.0294 24.7 280ct2008, 20:10 3.08 Pond4 0.0270 26.0 280ct2008, 20:00 3.02 Reach 1 0.0481 37.0 280ct2008, 19:40 3.19 Project: Meadow Creek Simulation Run: Post 2 yr 12 hr Start of Run: 280ct2008, 13:00 Basin Model: End of Run: 290ct2008, 13:15 Meteorologic Model: Compute Time: 04Nov2008, 14:57:15 Control Specifications Volume Units: IN Post Dev 2yr12hr 24 hr duration Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 401 0.0512 56.3 280ct2008, 19:25 1.83 402 0.1636 72.5 280ct2008, 19:55 1.31 403 0.0024 4.2 280ct2008, 19:10 2.01 404 0.0270 16.2 280ct2008, 19:45 1.45 405 0.0187 16.2 280ct2008, 19:30 1.69 406 0.0239 31.8 280ct2008, 19:20 2.14 407 0.0282 35.6 280ct2008, 19:20 1.98 Jct.3 0.0720 49.9 280ct2008, 19:25 1.76 Jct.4 0.2638 91.1 280ct2008, 19:55 1.50 Jct.5 0.3150 76.9 280ct2008, 19:30 1.56 Jct 1 0.0294 11.1 280ct2008, 20:10 1.50 Jct 2 0.0481 20.6 280ct2008, 19:35 1.57 Junction-1 0.0000 0.0 280ct2008, 13:00 Junction-2 0.0000 0.0 280ct2008, 13:00 Outfall 0.3150 69.3 280ct2008, 20:40 1.56 Pond 1 0.3150 69.3 280ct2008, 20:40 1.56 Pond2A 0.2638 65.4 280ct2008, 20:30 1.50 Pond2B 0.0720 12.1 280ct2008, 21:10 1.76 Pond3 0.0294 9.9 280ct2008, 20:25 1.50 Pond4 0.0270 10.8 280ct2008, 20:10 1.45 Reach 1 0.0481 20.6 280ct2008, 19:35 1.57 Project: Meadow Creek Simulation Run: Post 10 yr 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Post Dev End of Run: 290ct2008, 13:15 Meteorologic Model: 10 yr 12 hr Compute Time: 04Nov2008, 14:56:44 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 401 0.0512 108.6 280ct2008, 19:25 4.44 402 0.1636 181.4 280ct2008, 19:55 3.66 403 0.0024 7.4 280ct2008, 19:10 4.68 404 0.0270 37.0 280ct2008, 19:40 3.88 405 0.0187 33.5 280ct2008, 19:30 4.24 406 0.0239 57.0 280ct2008, 19:20 4.85 407 0.0282 66.1 280ct2008, 19:20 4.63 Jct.3 0.0720 96.2 280ct2008, 19:25 4.32 Jct.4 0.2638 262.0 280ct2008, 19:55 3.94 Jct.5 0.3150 248.1 280ct2008, 20:15 4.02 Jct 1 0.0294 35.4 280ct2008, 19:55 3.95 Jct 2 0.0481 52.4 280ct2008, 19:55 4.06 Junction-1 0.0000 0.0 280ct2008, 13:00 Junction-2 0.0000 0.0 280ct2008, 13:00 Outfall 0.3150 245.4 280ct2008, 20:20 4.02 Pond1 0.3150 245.4 280ct2008, 20:20 4.02 Pond2A 0.2638 221.9 280ct2008, 20:20 3.94 Pond2B 0.0720 62.1 280ct2008, 20:10 4.32 Pond3 0.0294 33.5 280ct2008, 20:00 3.95 Pond4 0.0270 34.1 280ct2008, 19:55 3.88 Reach 1 0.0481 52.2 280ct2008, 19:55 4.06 Project: Meadow Creek Simulation Run: Post 25 yr 12 hr Start of Run: 280ct2008, 13:00 Basin Model: End of Run: 290ct2008, 13:15 Meteorologic Model: Compute Time: 04Nov2008, 14:57:00 Control Specifications Volume Units: IN Post Dev 25yr12hr 24 hr duration Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 401 0.0512 131.9 280ct2008, 19:25 5.58 402 0.1636 231.8 280ct2008, 19:55 4.73 403 0.0024 8.8 280ct2008, 19:10 5.84 404 0.0270 46.7 280ct2008, 19:40 4.98 405 0.0187 41.3 280ct2008, 19:30 5.36 406 0.0239 68.1 280ct2008, 19:20 6.02 407 0.0282 79.6 280ct2008, 19:20 5.79 Jct.3 0.0720 118.8 280ct2008, 19:25 5.45 Jct.4 0.2638 341.9 280ct2008, 19:50 5.04 Jct.5 0.3150 334.0 280ct2008, 20:10 5.13 Jct 1 0.0294 46.1 280ct2008, 19:50 5.05 Jct 2 0.0481 71.2 280ct2008, 19:50 5.17 Junction-1 0.0000 0.0 280ct2008, 13:00 Junction-2 0.0000 0.0 280ct2008, 13:00 Outfall 0.3150 331.4 280ct2008, 20:15 5.13 Pond 1 0.3150 331.4 280ct2008, 20:15 5.13 Pond2A 0.2638 297.4 280ct2008, 20:15 5.04 Pond2B 0.0720 80.9 280ct2008, 20:05 5.45 Pond3 0.0294 44.4 280ct2008, 20:00 5.05 Pond4 0.0270 44.3 280ct2008, 19:50 4.98 Reach 1 0.0481 71.1 280ct2008, 19:50 5.17 Project: Meadow Creek Simulation Run: Post 50 yr 12 hr Start of Run: 280ct2008, 13:00 Basin Model: Post Dev End of Run: 290ct2008, 13:15 Meteorologic Model: 50 yr 12 hr Compute Time: 04Nov2008, 14:57:32 Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak Volume (IN) 401 0.0512 149.7 280ct2008, 19:25 6.57 402 0.1636 270.9 280ct2008, 19:55 5.67 403 0.0024 9.9 280ct2008, 19:10 6.84 404 0.0270 54.2 280ct2008, 19:40 5.94 405 0.0187 47.3 280ct2008, 19:30 6.34 406 0.0239 76.6 280ct2008, 19:20 7.03 407 0.0282 89.8 280ct2008, 19:20 6.79 Jct.3 0.0720 137.0 280ct2008, 19:25 6.43 Jct.4 0.2638 392.2 280ct2008, 19:50 6.00 Jct.5 0.3150 395.7 280ct2008, 20:05 6.09 Jct 1 0.0294 53.8 280ct2008, 19:50 6.01 Jct 2 0.0481 85.1 280ct2008, 19:45 6.14 Junction-1 0.0000 0.0 280ct2008, 13:00 Junction-2 0.0000 0.0 280ct2008, 13:00 Outfall 0.3150 392.7 280ct2008, 20:10 6.09 Pond1 0.3150 392.7 280ct2008, 20:10 6.09 Pond2A 0.2638 351.2 280ct2008, 20:10 6.00 Pond2B 0.0720 88.8 280ct2008, 20:10 6.43 Pond3 0.0294 52.1 280ct2008, 19:55 6.01 Pond4 0.0270 51.8 280ct2008, 19:50 5.94 Reach 1 10.0481 84.9 280ct2008, 19:45 6.14 Project: Meadow Creek Simulation Run: Post 100 yr 12 hr Start of Run: 280ct2008, 13:00 End of Run: 290ct2008, 13:15 Compute Time: 04Nov2008, 14:56:30 Basin Model: Post Dev Meteorologic Model: 100 yr 12 hr Control Specifications: 24 hr duration Volume Units: IN Hydrologic Element Drainage Area (M12) Peak Discharge (CFS) Time of Peak 401 0.0512 167.1 280ct2008, 19:20 402 0.1636 311.0 280ct2008, 19:55 403 0.0024 11.0 280ct2008, 19:10 404 0.0270 61.6 280ct2008, 19:40 1405 0.0187 53.2 280ct2008, 19:30 1406 0.0239 84.8 280ct2008, 19:20 407 0.0282 99.8 280ct2008, 19:20 Jct.3 0.0720 160.6 280ct2008, 19:30 Jct.4 0.2638 474.8 280ct2008, 19:55 Jct.5 0.3150 477.1 280ct2008, 20:05 Jct 1 0.0294 61.6 280ct2008, 19:50 Jct 2 0.0481 98.6 6 280ct2008, 19:40 Junction-1 0.0000 0.0 280ct2008, 13:00 Junction-2 0.0000 0.0 280ct2008, 13:00 Outfall 0.3150 472.6 280ct2008, 20:10 0.3150 472.6 280ct2008, 20:10 A F 0.2638 422.6 280ct2008, 20:10 Pond2B 0.0720 126. 6 280ct2008, 19:55 Pond3 0.0294 60.0 280ct2008, 19:55 Pond4 0.0270 59.2 280ct2008, 19:50 Reach 1 0.0481 98.5 280ct2008, 19.45 Volume (IN) 7.59 6.65 7.86 6.93 7.35 8.06 7.81 7.44 6.99 7.09 7.00 7.14 7.09 7.09 6.99 7.44 7.00 6.93 7.14 APPENDIX G Post-Development Pond Elevations for 100-yr Event From HEGHMS Output Data Project: Meadow Creek Simulation Run: Post 100 yr 12 hr Reservoir: Pond1 Start of Run: 280ct2008, 13:00 Basin Model: Post Dev End of Run: 290ct2008, 13:15 Meteorologic Model: 100 yr 12 hr Compute Time: 04Nov2008, 14:56:30 Control Specifications: 24 hr duration Volume Units: IN Computed Results Peak Inflow : 477.1 (CFS) Date/Time of Peak Inflow : 280ct2008, 20:05 Peak Outflow : 472.6 (CFS) Date/Time of Peak Outflow : 280ct2008, 20:10 Total Inflow : 7.09 (IN) Peak Storage : 6.0 (AC-FT) Total Outflow : 7.09 (IN) Peak Elevation : 299.6 (FT) Project: Meadow Creek Simulation Run: Post 100 yr 12 hr Reservoir: Pond2A Start of Run: 280ct2008, 13:00 Basin Model: Post Dev End of Run: 290ct2008, 13:15 Meteorologic Model: 100 yr 12 hr Compute Time: 04Nov2008, 14:56:30 Control Specifications: 24 hr duration Volume Units: IN Computed Results Peak Inflow : 474.8 (CFS) Date/Time of Peak Inflow : 280ct2008, 19:55 Peak Outflow : 422.6 (CFS) Date/Time of Peak Outflow : 280ct2008, 20:10 Total Inflow : 6.99 (IN) Peak Storage : 15.3 (AC-FT) Total Outflow : 6.99 (IN) Peak Elevation : 302.8 (FT) Project: Meadow Creek Sim ulation Run: Post 100 yr 12 hr Reservoir: Pond2B Start of Run: 280ct2008, 13:00 Basin Model: Post Dev End of Run: 290ct2008, 13:15 Meteorologic Model: 100 yr 12 hr Compute Time: 04Nov2008, 14:56:30 Control Specifications: 24 hr duration Volume Units: IN Computed Result s Peak Inflow : 160.6 (CFS) Date/Time of Peak Inflow : 280ct2008, 19:30 Peak Outflow : 126.6 (CFS) Date/Time of Peak Outflow : 280ct2008, 19:55 Total Inflow : 7.44 (IN) Peak Storage : 8.1 (AC-FT) Total Outflow : 7.44 (IN) Peak Elevation : 304.1 (FT) Project: Meadow Creek Simulation Run: Post 100 yr 12 hr Reservoir: Pond3 Start of Run: 280ct2008, 13:00 Basin Model: Post Dev End of Run: 290ct2008, 13:15 Meteorologic Model: 100 yr 12 hr Compute Time: 04Nov2008, 14:56:30 Control Specifications: 24 hr duration Volume Units: IN Computed Results Peak Inflow : 61.6 (CFS) Date/Time of Peak Inflow: 280ct2008, 19:50 Peak Outflow : 60.0 (CFS) Date/Time of Peak Outflow : 280ct2008, 19:55 Total Inflow : 7.00 (IN) Peak Storage : 0.9 (AC-FT) Total Outflow : 7.00 (IN) Peak Elevation : 312.0 (FT) Project: Meadow Creek Simulation Run: Post 100 yr 12 hr Reservoir: Pond4 Start of Run: 280ct2008, 13:00 Basin Model: Post Dev End of Run: 290ct2008, 13:15 Meteorologic Model: 100 yr 12 hr Compute Time: 04Nov2008, 14:56:30 Control Specifications: 24 hr duration Volume Units: IN Computed Results Peak Inflow : 61.6 (CFS) Date/Time of Peak Inflow : 280ct2008, 19:40 Peak Outflow : 59.2 (CFS) Date/Time of Peak Outflow : 280ct2008, 19:50 Total Inflow : 6.93 (IN) Peak Storage : 1.2 (AC-FT) Total Outflow : 6.93 (IN) Peak Elevation : 315.9 (FT) EXHIBIT A Drainage Area Map - Pre-Development EXHIBIT B Drainage Area Map - Post-Development, Pond Design EXHIBIT C Grading Plan - Sheet I of 2 EXHIBIT D Grading Plan - Sheet 2 of 2