July 29, 2002
TO: Greg Taggart, Municipal Development Group, Via fax 693-4243
FROM: Bridgette George, Assistant Development Manager
SUBJECT: CALLAWAY HOUSE PARKINGS (PP) - Preliminary Plat
Staff reviewed the above-mentioned preliminary plat as requested. The following page
is a list of staff review comments detailing items that need to be addressed. Please
address the comments and submit the following information by Monday, August 5,
10:00 a.m. to be placed on the next available Planning and Zoning Commission
meeting scheduled for August 15, 2002, 7:00 p.m. in the City Hall Council Chambers,
1101 Texas Avenue.
Ten (10) copies of the revised preliminary plat; and,
One (1) Mylar original of the revised preliminary plat.
One (1) copy of the digital file of the preliminary plat on diskette or e-mail
to nmanhart@ci.college-station.tx.us
Upon receipt of the required documents for the Planning & Zoning meeting, your project
will be considered formally filed with the City of College Station. If you have any
questions or need additional information, please call me at 764-3570.
Attachments: Staff review comments
cc: Michael Orsak, SHP Callaway Land, LP, Via fax 512-479-4067
Case file #02-00500157
Home of Texas A&M University
STAFF REVIEW COMMENTS NO. 1
Project: CALLAWAY HOUSE PARKINGS (PP) - (02-00500157)
PLANNING
1. Please show owner information in the Title Block
2. Please call out the (2-ft.) topography intervals.
Reviewed by: Jennifer Flanery/Jennifer Reeves Date: 07-29-02
ENGINEERING
1. Survey information is inaccurate. Please make all calls, distances and directions,
clear and accurate.
2. The Comprehensive Plan shows Marion Pugh as a Major Collector. ROW for a
Major Collector 70-ft. Due to the fact that the existing ROW is 60-ft, you will be
required to donate Y2 of the needed ROW.
Reviewed by: Spencer Thompson
Date: July 29, 2002
ELECTRICAL
1. Developer installs conduit as per city specs and design.
2. Developer pours transformer pad as per city specs and design.
3. Developer provides temp blanket easement for construction purposes.
4. Developer provides upon completion of project meets and bounds descriptive
easements for all electric lines.
5. Developer provides digital site plan in AutoCAD 2000i. Email site plan to
rbolin -ci.college-station.tx.us.
6. Developer load data for project.
Reviewed by: Ronnie Bolin Date:7-25-02
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
2 of 2
STAFF REVIEW COMMENTS NO. 2
Project: CALLAWAY HOUSE PARKINGS (PP) - 02-00500157
ENGINEERING
1. Show 6" water line along the front of the property.
Reviewed by: Jennifer Flanery Date: August 6, 2002
NOTE: Any changes made to the plans, that have not been requested by the City of College Station,
must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on
these plans that have not been pointed out to the City, will constitute a completely new review.
2 of 2
Commission Action Options: The Commission has final authority over the
preliminary plat. The options regarding the preliminary plat are:
■ Approval with conditions;
■ Approval as submitted;
■ Denial;
■ Defer action only at applicant's request; or,
■ Table only at applicant's request.
Supporting Materials:
1. Location Map
2. Application
3. Infrastructure and Facilities
4. Copy of Preliminary Plat
5. Section 7.17 District M-2 Heavy Industrial, College Station Zoning Ordinance
6. Staff Comments #2
INFRASTRUCTURE AND FACILITIES
Water required for plat: No, 6" water existing along frontage.
Water Service: Service will be taken from 6" main.
Sewer required for plat: No, sewer main along rear of property.
Sewer Service: Service will be taken from main in rear.
Street(s) required for plat: No, however Marion Pugh is shown on the
Thoroughfare Plan as a major collector requiring 70-ft of ROW. It
appears that there is 60-ft existing ROW. This plat requires an additional
5-ft of ROW dedication.
Streets/Access: The property fronts on and has access to Marion Pugh.
There exists a joint access easement with McDonalds. Any other access
to this property must meet the Driveway Ordinance.
Off-site Easements required for plat: None known at this time.
Drainage: A Development Permit is required for development of this
site. It appears the site could drain to the rear along the railroad ROW or
to the front into the City storm system.
Flood Plain: The property is not located within the 100-year flood plain.
Oversize request: None.
Impact Fees: None.
Parkland Dedication Fees: None, if developed as a parking lot. If the
site redevelops as "dwelling units", parkland would be required.