No. 1
Project:: EXXON AT DARTMOUTH CROSSING (C-N SITE/USE) (0-46)
1. Need to continue fence after walkway. (@ Heritage at Dartmouth)
2. Need to screen water/air station.
3. Only 28 non-canopy trees were found on landscape plan. Either place two
more non-canopy trees to meet proposed landscape points, or recalculate the
points.
4. The entire building is not encompassed in a 150' fire protection radius from
the end of the lay of hose point. Will either need to place an additional fire
hydrant or shift the driveway to meet the radius requirement.
5. Provide curb detail.
6. Provide aisle width from the fuel station canopy to the parking spaces.
7. Give width of the sidewalk located on the Dartmouth Drive side.
8. The access drive on Southwest Parkway may not have an aisle width greater
than 40'.
9. Please resubmit engineering and grading plans. These plans must be
approved before the issuance of a development permit.
Reviewed by: SHAUNA ANDERSON Date: 20-Mar-00
Staff Review Comments Page 1 of 1
STAFF REVIEW COMMENTS
No. 2
Project: EXXON AT DARTMOUTH CROSSING (C-N SITE/USE) (0-46)
1. Only 110 shrubs were found on the landscape plan. Either place one
more shrub to meet proposed landscape points, or recalculate the points.
2. Width of sidewalk on Dartmouth Drive scales to be 5' instead of noted 6'.
3. Waiting for approval from the Fire Marshal about proposed "lay of hose"
configuration.
4. Engineering is currently reviewing submitted engineering and grading
plans. These plans must be approved before the issuance of a
development permity.
Reviewed by: SHAUNA ANDERSON Date: 29-Mar-00
Staff Review Comments Page 1 of 1
STAFF REVIEW COMMENTS
No. 2
Project: EXXON AT DARTMOUTH CROSSING (C-N SITE/USE) (0-46)
1. Only 110 shrubs were found on the landscape plan. Either place one
more shrub to meet proposed landscape points, or recalculate the points.
2. Width of sidewalk on Dartmouth Drive scales to be 5' instead of noted 6'.
3. Waiting for approval from the Fire Marshal about proposed "lay of hose"
configuration.
4. Engineering is currently reviewing submitted engineering and grading
plans. These plans must be approved before the issuance of a
development permity.
Reviewed by: SHAUNA ANDERSON Date: 30-Mar-00
STAFF REVIEW COMMENTS
No. 2
Project: EXXON AT DARTMOUTH CROSSING (C-N SITE/USE) (0-46)
1. Only 110 shrubs were found on the landscape plan. Either place one
more shrub to meet proposed landscape points, or recalculate the points.
2. Width of sidewalk on Dartmouth Drive scales to be 5' instead of noted 6'.
3. The Fire Marshal has denied the proposed "lay of hose" configuration.
Will need to either shift the driveway or place a hydrant on Dartmouth
Drive.
4. Engineering is currently reviewing submitted engineering and grading
plans. These plans must be approved before the issuance of a
development permit.
Reviewed by: SHAUNA ANDERSON Date: 31-Mar-00
Staff Review Comments Page 1 of 1