HomeMy WebLinkAbout00072448DEVELOPMENT SERVICES
TRANSMITTAL LETTER
Name/Finn: jp e ►u-, +S; ��xGf�Vl
Address: 00 6 yi t h a m
Co O we T441 V4 . TX 7 ?94�
Date: // — //— ZlaDZ
Phone: 0
Fax:
We are transmitting the following for Development Services to review and comment: (Check all that apply.):
❑
Master Development Plan
w/ ❑
Redlines
❑ Development Permit App.
❑
Preliminary Plat
w/ ❑
Redlines
❑ Conditional Use Permit
Final Plat
w/ ❑
Redlines
❑ Rezoning Application
•
FEMA CLOMA/CLOMR/LOMA/LOMR
w/ ❑
Redlines
❑ Variance Request
•
Site Plan
w/ ❑
Redlines
❑ Other - Please specify
❑
❑ Grading Plan
w/ ❑
Redlines
❑ Landscape Plan
w/ ❑
Redlines
❑ Irrigation Plan
w/ ❑
Redlines
❑ Building Construction Documents w/ ❑ Redlines
INFRASTRUCTURE AND ENGINEERING DOCUMENTS
All infrastructure documents must be submitted as a complete set.
The following are included in the complete set:
LJ
Waterline Construction Documents
w/ ❑
Redlines
t
Sewerline Construction Documents
w/❑
Redlines
LJ
Drainage Construction Documents
w/ ❑
Redlines
Ef
Street Construction Documents
w/ ❑
Redlines
❑
Easement application with metes & bounds
decsription
Ef
Drainage Letter or Report w/ ❑
Redlines
❑
Fire Flow Analysis
w/ ❑
Redlines
a TXDOT Driveway Permit
❑ TxDOT Utility Permit
❑ Other - Please specify
Special Instructions:
�4 wd be �J)iy e a� o (akr_ -
TRANSMITTAL LETTER 1 of I
TRANSMIT.DOC 10/14/2002
TPACON
General Contractors
Div. of CDS Enterprises, Inc.
1707 Graham Rd. • College Station, TX 77845 • 979 - 690 -7711 • Fax: 979 - 690 -9797
December 12, 2002
Bridgette George
Asst. Development Coordinator
City of College Station
1101 Texas Avenue South
College Station, TX 77842
RE: Revised Construction Documents, Drainage Report & Estimate
Oxburgh Drive — Phase 1
College Station, Texas
Dear Ms. George:
Attached are two (2) copies each of the revised construction documents, revised drainage
report and the engineer's cost estimate for the above - mentioned project. Also attached
are two (2) copies of the revised Sheet 4 to be included with the TxDOT driveway permit
previously submitted.
If you have any questions or need additional information, please do not hesitate to give
me a call at (979) 690 -7711.
Sincerely Yours,
Joe Schultz, P.E.
Engineering Manager
3 p
Attachments
TEXCON GENERAL CONTRACTORS 12- Dec -02
CONSTRUCTION COST ESTIMATE
OXBURGH DRIVE, PHASE 1
COLLEGE STATION, TEXAS
Item
Storm Drainage
Estimated
Unit
Estimated
No.
Description
Quantity
LF
Price
Cost
17
Sitework
181
LF
$45.00
$8,145
1
Mobilization /Layout
1.0
LS
$10,000.00
$10,000
2
Site Preparation
2.0
AC
$3,000.00
$6,000
3
Topsoil Stripping & Replacement
1,220
CY
$4.50
$5,490
4
Excavation
3,660
CY
$3.50
$12,810
5
Lime Stabilized Subgrade
6,750
SY
$3.00
$20,250
6
Concrete Curb & Gutter (Standard)
2,080
LF
$8.00
$16,640
7
Base Material - 6" depth
5,770
SY
$6.00
$34,620
8
Asphalt Paving - 1 1/2" depth
5,770
SY
$5.00
$28,850
9
Concrete Apron
0
SF
$5.50
$0
10
ADA Ramp - regular
0
EA
$350.00
$0
11
ADA Ramp - corner
0
EA
$450.00
$0
12
Concrete Sidewalk - 4' wide
8,310
SF
$2.60
$21,606
13
Seeding & Hydromulch
5,000
SY
$0.50
$2,500
14
Silt Fence
1,177
LF
$2.50
$2,943
15
Construction Exit
30
TON
$40.00
$1
Subtotal $162,909
Subtotal $184,285
Storm Drainage
16
Drainage Pipe - 18" RCP - structural
58
LF
$38.00
$2,204
17
Drainage Pipe - 24" RCP - structural
181
LF
$45.00
$8,145
18
Drainage Pipe - 27" RCP - structural
452
LF
$48.00
$21,696
19
Inlets 5' wide / Junction boxes
2
EA
$2,400.00
$4,800
20
Inlets 10' wide
1
EA
$3,200.00
$3,200
21
Inlets 15' wide
1
EA
$3,600.00
$3,600
22
8'x4' Box Culvert
240
LF
$410.00
$98,400
23
Headwalls /wingwalls - triple 8'x4' box culvert
2
EA
$18,000.00
$36,000
24
24" Sloped End Sections
2
EA
$1,200.00
$2,400
25
Handrails
64
LF
$60.00
$3,840
Subtotal $184,285
Page 1 of 2
Water Lines
26
8" Water PVC CL200 (C900) structural
150
LF
$30.00
$4,500
27
12" Water PVC CL200 (C900) structural
945
LF
$42.00
$39,690
28
12" Water PVC CL200 (C900) non - structural
85
LF
$28.00
$2,380
29
24 "x12" Tapping Sleeve & Valve
1
EA
$6,000.00
$6,000
30
Gate Valves - 8"
2
EA
$600.00
$1,200
31
Gate Valves - 12"
2
EA
$1,500.00
$3,000
32
M.J. Tees - 12 "x8"
2
EA
$500.00
$1,000
33
M.J. Tees - 12" x 6"
1
EA
$500.00
$500
34
M.J. Bend - 12" 11.25 deg.
6
EA
$500.00
$3,000
35
2" Blow off Assembly
3
EA
$450.00
$1,350
36
Air release valve
1
EA
$2,800.00
$2,800
37
Fire Hydrant Assembly
1
EA
$2,200.00
$2,200
38
20" Steel Casing w/ Spacers and Seals
40
LF
$100.00
$4
Subtotal
$71,620
Page 1 of 2
TEXCON GENERAL CONTRACTORS 12- Dec -02
CONSTRUCTION COST ESTIMATE
OXBURGH DRIVE, PHASE 1
COLLEGE STATION, TEXAS
Sanitary Sewer Lines
Subtotal $0
Total Sitework $162,909
Total Storm Drainage $184,285
Total Water $71,620
Total Sanitary Sewer $0
TOTAL CONSTRUCTION $418,814
Engineering and Survey @ 6% $25,129
Contingency @ 5% $20,941
TOTAL $464,883
� PEE OF TE'A%���
. JOSEPH P
• NAL -m
Page 2 of 2
Drainage Report
for
Oxburgh Drive
Phase 1
College Station, Texas
November 2002
Revised December 2002
(Revisions in bold italics)
Developer:
Spring Creek CS Development, Ltd.
4490 Castlegate Drive
College Station, Texas 77845
(979) 690 -7250
Prepared BV:
TEXCON General Contractors
1707 Graham Road
College Station, Texas 77845
(979) 690 -7711
CERTIFICATION
I, Joseph P. Schultz, Licensed Professional Engineer No. 65889, State of Texas, certify that this
report for the drainage design for the Oxburgh Drive, Phase 1 (Revised), was prepared by me
in accordance with the provisions of the City of College Station Drainage Policy and Design
Standards for the owners hereof.
L b4c:5�
Gingca. Urso, P.E.
°a o
T
JOSE'N, P G 'ili...l
e ...65? 4U
(Z -1 2 -DZ
ff� ha
i
y
. f
TABLE OF CONTENTS
DRAINAGE REPORT - Revised
OXBURGH DRIVE — PHASE 1
CERTIFICATION.................................................................................................................................. ............................... I
TABLEOF CONTENTS ......................................................................................................................... ..............................2
LISTOF TABLES .................................................................................................................................... ..............................3
INTRODUCTION................................................................................................................................... ............................... 4
GENERALLOCATION AND DESCRIPTION .................................................................................. ............................... 4
FLOODHAZARD INFORMATION ..................................................................................................... ..............................4
DEVELOPMENTDRAINAGE PATTERNS ........................................................................................ ..............................4
DRAINAGEDESIGN CRITERIA ........................................................................................................ ............................... 4
STORM WATER RUNOFF DETERMINATION ............................................................................... ............................... 5
DETENTION FACILITY DESIGN ...................................................................................................... ............................... 6
STORMSEWER DESIGN ..................................................................................................................... ............................... 6
CULVERTDESIGN ............................................................................................................................... ............................... 7
FEMAFLOODPLAIN IMPACTS ........................................................................................................ ............................... 8
CONCLUSIONS...................................................................................................................................... ............................... 8
APPENDIXA .......................................................................................................................................... ............................... 9
Storm Sewer Inlet Design Calculations
APPENDIX ........................................................................................................................................... .............................11
Storm Sewer Pipe Design Calculations
APPENDIX .......................................................................................................................................... .............................16
Culvert Design Calculations
APPENDIX .......................................................................................................................................... .............................19
Drainage Area C2: Curve Number & Time of Concentration Calculations
EXHIBIT ............................................................................................................................................ ............................... 23
Post - Development Drainage Area Map — Culvert Design
EXHIBIT ............................................................................................................................................ ............................... 25
Post - Development Drainage Area Map — Storm Sewer Design
2
LIST OF TABLES
TABLE 1 — Rainfall Intensity Calculations ............................................................... ............................... 5
TABLE 2 — Post - Development Runoff Information — Storm Sewer Pipe Design Data .......................... 6
TABLE3 — Culvert No. 1 Design Data ..................................................................... ............................... 8
TABLE4 — Culvert No. 2 Design Data ..................................................................... ............................... 8
9
DRAINAGE REPORT - Revised
OXBURGH DRIVE — PHASE 1
INTRODUCTION
The purpose of this report is to provide the hydrological effects of the construction of Oxburgh
Drive — Phase 1, and to verify that the proposed storm drainage system meets the requirements
set forth by the City of College Station Drainage Policy and Design Standards.
GENERAL LOCATION AND DESCRIPTION
The project is located on a portion of a 62.18 acre tract located north of Greens Prairie Road
along the West Frontage Road of State Highway 6 in College Station, Texas. This report
addresses Oxburgh Drive, Phase 1, which is made up of 2.041 acres of the 62.18 acre tract.
The site is pastureland with approximately 30% of the area wooded. The existing ground
elevations range from elevation 261 to elevation 270. The general location of the project site is
shown on the vicinity map in Exhibit A.
FLOOD HAZARD INFORMATION
The project site is located in the Spring Creek branch of the Lick Creek Drainage Basin. The
site is located within a special flood hazard area according to the Flood Insurance Rate Map
prepared by the Federal Emergency Management Agency (FEMA) for Brazos County, Texas
and incorporated areas dated February 9, 2000, panel numbers 48041CO205 -D and
48041 CO201 -D. LJA Engineering & Surveying, Inc. submitted a Request for Conditional
Letter of Map Revision ( CLOMR) to FEMA to outline a proposed 100 -year floodplain area.
This CLOMR No. 00- 06 -844R was approved by FEMA on 9/9/2000. Oxburgh Drive passes
through this proposed floodplain.
DEVELOPMENT DRAINAGE PATTERNS
Prior to development, the runoff flows in a southerly direction until it enters a tributary of
Spring Creek or into the proposed regional detention facility.
DRAINAGE DESIGN CRITERIA
The design parameters for the storm sewer are as follows:
• The Rational Method is utilized to determine peak storm water runoff rates for the storm
sewer design. HEC -1 is used for Culvert No. 2 design.
Design Storm Frequency
Storm Sewer system
Culverts
10 and 100 -year storm events
25 and 100 -year storm events
• Runoff Coefficients
Pre - development
Post - development (commercial)
C = 0.30
C = 0.70
4
• Curve Numbers - CN
Refer to Appendix D for Curve Number calculations based on the soil
classification and land use.
Rainfall Intensity values for Brazos County for a minimum time of concentration of 10
minutes can be found in Table 1. Where a longer time of concentration was necessary, it is
noted in the respective table, and the intensities are calculated with the higher values where
required.
Time of Concentration, t, — Due to the small sizes of the drainage areas, the calculated
times of concentration, t, are less than 10 minutes. Therefore, a minimum t of 10 minutes
is used in most cases to determine the rainfall intensity values. Where a longer time of
concentration was necessary, it is noted and used accordingly. The time of concentration
calculations for Drainage Area C2 are located in Appendix D.
STORM WATER RUNOFF DETERMINATION
The peak runoff values were determined in accordance with the criteria presented in the
previous section for the 5, 10, 25, 50, and 100 -year storm events. The runoff coefficients are
based on the future development of this tract. The drainage areas for post - development are
shown on Exhibits A and B. Exhibit A shows the post- development drainage areas for the
design of Culverts No. 1 and No. 2. Due to the size of the watershed draining to Culvert No. 2,
the HEC -1 program was used to calculate the runoff for this structure. The runoff for the
design of Culvert No. 1 and the storm sewer system was determined using the Rational
Equation. Exhibit B shows the post - development drainage areas for the storm sewer design.
Post - development runoff conditions for the storm sewer design are summarized in Table 2.
TABLE 1 — Rainfall Intensity Calculations
Rainfall Intensity
Values (in /hr)
Storm
Event
t _
10 min
I S
7.693
1 10
8.635
1 25
9.861
1 50
11.148
1100
11.639
Brazos County:
5 year storm
b = 76
d = 8.5
e = 0.785
I = b / (t
I = Rainfall Intensity ( in /hr)
t = U(V *60)
t c = Time of concentration (min)
L = Length (ft)
V = Velocity (ft/sec)
10 year storm 25 year storm 50 year storm 100 year storm
b = 80 b = 89 b = 98 b = 96
d =8.5 d =8.5 d =8.5 d =8.0
e = 0.763 e = 0.754 e = 0.745 e = 0.730
(Data taken from State Department of Highways and Public Transportation Hydraulic Manual page 2 -16)
TABLE 2 - Post - Development Runoff Information - Storm Sewer Pipe Design Data
Area #
Area
C
tc
(min)
5 year storm
10 year storm
25 year storm
50 year storm
100 year storm
1 5
(in /hr)
Q5
(cfs)
1 10
(in /hr)
Q10
(cfs)
1 25
(in /hr)
Q25
(cfs)
1 50
(in /hr)
450
(cfs)
1 100
(in /hr)
4100
(cfs)
(acres)
19
0.26
0.7
10
7.693
1.40
8.635
1.57
9.861
1
1.79
11.148
2.03
11.639
2.12
20A
3.28
0.7
10
7.693
17.66
8.635
19.82
9.861
22.64
11.148
25.59
11.639
26.72
23
0.63
0.7
10
7.693
3.39
8.635
3.81
9.861
4.35
11.148
4.92
11.639
5.13
24
0.27
0.7
10
7.693
1.45
8.635
1.63
9.861
1.86
11.148
2.11
11.639
2.20
25
0.24
0.7
10
7.693
1.29
8.635
1.45
9.861
1.66
11.148
1.87
11.639
1.96
26
2.10
0.7
10
7.693
11.31
8.635
12.69
9.861
14.50
11.148
16.39
11.639
17.11
27
0.94
0.7
10
7.693
5.06
8.635
5.68
9.861
6.49
11.148
7.34
11.639
7.66
28
0.15
0.7
10
7.693
0.81
8.635
0.91
9.861
1.04
11.148
1.17
11.639
1.22
29
1 2.40
0.55
1 10
7.693
1 10.15
1 8.635
11.40
9.861
1 13.02
11.1481
14.71
1 11.6391
15.36
The Rational Method:
Q = CIA
Q = Flow (cfs)
A = Area (acres)
C = Runoff Coeff.
I = Rainfall Intensity (in /hr)
Brazos County
5 year storm
10 year storm
b = 76
b = 80
d = 8.5
d = 8.5
e = 0.785
e = 0.763
DETENTION FACILITY DESIGN
t = u(V *60)
L = Length (ft)
V = Velocity (ft/sec)
25 year storm 50 year storm
b =89 b =98
d = 8.5 d = 8.5
e = 0.754 e = 0.745
100 year storm
b = 96
d = 8.0
e = 0.730
The detention for this site is a regional facility designed by LJA Engineering & Surveying, Inc.
and was previously constructed adjacent to this project. The detention facility is located
adjacent to Spring Creek prior to Spring Creek entering the State Highway 6 right -of -way.
The location of this proposed detention facility is shown on Exhibit A. The runoff from this
project flows into the existing drainage channel constructed with the detention facility or into
the detention pond. The detention facility was designed to control the increased runoff from
the development of the Castlegate Subdivision and the Crowley Tract. Refer to the Request for
Conditional Letter of Map Revision (CLOMR) for details of the design of the detention facility.
STORM SEWER DESIGN
The storm sewer piping for this project has been selected to be Reinforced Concrete Pipe
(RCP) meeting the requirements of ASTM C -76, Class III pipe. The curb inlets will be cast -in-
place concrete.
Appendix A presents a summary of the storm sewer inlet design parameters and calculations.
The inlets were designed based on a 10 -year design storm. As per College Station guidelines,
the capacities of inlets in sump were reduced by 10% to allow for clogging.
Inlets for Oxburgh Drive were located to maintain a gutter flow depth of 7" or less. These
design depths will prevent the spread of water from reaching the crown of the road for the 10-
year storm event. The runoff intercepted by the proposed storm sewer inlets was calculated
using the following equations. The depth of flow in the gutter was determined by using the
Straight Crown Flow equation. The capacities for the inlets in sumps (Inlets 1 -4) were
calculated using the Inlets in Sumps, Weir Flow equation with a maximum allowable depth of
7" (5" gutter flow plus 2" gutter depression). The maximum depth of flow in the street gutter is
4.2" for the 10 -year storm event at Inlet No. 4. These equations and the resulting data are
summarized in Appendix A.
Appendix B presents a summary of the storm sewer pipe design parameters and calculations.
All pipes are 18" in diameter or larger. For pipes with 18" and 24" diameters, the cross -
sectional area is reduced by 25 %, as per College Station requirements. A summary of how this
was achieved is shown in Appendix B as well. The pipes for the storm sewer system were
designed based on the 10 -year storm event, and will also pass the 100 -year storm event without
any headwater. Based on the depth of flow in the street determined for the 100 -year storm
event, this runoff will be contained within the street right -of -way until it enters the storm sewer
system. As required by College Station, the velocity of flow in the storm sewer pipe system is
not lower than 2.5 feet per second, and it does not exceed 15 feet per second. As the data
shows, even during low flow conditions, the velocity in the pipes will exceed 2.5 feet per
second and prevent sediment build -up in the pipes. Appendix B contains a summary of the
Manning pipe calculations. A 24" RCP pipe stub is planned for under Oxburgh Drive for
draining future development of the townhouse tract. Flow calculations for this pipe will be
addressed in a future report.
CULVERT DESIGN
The culverts for this project have been selected to be either Reinforced Concrete Pipe for
Culvert No. 1 or Reinforced Concrete Precast Box Sections meeting the requirements of ASTM
C -789 for Culvert No. 2. The headwalls at either end of Culvert No. 2 will be cast -in -place
concrete. The safety end treatments at either end of Culvert No. 1 will be pre -cast sections.
Data used for designing Culvert Nos. 1 & 2 can be found in Tables 3 & 4, respectively. Three
8'x4' box sections were selected for Culvert No. 2 because this is the same size utilized for the
Proposed Culvert No. 4 in the CLOMR prepared by LJA Engineering, Inc. The slope of the
culvert has been revised from the 1% used in the CLOMR to 0.65 %, which is the slope of the
25' wide drainage channel in the detention facility construction drawings, also prepared by LJA
Engineering, Inc.
The culverts were designed to pass the runoff from the 25 -year storm event with the upstream
headwater at least 1 foot below the street top of curb. Culvert No. 1 passes the 25 -year and the
100 -year storm runoff without any headwater greater than the pipe diameter. Culvert No. 2 has
a headwater elevation of 265.8 for the 25 -year storm event and 266.3 for the 100 -year storm
event, both of which are more than 1 foot below the top of road elevation of 268.7. The 25-
year exit velocity for Culvert No. 1 is 7.2 fps, and the 25 -year exit velocity for Culvert No. 2 is
5.5 fps. The downstream headwall for Culvert No. 2 will have energy dissipaters. Refer to
Appendix C for the Manning's Equation and culvert calculator data for the culvert design.
7
FEMA FLOODPLAIN IMPACTS
The proposed street crossing of the 100 -year floodplain was anticipated and included in the
CLOMR. Culvert No. 2 is the same size and number of box sections as proposed in the
CLOMR. The impact to the floodplain was previously addressed in the CLOMR.
TABLE 3 — Culvert No. 1 Design Data
Area #
A
C
tc
5 year storm
10 year storm
25 year storm
50 year storm
100 year storm
I
Q5
110
Q10
1 25
Q25
Iw
Q50
1 100
Q+oo
(acres)
(min)
(in /hr)
(cfs)
(in/hr)
(cfs)
(in/hr)
(cfs)
(in/hr)
(cfs)
(in /hr)
(cfs)
29
2.40
1 0.55
10
7.693
1 10.2
8.635
1 11.4
9.861
13.0
11.148
14.7
11.639
15.4
The Rational Method:
Q = CIA
Q = Flow (cfs)
A = Area (acres)
C = Runoff Coeff.
I = Rainfall Intensity (in /hr)
Brazos County
I = b / (t
t = u(V-60)
t = Time of concentration (min)
L = Length (ft)
V = Velocity ftsec)
5 year storm 10 year storm 25
year storm
50 year storm 100 year storm
b =76 b =80
b =89
b =98 b =96
d =8.5 d =8.5
d =8.5
d =8.5 d =8.0
e = 0.785 e = 0.763
e = 0.754
e = 0.745 e = 0.730
1— 24" Reinforced Concrete Pipe (RCP) with Safety End Treatments
Length = 96', Slope = 0.9
FL in = 266.66
FL out = 265.80
Top of Road = 269.50
TABLE 4 — Culvert No. 2 Design Data
Drainage Area
Lag Time
SCS Curve Number, CN
No.
(acres)
(sq. mi.)
(hrs)
C -2
122.90
0.1920
0.22
80.9
HEC -1 Peak Runoff values:
Q25 = 524 cfs
Q100 = 682 cfs
3 — 8' (span) x 4' (rise) box culverts with headwalls & wingwalls
Length = 78.7'
FLin= 261.51
FL out = 261.00
Top of Road = 268.7'
CONCLUSIONS
The construction of this project will significantly increase the storm water runoff from this site.
The proposed storm sewer system and culverts should adequately control the runoff and release
it into the existing drainage channel. Also, the regional detention facility should adequately
reduce the peak post - development runoff to less than the pre - development runoff for the design
storm event. This will prevent any impact on the properties downstream of this project.
APPENDIX A
Storm Sewer Inlet Design Calculations
N
C
w+
V
d
� U
C
� d
0 a
V
J o0
M � �
O
C
v
N
V
r
N
m
M
T C C II
O O 11
O
O
O
O
�
N
G O ,C
04
O
u
�
I I M
m ''. r
-
H U
N
V",m
N
N'
C!
E
r
10
N
m
N
N
m
N
N
N
m
N '�. N
N M
O
0
N
V
I
�
N
O
T
MIN
m N
O
N
r M
N
C! V
M m
N
N
N M
o
N
M
r
N
r
m
_
v
O
M
o
m
M
0
M
0
M
N
6
m
N
'2
N
J
r
(,Pr
N
n
O
M
N
O
m
O
N
N
M
N N
N
V
E
q
M I o
O
fD
m
N
m
I
O
M
�
I
o
0
O
O
0
0
m
O
O o
m
O
M
W. O
q
0 1 <O
�
C7
N
'
V N
M
r
I
O
G w
Q>!7
mIM
Nl m
f0
N
O!O
m.
>
d
C
.E
o
y 0
V
�
p
m
N
�
m
N
M
Mir
(O N
O
O
M
O
N
m
D)
()
M
M
M
M
O
O
O
O
O
O
o
0
_
N
m
I
N
N
m
N
O O
O
N
O
O
O
M
a
E
e
�
'Q
y
m
o m
m N
N N
r m
NN
v
NIA-
W
M O
NN
C
LL Q
C
L
m
J
in
sc
d
C
N
M
R
V
NI C`7
_O
m II
C N
v O
O L
O
O 'X
� O
O
CO
O
O
II
N N
O '�
m �
C L
3 O
O
U 0
� L
o
N �
N
C
C
a
to
N
O
�_ ap
11 O
T O
T U O N
r � a
_ O
fn O Cn fa
U � 3
C N 0
L L
C7 C Cn T
J o0
M � �
O
o
u rn 5 �
LL
T C C II
O O 11
Q o w o f
U N
�
N
G O ,C
ET
0
u
�
�
N >
CY J
-
II II � 11
�
J JC7 >,E
NI C`7
_O
m II
C N
v O
O L
O
O 'X
� O
O
CO
O
O
II
N N
O '�
m �
C L
3 O
O
U 0
� L
o
N �
N
C
C
a
to
N
O
�_ ap
11 O
T O
T U O N
r � a
_ O
fn O Cn fa
U � 3
C N 0
L L
C7 C Cn T
APPENDIX B
Storm Sewer Pipe Design Calculations
11
N
N M
O
M
E
o
4
E
H
O
d
m
N
M W
fII
�
H
C
LL
V
6
a
N
£
\°
(O
00
(6 O
N
o C
CO
4
W
L6
to
�p
Q
Q
00
L
0
_m
ui
a
N
(B
�
O
O
O
O
LL
Ill
eD
(n
N
M
U
a
N
�
�
N
M
;
d
E
o
to i
N 0
N
°'
fn _
01
F
U)
_Q
N O
A
E
L
LL
o
o
LO cli
LL7
h
� L
Y
L
W
N
m
o f/!
a
O
v
I--
L6
o
d
LL y
M
rn
N
M
�
L
3
0
~ y
LL
m
co
N co
N
fl C
c h
N O M
N W
(�G
E_ d
`.
h
N
00
Co
O >
N
N
N
N
C
a
W crj
4)
W
N N
O () N
?� Q •�
!
h a
O N
_
c
N N
� o
M C Q D
W
(.) 0 0
ev
o o
°O
ai
t
N ,"
° I, °
� �' a
a
0�
U�
N
to
cp a
to
•�
N M �
N_ C
Oo N
`Fr
w
O
Q
N
> O m
Q
Lo
. 0
oa
a
* z
Pipe 14 - 10 Year Storm
Manning Pipe Calculator
Given Input Data:
Shape ...........................
Solving for .....................
Diameter ........................
Flowrate ........................
Slope ...........................
Manning's n .....................
Computed Results:
Depth ...........................
Area ............................
Wetted Area .....................
Wetted Perimeter ................
Perimeter .......................
Velocity ........................
Hydraulic Radius ................
Percent Full ....................
Full flow Flowrate ..............
Full flow velocity ..............
Circular
Depth of Flow
27.0000 in
17.3600 cfs
0.0050 ft /ft
0.0140
19.1867 in
3.9761 ft2
3.0219 ft2
54.1514 in
84.8230 in
5.7448 fps
8.0358 in
71.0620 %
20.3351 cfs
5.1144 fps
Pipe 14 - 100 Year Storm
Manning Pipe Calculator
Given Input Data:
Shape ............
Solving for ......
Diameter .........
Flowrate .........
Slope ............
Manning's n ......
Computed Results:
Depth ............
Area .............
Wetted Area ......
Wetted Perimeter .
Perimeter ........
Velocity .........
Hydraulic Radius .
Percent Full .....
Full flow Flowrate
Full flow velocity
Circular
Depth of Flow
27.0000 in
21.1800 cfs
0.0050 ft /ft
0.0140
23.2999 in
3.9761 ft2
3.6481 ft2
64.3454 in
84.8230 in
5.8058 fps
8.1641 in
86.2958%
20.3351 cfs
5.1144 fps
Oxburgh Drive, Phase 1
College Station, Texas
Pipe 15 - 10 Year Storm
Manning Pipe Calculator
Given Input Data:
Shape ............
Solving for ......
Diameter .........
Flowrate .........
Slope ............
Manning's n ......
Computed Results:
Depth ............
Area .............
Wetted Area ......
Wetted Perimeter .
Perimeter ........
Velocity .........
Hydraulic Radius .
Percent Full .....
Full flow Flowrate
Full flow velocity
Circular
Depth of Flow
18.0000 in
3.8100 cfs
0.0050 ft /ft
0.0140
9.5519 in
1.7671 ft2
0.9525 ft2
29.3787 in
56.5487 in
4.0000 fps
4.6687 in
53.0659 %
6.8971 cfs
3.9030 fps
Pipe 15 - 100 Year Storm
Manning Pipe Calculator
Given Input Data:
Shape ........................... Circular
Solving for ..................... Depth of Flow
Diameter ........................ 18.0000 in
Flowrate ........................ 5.1400 cfs
Slope ........................... 0.0050 ft /ft
Manning's n ..................... 0.0140
Computed Results:
Depth ........................... 11.5793 in
Area ............................ 1.7671 ft2
Wetted Area ..................... 1.2015 ft2
Wetted Perimeter ................ 33.5064 in
Perimeter ....................... 56.5487 in
Velocity ........................ 4.2779 fps
Hydraulic Radius ................ 5.1638 in
Percent Full .................... 64.3296 %
Full flow Flowrate .............. 6.8971 cfs
Full flow velocity .............. 3.9030 fps
Oxburgh Drive, Phase 1
College Station, Texas
APPENDIX C
Culvert Design Calculations
[L
Culvert No. 1 - 25 Year Storm
Manning Pipe Calculator
Given Input Data:
Shape .....
Solving for
Diameter .
Flowrate .
Slope .....
Manning's n
Circular
Depth of Flow
24.0000 in
13.0000 cfs
0.0090 ft /ft
0.0130
Computed Results:
Depth ............
Area .............
Wetted Area ......
Wetted Perimeter .
Perimeter ........
Velocity .........
Hydraulic Radius .
Percent Full .....
Full flow Flowrate
Full flow velocity
13.4785 in
3.1416 ft2
1.8166 ft2
40.6637 in
75.3982 in
7.1562 fps
6.4330 in
56.1606 %
21.4615 cfs
6.8314 fps
Culvert No. 1 - 100 Year Storm
Manning Pipe Calculator
Given Input Data:
Shape ........................... Circular
Solving for ..................... Depth of Flow
Diameter ........................ 24.0000 in
Flowrate ........................ 15.4000 cfs
Slope ........................... 0.0090 ft /ft
Manning's n ..................... 0.0130
Computed Results:
Depth ........................... 15.0442 in
Area ............................ 3.1416 ft2
Wetted Area ..................... 2.0727 ft2
Wetted Perimeter ................ 43.8547 in
Perimeter ....................... 75.3982 in
Velocity ........................ 7.4301 fps
Hydraulic Radius ................ 6.8057 in
Percent Full .................... 62.6840 %
Full flow Flowrate .............. 21.4615 cfs
Full flow velocity .............. 6.8314 fps
Oxburgh Drive, Phase 1
College Station, Texas
Culvert No. 2 - 25 Year Storm
Culvert Calculator
Entered Data:
Shape ...........................
Number of Barrels ...............
Solving for .....................
Chart Number ....................
Scale Number ....................
Chart Description ...............
Scale Description ...............
Overtopping .....................
Flowrate ........................
Manning's n .....................
Roadway Elevation ...............
Inlet Elevation .................
Outlet Elevation ................
Height ..........................
Width ...........................
Length ..........................
Entrance Loss ...................
Tailwater .......................
Rectangular
3
Headwater
9
2
BOX CULVERT WITH FLARED WINGWALL AND INLET TOP EDGE BEVEL
WINGWALL FLARED 18 TO 33.7 DEGREES; INLET TOP EDGE BEVEL = 0.083D
Off
524.0000 cfs
0.0140
268.7000 ft
261.5100 ft
261.0000 ft
48.0000 in
96.0000 in
78.7000 ft
0.4000
4.0000 ft
Computed Results:
Headwater .......................
Slope ...........................
Velocity ........................
265.7893 ft Outlet Control
0.0065 ft /ft
5.4583 fps
Culvert No. 2 - 100 Year Storm
Culvert Calculator
Entered Data:
Shape ...........................
Number of Barrels ...............
Solving for .....................
Chart Number ....................
Scale Number ....................
Chart Description ...............
Scale Description ...............
Overtopping .....................
Flowrate ........................
Manning's n .....................
Roadway Elevation ...............
Inlet Elevation .................
Outlet Elevation ................
Height ..........................
Width ...........................
Length ..........................
Entrance Loss ...................
Tailwater .......................
Rectangular
3
Headwater
9
2
BOX CULVERT WITH FLARED WINGWALL AND INLET TOP EDGE BEVEL
WINGWALL FLARED 18 TO 33.7 DEGREES; INLET TOP EDGE BEVEL = 0.083D
Off
682.0000 cfs
0.0140
268.7000 ft
261.5100 ft
261.0000 ft
48.0000 in
96.0000 in
78.7000 ft
0.4000
4.0000 ft
Computed Results:
Headwater .......................
Slope ...........................
Velocity ........................
266.3371 ft Outlet Control
0.0065 ft /ft
7.1042 fps
Oxburgh Drive, Phase 1
College Station, Texas
APPENDIX D
Drainage Area C2: Curve Number & Time of Concentration Calculations
19
SCS CURVE NUMBER CALCULATIONS
OXBURGH DRIVE - DRAINAGE AREA C -2
Area - Ac. 122.9
sq. mi. 0.1920
Land Use
Weighted
Area, Ac. CN II* CN
Residential -1/8 acre
3.49
92
2.6
Residential -1/4 acre
50.43
87
35.7
Farmstead
2.13
86
1.5
Commercial
6.78
95
5.2
Open Space /Grass
1.77
80
1.2
Pasture
27.63
83
18.7
Woods
29.62
79
19.0
Roads
1.05
98
0.8
Water
0.00
100
0.0
Total - CN II
* Type "D" Soils
122.90
84.7
Average Runoff Condition ** CN = 80.9
CN I = 69.4
ARC CN = CN I = 0.75(CN II -CN 1)
** Average Runoff Conditions per Texas Engineering Technical Note
No. 210- 18 -TX5 -SCS- USDA -March 1983.
N
C
O
r
_R
7
v
R
U
e
w
<o
C
d
V
C
0
U
0
O
d
E
H
�
C
0
z
d
it
7
U
N
U
m �
'C �
Q
s �
as �
� c
s
X
00
a
z
w
z
U
3
0
c
m
a�
0
d
N
c0
CL
(n
N
f0
O)
r
O
L
N
N
LO
N
R)
U-
_0
c
m
a�
a
y
C
(9
C
O
N
m
3 a
O C6
o �
N T
a O
N _
7 N
d >
E 3
U 0
N II
E_>
(D N
> L
m 3
F �
00
C�
-O J
c II
m F
d > ~
O
a
U)
C
a
m
N U?
3
O 11
_o u
N d
(0 -O
- O C
N N
7 Q
E C7
O II
U >
N N
E
~ L
a� 3
m
o
O J
LL ..
25 r
C�
N
�.5
FIGURE 1
• N
+
'—a
1
rr
►-t
I I�
O
�
j i I � i S\ 1 9� 3
\
i -,•^^. — J.� ;\ i'
i
1
f tii..J i �:,
• � � I 4 i . c r� -+. —f � i i I j �
�
� I i ..�.
4 �
7
l I
e E ; "� - --1 `
j l l i � � � E j I S r I '• r
+� �
C--)v
w
LL-
• i
=
i..i
EXHIBIT A
Post - Development Drainage Area Map — Culvert Design
23
EXHIBIT B
Post - Development Drainage Area Map — Storm Sewer Design
W