HomeMy WebLinkAbout00071548STAFF REVIEW COMMENTS NO. 1
Project: MCALISTERS DELI-SITE PLAN (1-500219)
PLANNING
1. Please show water meter location. Please show water and sewer demands by
which your meter will be sized by Staff. An irrigation estimation must be made as
well for meter sizing.
2. Please label fire hydrant; show as proposed or existing as well.
3. Please see buffer ordinance section 8.10 of Zoning Ordinance. The buffer
requirement for this piece of property will require a 5 ft. buffer with the required
landscaping installed on three sides of this site. Please be aware that the required
landscaping in these buffer areas cannot count toward your site's landscape
requirement. Staff did a cursory review of the landscaping that could count toward
your landscaping. You show 1569 points required for this site and staff counted
1470 points that could count toward your landscaping point calculation.
4. Signs are to be permitted separately.
Reviewed by: Jennifer Reeves Date: 10/03/01
ENGINEERING
1. Please call out fittings to be used on Public waterline (2-tees, 1/4 bend and meter).
Reviewed by: Spencer Thompson Date: October 4, 2001
ELECTRICAL
1. Developer installs conduit per city specs and design.
2. Developer pours transformer pad per city specs and design.
3. Developer installs pull boxes as per city specs and design.(pull boxes
provided by the city).
4. Developer provides digital AutoCAD 14 version of plat and/or site plan.
email to rbolin _ci.college-station.tx.us
5. Developer provides load data for project.
6. Developer provides temporary blanket easement for construction
purposes.
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
Staff Review Comments Page 2 of 4
JAPZTEXT\SR1.D0C
7. Developer provides easements for electric infrastructure as installed for
electric lines (including street lights).
Reviewed by: Ronnie Bolin Date:10/01 /01
MISCELLANEOUS
1. Irrigation system must be protected by either a Pressure Vacuum Breaker or
Reduced Pressure Principle Back Flow Device and installed as per City Ordinance
2394.
2. All BackFlow devises must be installed and tested upon installation as per City
Ordinance 2394.
Reviewed by: Rob Werley
SANITATION:
1. Shows a pad 25 feet by 9 feet for a 30 yard roll-off compactor. These are the
dimensions of the unit itself. It will need to be 29 feet by 16 feet 6 inches in order to
allow the restaurant personnel access to load it (it loads from the side) and for the
truck to be able to fit in the gates.
Reviewed by: Pete Caler Date: 10/02/01
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
Staff Review Comments Page 3 of 4
J:\PZTEXT\SR1.DOC