HomeMy WebLinkAbout00071300Drozd Subdivision
Probable Cost Estimate
Public Improvements
PUBLIC IMPROVEMENTS
N 0.
1
DESCRIPTION
24"x 12" Ta in Sleeve & Valve
UNIT
EA
QTY.
1
UNIT COST
$3,000.00
TOTAL COST
$3,000.00
2
12" PVC Waterline pipe
LF
208
$55.00
$11,440.00
3
12" 45 Bend
EA
2
$350.00
$700.00
4
Standard Fire Hydrant Assembly
EA
1
$3,000.00
$3,000.00
5
Reve etation in Row
LS
1
$200.00
$200.00
6
Standard 4' Sanita Sewer Manhole in lace
EA
1
$2,500.00
$2,500.00
7
24" RCP
LF
33
$45.00
$1,485.00
8
Precast Safte End Treatment
EA
1
$2,000.00
$2,000.00
9
Double Precast Safte End Treatment
EA
1
$2,500.00
$2,500.00
10
Stone Rip Rap
SY
14
$34.00
$476.00
Traffic Control
1
1/2" As halt Pavement
120
1 $b.00
$720
13
6" Cement Stabilized Crushed Limestone Base
120
14
1 Curb & Gutter
100
1 $lU.UU
$1,000.00
ESTIMATED CONSTRUCTION COST $56,931.00
Contingency (15%) $8,539.65
TOTAL CONSTRUCTION COST $65,470.65
NOTES CONCERNING OPINIONS OF PROBABLE CONSTRUCTION COST
Urban Design Group's (UDG) opinions of probable construction cost provided for herein are made
on the basis of our experience and qualifications and represent our best judgment as an experienced
and qualified professional engineering firm generally familiar with the construction industry and
applicable development regulations. However, since UDG has not obtained approval from the
appropriate jurisdiction and UDG has no control over the cost of labor, materials, equipment or
services furnished by others, or over the Contractor's methods of determining prices, or over
competitive bidding or market conditions, UDG cannot and does not guarantee that proposals,
bids or actual construction cost will not vary from opinions of probable construction cost prepared
by UDG.
1ofI
Drozd Subdivision
Probable Cost Estimate
Public Improvements
PUBLIC IMPROVEMENTS
•
1
•
N
24" x 12" Tapping Sleeve & Valve
'UNIT
EA
•
1
UNIT COST
$3,000.00
TOTAL COST
$3,000.00
2
12" PVC Waterline pipe
LF
208
$55.00
$11,440.00
3
12" 45 Bend
EA
2
$350.00
$700.00
4
Standard Fire Hydrant Assembly
EA
1
$3,000.00
$3,000.00
5
Reve etation in Row
LS
1
$200.00
$200.00
6
Standard 4' Sanitary Sewer Manhole in lace)
EA
1
$2,500.00
$2,500.00
7
24" RCP
LF
s33
$45.00
$1,485.00
8
Precast Safte End Treatment
EA
1
$2,000.00
$2,000.00
9
Double Precast Safte End Treatment
EA
1
$2,500.00
$2,500.00
10
Stone Rip Rap
SY
` 14
$34.00
$476.00
Traffic Control
L
1
1/2" Asphalt Pavement
` 120
$6.00
$720.707T
6" Cement Stabilized Crushed Limestone Base
-
120
-
14
Curb & Gutter
17
-100
$10. 07
$1,007.7m
ESTIMATED CONSTRUCTION COST $56,931.00
Contingency (15%Q) $8,539.65
TOTAL CONSTRUCTION COST 165.470.65
NOTES CONCERNING OPINIONS OF PROBABLE CONSTRUCTION COST
Urban Design Group's (UDG) opinions of probable construction cost provided for herein are made
on the basis of our experience and qualifications and represent our best judgment as an experienced
and qualified professional engineering firm generally familiar with the construction industry and
applicable development regulations. However, since UDG has not obtained approval from the
appropriate jurisdiction and UDG has no control over the cost of labor, materials, equipment or
services furnished by others, or over the Contractor's methods of determining prices, or over
competitive bidding or market conditions, UDG cannot and does not guarantee that proposals,
bids or actual construction cost will not vary from opinions of probable construction cost prepared
by UDG.
1 of 1