HomeMy WebLinkAbout00071300Drozd Subdivision Probable Cost Estimate Public Improvements PUBLIC IMPROVEMENTS N 0. 1 DESCRIPTION 24"x 12" Ta in Sleeve & Valve UNIT EA QTY. 1 UNIT COST $3,000.00 TOTAL COST $3,000.00 2 12" PVC Waterline pipe LF 208 $55.00 $11,440.00 3 12" 45 Bend EA 2 $350.00 $700.00 4 Standard Fire Hydrant Assembly EA 1 $3,000.00 $3,000.00 5 Reve etation in Row LS 1 $200.00 $200.00 6 Standard 4' Sanita Sewer Manhole in lace EA 1 $2,500.00 $2,500.00 7 24" RCP LF 33 $45.00 $1,485.00 8 Precast Safte End Treatment EA 1 $2,000.00 $2,000.00 9 Double Precast Safte End Treatment EA 1 $2,500.00 $2,500.00 10 Stone Rip Rap SY 14 $34.00 $476.00 Traffic Control 1 1/2" As halt Pavement 120 1 $b.00 $720 13 6" Cement Stabilized Crushed Limestone Base 120 14 1 Curb & Gutter 100 1 $lU.UU $1,000.00 ESTIMATED CONSTRUCTION COST $56,931.00 Contingency (15%) $8,539.65 TOTAL CONSTRUCTION COST $65,470.65 NOTES CONCERNING OPINIONS OF PROBABLE CONSTRUCTION COST Urban Design Group's (UDG) opinions of probable construction cost provided for herein are made on the basis of our experience and qualifications and represent our best judgment as an experienced and qualified professional engineering firm generally familiar with the construction industry and applicable development regulations. However, since UDG has not obtained approval from the appropriate jurisdiction and UDG has no control over the cost of labor, materials, equipment or services furnished by others, or over the Contractor's methods of determining prices, or over competitive bidding or market conditions, UDG cannot and does not guarantee that proposals, bids or actual construction cost will not vary from opinions of probable construction cost prepared by UDG. 1ofI Drozd Subdivision Probable Cost Estimate Public Improvements PUBLIC IMPROVEMENTS • 1 • N 24" x 12" Tapping Sleeve & Valve 'UNIT EA • 1 UNIT COST $3,000.00 TOTAL COST $3,000.00 2 12" PVC Waterline pipe LF 208 $55.00 $11,440.00 3 12" 45 Bend EA 2 $350.00 $700.00 4 Standard Fire Hydrant Assembly EA 1 $3,000.00 $3,000.00 5 Reve etation in Row LS 1 $200.00 $200.00 6 Standard 4' Sanitary Sewer Manhole in lace) EA 1 $2,500.00 $2,500.00 7 24" RCP LF s33 $45.00 $1,485.00 8 Precast Safte End Treatment EA 1 $2,000.00 $2,000.00 9 Double Precast Safte End Treatment EA 1 $2,500.00 $2,500.00 10 Stone Rip Rap SY ` 14 $34.00 $476.00 Traffic Control L 1 1/2" Asphalt Pavement ` 120 $6.00 $720.707T 6" Cement Stabilized Crushed Limestone Base - 120 - 14 Curb & Gutter 17 -100 $10. 07 $1,007.7m ESTIMATED CONSTRUCTION COST $56,931.00 Contingency (15%Q) $8,539.65 TOTAL CONSTRUCTION COST 165.470.65 NOTES CONCERNING OPINIONS OF PROBABLE CONSTRUCTION COST Urban Design Group's (UDG) opinions of probable construction cost provided for herein are made on the basis of our experience and qualifications and represent our best judgment as an experienced and qualified professional engineering firm generally familiar with the construction industry and applicable development regulations. However, since UDG has not obtained approval from the appropriate jurisdiction and UDG has no control over the cost of labor, materials, equipment or services furnished by others, or over the Contractor's methods of determining prices, or over competitive bidding or market conditions, UDG cannot and does not guarantee that proposals, bids or actual construction cost will not vary from opinions of probable construction cost prepared by UDG. 1 of 1