Project: DALIN'S DONUTS - SITE PLAN (01 -59)
9. Landscaping is required for the area of the site that is being newly developed.
This site will require the minimum number of points which is 500. Existing
canopy and non - canopy trees on site can count toward the requirement if
they are properly barricaded.
10. Clearly delineate existing vs. proposed paving.
11. All proposed paving must meet current standards, including but not limited to,
materials, design spec's, width and curbing requirements.
12. Although the proposed curb cut onto Hensel Dr. appears to meet the City's
Driveway Ordinance, the City does not have the authority to permit a curb cut
onto TAMU property. After checking the City's records, it was determined that
we do not currently maintain Hensel Dr. Your letter dated 1983 from TAMU,
therefore appears to be out of date, and we advise you to contact TAMU for
more current information.
STAFF REVIEW COMMENTS NO. 1
1. Provide a vicinity map.
2. Provide the legal description of the property.
3. This property is not in the floodplain. Please annotate this with the reference
note, "This property is not in the floodplain according to FEMA Map #
48041 C01 42C, effective date July 2, 1992 ".
4. Are there any easements on the property? If yes, show them on the plan.
5. Please be aware that signs will be permitted separately.
6. Provide a parking requirement legend. The requirement for a restaurant with
a drive -thru is 1 parking space to every 100 sq. feet of building. By adding
the drive -thru you will now meet the parking space requirement. It appears
that the construction and layout of the parking may still be legally
nonconforming, if the following concern can be addressed.
7. The current configuration of the parking blocks circulation through the drive -
thru. This is a safety hazard and will need to be addressed.
8. What is the current sanitation service? Will it be changing? If a dumpster is
required instead of rollout garbage cans, then a dumpster pad will need to be
installed that is accessible to the sanitation trucks.
Reviewed by:
Jessica Jimmerson
Date: 3 -19 -01
ENGINEERING
1. As mentioned previously, the Drainage Letter is approved.
Reviewed by: Thomas V. Vennochi Jr. Date: 3 -14 -01
J: \PZTEXT\PZ04482.DOC Page 1 of 1
STAFF REVIEW COMMENTS
No. 2
Project: DALIN'S DONUTS - SITE PLAN (01 -59)
PLANNING
1. Provide a vicinity map. This should be on the site plan.
2. Provide the legal description of the property. This should be on the site
plan.
3. This property is not in the floodplain. Please annotate this with the reference
note, "This property is not in the floodplain according to FEMA Map #
48041 C0142C, effective date July 2, 1992 ". This should be noted on the
site plan.
4. okay
5. okay
6. Provide a parking requirement legend. The requirement for a restaurant with
a drive -thru is 1 parking space to every 100 sq. feet of building. By adding
the drive -thru you will now meet the parking space requirement. It appears
that the construction and layout of the parking may still be legally
nonconforming, if the following concern can be addressed.
This should be on the site plan, in a manner similar to the following.
Required parking 1 space:100 sf of building
XXX square feet /100 = XXX spaces required
XXX spaces provided
7. The current configuration of the parking blocks circulation through the drive -
thru. This is a safety hazard and will need to be addressed. We will need to
see your proposal accurately depicted on the site plan, with
dimensions, to detemine the safety and if it affects the grandfathered
parking spaces in the front.
8. okay '
9. Landscaping is required for the area of the site that is being newly developed.
This site will require the minimum number of points which is 500. Existing
canopy and non - canopy trees on site can count toward the requirement if
they are properly barricaded. Additional information is needed for the
landscaping. What kind of trees are they? Canopy vs. Non - canopy?
What is the circumference of the trunks, so that we can determine how
many points they count for under our landscaping ordinance? For
every inch of circumference the required barricade must be one foot
away from the trunk. Ex. An 8 -in. tree would need to have barricading 8
feet away from the truck. The land cannot be disturbed within the
barricade by any means, other than hand clearing, during construction.
The barricades must be up before any construction begins on site.
Staff Review Comments Page 1 of 1
10. Clearly delineate existing vs. proposed paving. This should be on the site
plan.
11.All proposed paving must meet current standards, including but not limited to,
materials, design spec's, width and curbing requirements. Curbing is
required around all pavement sections as part of the zoning ordinance.
Curbing is not a drainage issue. In rare instances, where curbing would
be detrimental to the drainage of a site, variances may have been
granted allowing segmented curbing, which would allow drainage and
still function as a curb. As you stated in your comment, this exception
does not apply to your site. We also need pavement and curbing
specifications shown on the plan, which meet our paving and curbing
requirements. The areas to be paved need to be shown to scale on the
site plan showing that they are planned to meet our circulation aisle
width of 20 feet.
12. Although the proposed curb cut onto Hensel Dr. appears to meet the City's
Driveway Ordinance, the City does not have the authority to permit a curb cut
onto TAMU property. After checking the City's records, it was determined that
we do not currently maintain Hensel Dr. Your letter dated 1983 from TAMU,
therefore appears to be out of date, and we advise you to contact TAMU for
more current information. Although the proposed curb cut does meet the
City's Driveway Ordinance, permission to construct it must be granted
by TAMU.
Reviewed by: JESSICA JIMMERSON Date: 4 -5 -01
NOTE: Any changes made to the plans, that have not been requested by the
City of College Station, must be explained in your next transmittal letter and
"bubbled" on your plans. Any additional changes on these plans that have not
been pointed out to the City, will constitute a completely new review.
Staff Review Comments Page 2 of 1
PROVIDE LANDSCAPING LEGEND. RECEIVING BARRICADED TREE
POINTS IS NOT POSSIBLE NOW, SINCE WORK HAS TAKEN PLACE ON
SITE WITH OUT TREE BARRICADES IN PLACE.
10. okay
11. All proposed paving must meet current standards, including but not limited to,
materials, design spec's, width and curbing requirements. Curbing is
required around all pavement sections as part of the zoning ordinance.
Curbing is not a drainage issue. In rare instances, where curbing would
be detrimental to the drainage of a site, variances may have been
granted allowing segmented curbing, which would allow drainage and
still function as a curb. As you stated in your comment, this exception
does not apply to your site. We also need pavement and curbing
specifications shown on the plan, which meet our paving and curbing
requirements. The areas to be paved need to be shown to scale on the
site plan showing that they are planned to meet our circulation aisle
width of 20 feet. THE SITE PLAN WILL NOT BE APPROVED
UNTIL THIS ISSUE IS ADDRESSED. IF YOU WANT TO PURSUE A
o VARIANCE TO NOT REQUIRE THE CURBING YOU MUST GO TO THE
ZONING BOARD OF ADJUSTMENT (ZBA). STAFF WOULD BE HAPPY TO
TALK TO YOU ABOUT HOW THIS PROCESS WORKS, HOWEVER
PLEASE BE AWARE THAT STAFF WILL NOT BE SUPPORTING A
. VARIANCE. SHOW THE PAVING DESIGN SPECIFICATIONS ON THE
SITE PLAN.
k 12. This comment was just an FYI to you.
L3'REMOVE THE ENGINEER'S SEAL FROM THE PLAN, IF YOU HAVE
ALTERED IT IN ANY WAY SINCE IT WAS SEALED.
�HE SCALE SHOULD BE A STANDARD ENGINEERING SCALE, I.E. 1 :10,
1:20,1:30, ETC.
Reviewed by: JESSICA JIMMERSON Date: 4 -24 -01
NOTE: Any changes made to the plans, that have not been requested by the
City of College Station, must be explained in your next transmittal letter and
"bubbled" on your plans. Any additional changes on these plans that have not
been pointed out to the City, will constitute a completely new review.
JAPZTEXT\PZ04724.D0C Page 2 of 1
i loo ctt�'
STAFF REVIEW COMMENTS
No. 3
Project: DALIN'S DONUTS - SITE PLAN (01 -59)
PLANNING
1. okay
2. okay
3. okay
4. okay
5. okay
L, f.- Provide a parking requirement legend. The requirement for a restaurant with
a drive -thru is 1 parking space to every 100 sq. feet of building. By adding
the drive -thru you will now meet the parking space requirement. It appears
that the construction and layout of the parking may still be legally
nonconforming, if the following concern can be addressed.
This should be on the site plan, in a manner similar to the following.
Required parking 1 space:100 sf of building
XXX square feet /100 = XXX spaces required
XXX spaces provided
PROVIDE PARKING LEGEND ON THE SITE PLAN.
7. The current configuration of the parking blocks circulation through the drive -
thru. This is a safety hazard and will need to be addressed. We will need to
see your proposal accurately depicted on the site plan, with
dimensions, to detemine the safety and if it affects the grandfathered
parking spaces in the front. PROVIDE DIMENSIONS FOR THE
DRIVE -THRU. THE DIMENSION SHOULD BE UNIFORM AROUND THE
DRIVE -THRU. IT IS STAFF'S UNDERSTANDING THAT EDGES OF THE
SIDEWALK ALONG THE FRONT OF THE BUILDING HAVE ALSO BE
ALTERED TO HELP ACCOMMODATE THE DRIVE -THRU, ACCURATELY
DEPICT THAT ALTERATION.
8. okay
Landscaping is required for the area of the site that is being newly developed.
This site will require the minimum number of points which is 500. Existing
canopy and non - canopy trees on site can count toward the requirement if
they are properly barricaded. Additional information is needed for the
landscaping. What kind of trees are they? Canopy vs. Non - canopy?
What is the circumference of the trunks, so that we can determine how
many points they count for under our landscaping ordinance? For
every inch of circumference the required barricade must be one foot
away from the trunk. Ex. An 8 -in. tree would need to have barricading 8
feet away from the truck. The land cannot be disturbed within the
barricade by any means, other than hand clearing, during construction.
The barricades must be up before any construction begins on site.
J: \PZTEXT\PZ04724.DOC Page 1 of 1
STAFF REVIEW COMMENTS
No. 4
Project: DALIN'S DONUTS - SITE PLAN (01 -59)
PLANNING
11. All proposed paving must meet current standards, including but not limited to,
materials, design spec's, width and curbing requirements. Curbing is required
around all pavement sections as part of the zoning ordinance. Curbing is not
a drainage issue. In rare instances, where curbing would be detrimental to the
drainage of a site, variances may have been granted allowing segmented
curbing, which would allow drainage and still function as a curb. As you
stated in your comment, this exception does not apply to your site. We also
need pavement and curbing specifications shown on the plan, which meet our
paving and curbing requirements. The areas to be paved need to be shown to
scale on the site plan showing that they are planned to meet our circulation
aisle width of 20 feet. THE SITE PLAN WILL NOT BE APPROVED
UNTIL THIS ISSUE IS ADDRESSED. IF YOU WANT TO PURSUE A VARIANCE
TO NOT REQUIRE THE CURBING YOU MUST GO TO THE ZONING BOARD OF
ADJUSTMENT (ZBA). STAFF WOULD BE HAPPY TO TALK TO YOU ABOUT
HOW THIS PROCESS WORKS, HOWEVER PLEASE BE AWARE THAT STAFF
WILL NOT BE SUPPORTING A VARIANCE. SHOW THE PAVING DESIGN
,� SPECIFICATIONS ON THE SITE PLAN. Please be aware that the curbing will
`J be required to be installed before a Certificate of Occupancy will be issued for the
building. If the entire length of the drive -thru will not be 20 feet wide, then it will need
°z to marked as one way only. The minimum width of a one way drive aisle is 10 feet.
The driveway onto Hensel may be two -way. Per a discussion with Jane Kee, we still
o need to receive a letter from the contractor certifying that the pavement has been
installed to the City's paving requirements.
�4.THE SCALE SHOULD BE A STANDARD ENGINEERING SCALE, I.E. 1:10, 1:20,
U 1:30, ETC. Since the plan is not drawn to scale remove the reference to scale.
Reviewed by: JESSICA JIMMERSON Date: 4 -26 -01
NOTE: Any changes made to the plans, that have not been requested by the City of
College Station, must be explained in your next transmittal letter and "bubbled" on your
plans. Any additional changes on these plans that have not been pointed out to the City,
will constitute a completely new review.
C ) C "m rte"
Ll
- r'.
JAPZTEXT\PZ04745.D0C Page 1 of 1