Staff reviewed the above - mentioned final plat as requested. The following page is a list of
staff review comments detailing items that need to be addressed. Please address the
comments and submit the following information by Monday, January 28, 10:00 a.m. to be
placed on the next available Planning and Zoning Commission meeting scheduled for
February 7, 2002, 7:00 p.m. in the City Hall Council Chambers, 1101 Texas Avenue.
Ten (10) copies of the revised final plat; and,
One (1) Mylar original of the revised final plat with the appropriate signatures.
One (1) copy of the digital file of the final plat on diskette or e-mail to
nmanhart @ci .college - station.tx.us
If you have any questions or need additional information, please call me at 764 -3570.
Attachments: Staff review comments
cc: Pebble Creek Development, Via fax 690 -6081
Ryan Virden, Via fax 254 -776 -2924
Case file #2- 500007
Home of Texas A &M University
STAFF REVIEW COMMENTS NO. 1
Project: PEBBLECREEK, PH 713-1 (FP) -FINAL PLAT (2- 500007)
ENGINEERING
FiDal Plat
X. Note- lower left corner- No. 48041 CO205 . Date of February 09, 2000
,2' 20' off -site PUE- will need evidence of filing before plat is filed
Signature block- Pebble Creek Dev. Corp. -Phase 7 -131 not 9 -A
—4. Please add 100 year flood plain along the south side- see sheet 20 of plans
Construction Documents
1.Cover sheet: Index- Sheets 6 -8 are Whistling Straits Drive; Sheet 9 is Piping Rock Circle.
2. Sheet 1: Final Plat is different from plat submitted for approval, ie, 22.83 vs 22.99 acres,
etc.
3. Sheet 3: Is fire hydrant at northwest corner of Royal Adelade Drive and Whistling Straits
Drive existing or proposed?
4. Sheets 9, 10, and 11: Add typical cross - section for outlet channel.
5. Sheet 16: Manhole at STA 15 +63.35- Label drop manhole.
6. Sheet 19: Mission Hills Drive should be Whistling Straits Drive.
7. Sheet 22: Erosion Control- need detail for silt fencing and need to show silt fencing on
the down slope of any areas that are to be substantially disturbed by clearing and
construction.
8. Need to add specifications and details for trench safety.
9. Sheet 31- Electrical is missing.
Drainage Analysis: OK
Reviewed by: Ted Mayo Date: 01 /18/02
ELECTRICAL
1. Developer installs conduit as per city specs and design.
2. Developer installs street lighting as per city specs and design.
3. Developer provides temporary blanket easement for construction
purposes.
4. Developer provides digital of plat and/or site plan for AutoCAD 14. Email
to rbolin(cDci .college - station.tx.us
5. Developer provides easements for electric infrastructure as installed
(including street lighting).
6. Upon completion of project surveyed sealed meets and bounds
descriptive easements are necessary to release temporary blanket
easement.
Reviewed by: Ronnie Bolin Date: 1 -17 -02
NOTE: Any changes made to the plans, that have not been requested by the City of College Station,
must be explained in your next transmittal letter and "bubbled" on your plans. Any additional
changes on these plans that have not been pointed out to the City, will constitute a completely
new review.
2of2
FAX COVER PAGE
Date: Wednesday, January 23, 2002 Time: 2:46 PM
To: Davis Young
Fax Phone: 6906081
From: Bridgette George
Title: Assistant Development Manager
Company: City of College Station
Address: 1101 Texas Ave
College Station, TX 77840
Fax Phone: 979 - 764 -3496
Phone: 979 - 764 -3570
Subject: Pebble Creek 713-1
Message:
3 pages including cover
ATTN: Ryan Virden
Ryan, the tax certificates for 7B -1 will suffice for 713-2.
Bridgette
STAFF REVIEW COMMENTS NO. 1
Project: PEBBLECREEK, PH 76 -1 (FP) -FINAL PLAT (2- 500007)
ENGINEERING
Final Plat
Note- lower left corner- No. 48041 CO205 Date of February 09, 2000
2: 20' off -site PUE- will need evidence of filing before plat is filed
.Signature block- Pebble Creek Dev. Corp. -Phase 7 -61 not 9 -A
-- 4. Please add 100 year floodplain along the south side- see sheet 20 of plans
Construction Documents
1.Cover sheet: Index- Sheets 6 -8 are Whistling Straits Drive; Sheet 9 is Piping Rock Circle.
2. Sheet 1: Final Plat is different from plat submitted for approval, ie, 22.83 vs 22.99 acres,
etc.
3. Sheet 3: Is fire hydrant at northwest corner of Royal Adelade Drive and Whistling Straits
Drive existing or proposed?
4. Sheets 9, 10, and 11: Add typical cross - section for outlet channel.
5. Sheet 16: Manhole at STA 15 +63.35- Label drop manhole.
6. Sheet 19: Mission Hills Drive should be Whistling Straits Drive.
7. Sheet 22: Erosion Control- need detail for silt fencing and need to show silt fencing on
the down slope of any areas that are to be substantially disturbed by clearing and
construction.
8. Need to add specifications and details for trench safety.
9. Sheet 31- Electrical is missing.
Drainage Analysis: OK
Reviewed by: Ted Mayo Date: 01 /18/02
ELECTRICAL
1. Developer installs conduit as per city specs and design.
2. Developer installs street lighting as per city specs and design.
3. Developer provides temporary blanket easement for construction
purposes.
4. Developer provides digital of plat and /or site plan for AutoCAD 14. Email
to rbolin ci.college- station.tx.us
5. Developer provides easements for electric infrastructure as installed
(including street lighting).
6. Upon completion of project surveyed sealed meets and bounds
descriptive easements are necessary to release temporary blanket
easement.
Reviewed by: Ronnie Bolin Date:1 -17 -02
NOTE: Any changes made to the plans, that have not been requested by the City of College Station,
must be explained in your next transmittal letter and "bubbled" on your plans. Any additional
changes on these plans that have not been pointed out to the City, will constitute a completely
new review.
2of2
of
Case file #2- 500007
STAFF REVIEW COMMENTS NO. 1
Project: PEBBLECREEK, PH 713-1 (FP) -FINAL PLAT (2- 500007)
ENGINEERING
Final Plat
1. Note- lower left corner- No. 48041 CO205 , Date of February 09, 2000
2. 20' off -site PUE- will need evidence of filing before plat is filed
3. Signature block- Pebble Creek Dev. Corp. -Phase 7 -131 not 9 -A
4. Please add 100 year floodplain along the south side- see sheet 20 of plans
Construction Documents
1.Cover sheet: Index- Sheets 6 -8 are Whistling Straits Drive; Sheet 9 is Piping Rock
Circle.
2. Sheet 1: Final Plat is different from plat submitted for approval, ie, 22.83 vs 22.99
acres, etc.
3. Sheet 3: Is fire hydrant at northwest corner of Royal Adelade Drive and Whistling
Straits Drive existing or proposed?
4. Sheets 9, 10, and 11: Add typical cross - section for outlet channel.
5. Sheet 16: Manhole at STA 15 +63.35- Label drop manhole.
6. Sheet 19: Mission Hills Drive should be Whistling Straits Drive.
7. Sheet 22: Erosion Control- need detail for silt fencing and need to show silt fencing
on the down slope of any areas that are to be substantially disturbed by clearing and
construction.
8. Need to add specifications and details for trench safety.
9. Sheet 31- Electrical is missing.
Drainage Analysis: OK
Reviewed by: Ted Mayo
Date: 01/18/02
NOTE: Any changes made to the plans, that have not been requested by the City of College Station,
must be explained in your next transmittal letter and "bubbled" on your plans. Any additional
changes on these plans that have not been pointed out to the City, will constitute a completely
new review.
2 of 2
ELECTRICAL
1. Developer installs conduit as per city specs and design.
2. Developer installs street lighting as per city specs and design.
3. Developer provides temporary blanket easement for construction
purposes.
4. Developer provides digital of plat and /or site plan for AutoCAD 14. Email
to rbolin _ci.colleae- station.tx.us
5. Developer provides easements for electric infrastructure as installed
(including street lighting).
6. Upon completion of project surveyed sealed meets and bounds
descriptive easements are necessary to release temporary blanket
easement.
Reviewed by: Ronnie Bolin Date:1 -17 -02
NOTE: Any changes made to the plans, that have not been requested by the City of College Station,
must be explained in your next transmittal letter and "bubbled" on your plans. Any additional
changes on these plans that have not been pointed out to the City, will constitute a completely
new review.
3of2