Loading...
HomeMy WebLinkAboutStaff ReportsL STAFF REVIEW COMMENTS No. 1 Project: STONE FOREST PHASE 1 (FP)-FINAL PLAT (0-195) PLANNING 1. Please remove the references to zoning on surrounding properties. Reviewed by: Spencer Thompson Date: 10/24/00 ENGINEERING 1. A 5' PUE appears on Lot 39/40 Block 5 which was not on the Pre-plat. It appears on some sheets and not on others. What is this for? Reviewed by: Spencer Thompson Date: 10/24/00 ELECTRICAL 1. Developer responsible for installing conduit per city spec. and design. 2. Developer responsible for providing and installing street lights per city spec. and design 3. Developer responsible for providing easements to cover all primary electrical lines and equipment. 4. Developer responsible for providing 5' easements to cover streetlight light services as needed Reviewed by: Jennifer Reeves Date: LAND MANAGEMENT 1. No comments Reviewed by: Melissa Rodgers Date: 10/23/00 NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City will constitute a completely new review. Staff Review Comments Page 1 of 2 Stone Forest Subdivision, Phase 1 Response to Staff Review Comments No. 1 Planning: References to zoning on surrounding properties have been removed. Engineering: The 5' PUE appearing on Lot 39/40, Block 5 which was not on the pre-plat is an easement for electrical service to a street light. Electrical: Developer will comply with electrical comments. STAFF REPORT Item: Consideration of a Final Plat for Stone Forest Subdivision Phase I, being 24.38 out of 64.99 acres of Stone Forest Subdivision (previously known as Stonegate Subdivision and Texas Centroid Ranch) located on Greens Prairie Road between Lakeway Drive and Pebble Creek Parkway. (0-195) Applicant: Joe Schultz (Texcon) for Johnson Investments, Inc. Staff Recommendations: Seeing that all City requirements have been met for this final plat, staff recommends to the Commission: "approval as submitted". Item Summary: City staff has confirmed that this Final Plat conforms to the approved Master Preliminary Plat approved by the Commission on September 21, 2000. The subdivision abuts the Pebble Creek Subdivision, however, there is no street connection to Pebble Creek. There is a street connection, Agate Drive, through Stone Forest to Lakeway Drive. As a condition of rezoning, the Council required a 20' buffer between Agate Drive and the Pebble Creek lots adjoining Agate. Phase I includes 80 R1-13 lots and the detention pond/ common area. Additions to City infrastructure include sanitary sewer, storm sewer and water lines. Phase II will contain the 34 lots to the south and includes the street connection to Lakeway Drive. Phase III will contain the remaining 41 lots to the west of Phase I. Commission Action Options: The Commission has final authority over the final plat. The Commission's options regarding the plat are as follows: • Approval as submitted • Approval with conditions • Denial • Defer action • Table only at applicant's request. Supporting Materials: 1. Location Map 2. Application 3. Infrastructure and Facilities 4. Copy of Final Plat Created on 11108100 5:01 PM J: IPZTEXTI PZ03896. DOC INFRASTRUCTURE AND FACILITIES Water: There is an existing 18" waterline along Greens Prairie Road suitable for this subdivision. We have discussed with the applicant looping the water line through the subdivision to the 18" water line along Lakeway for more efficient and effective water system operations. Sewer: There is an existing 10" sewer line along Greens Prairie Road suitable for this subdivision. Streets: The plat has approximately 2,420 feet of frontage along Greens Prairie Road, which has a 130' right-of-way and is classified on the Thoroughfare Plan as a major arterial. At this time, Lakeway Drive is considered to be a major collector on the Thoroughfare Plan. A divided entryway, Stone Forest Drive, will be taken off Green's Prairie Road. The subdivision will consist mainly of cul-de-sac streets with Agate Drive connecting through to Lakeway Drive. Off-site Easements: None Parkland Dedication: None required for commercial platting. Drainage: The site will be required to meet the Drainage Ordinance at the site plan stage. A drainage report is being reviewed at this time. Flood Plain: None Oversize request: Oversize participation has not been requested. Impact Fees: None NOTIFICATION: Legal Notice Publication(s): None Required. STAFF MEMBER: Spencer Thompson, Development Services, Engineering Created an 11108100 5:01 PM J: IPZTEXTI PZ03896. DOC