HomeMy WebLinkAboutStaff Reportsf ENGINEERING REVIEW COMMENTS No. 1 Project: College Main Parking Garage (SP)-SITE PLAN (0-115) 1. Concerning the irrigation water service, please include note in Water Service Notes- [2] "w/ Backflow Preventer (RPZ)". This note has been added by myself to the submitted drawings after my conversation with Mr. Mike Record (8/16/00). 2. Due to the fact that the water lines on College Main are Public Infrastructure up to the meter and or backflow preventer, please submit a plan and profile sheet detailing construction and any conflicts with other utilities. Reviewed by: Spencer Thompson Date: 08/16/2000 STAFF REVIEW COMMENTS No. 2 PROJECT: COLLEGE MAIN PARKING GARAGE (SP)-SITE PLAN (0-115) PLANNING 1. Please make a note on the first page of the site plan that the site plan consists of pages Al-2, A6-7, L1-2, and C1-8. 2. On Sheet A2, please show the overhead utility lines on the west side of the building as ending at a pole. 3. Will the sidewalk that is planned for the south side of the building meet minimum clearance when it reaches the transformer pad? As discussed at the Northgate Review Board meeting: 4. Landscaping in the area of the detention pond will be reviewed after detention pond changes are made. ~ 5. Bicycle rack(s) for the parking of 20 bicycles need to be added to the plan. Standards for rack design, color, and signage are described in the ""~ Northgate Design Guidelines. Copies of relevant pages from the Guidelines are attached to these review comments. ~- 6. A change from stamped concrete to brick pavers will be requested if their use is determined to be economical. ~ 7. It need not be included on the site plan, but the addition of the Northgate Logo on the eastern facade will be required as a condition of the building permit. Reviewed by: Molly Hitchcock Date: August 8, 2000 ENGINEERING 1. According to my conversation with Mr. Record, the design of the fire system is being addressed in order to meet NFPA standards. This will Staff Review Comments Page 1 of 1 J:\PZTEXT\PZ03548. DOC affect the water meter and line size going to the building. It will also eliminate the 2" connection of the domestic water supply to the fire line. 2. The final drainage report has not been reviewed. According to conversations with Mr. Llewellyn, he will amend and resubmit the report for final approval. Reviewed by: Spencer Thompson Date: August 11, 2000 ELECTRICAL 1. Reviewed by: Jennifer Reeves Date: NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. Staff Review Comments Page 2 of 1 J:\PZTEXT\PZ03548. DOC NORTHGATE REVITALIZATION BOARD (NRB) REVIEW SUBCOMMITTEE MEETING August 2, 2000 TO: Mike Record, Arkitex Studio, Via fax (979) 846-8224 Mark Smith, Via fax (979) 764-3489 FROM: NRB Review Subcommittee: Elton Abbott, Jr., NRB Member Cheryl Anz, NRB Member Richard Benning, NRB Member John Happ, P&Z Commissioner Ray Harris, P&Z Commissioner Karl Mooney, P&Z Commissioner Staff Attending: Sabine McCully, Senior Planner Molly Hitchcock, Staff Planner Bridgette George, Asst. Development Coordinator Tammy Macik, Secretary SUBJECT: College Main Parking College -request for approval for the development of a parking garage to be located at 309 College Main in Northgate. (00-115) The NRB Review Subcommittee held a meeting on Wednesday, August 2, 2000 to review the above-mentioned item. Mike Record opened the discussion by informing the NRB Committee that a change of design would be necessary for the water detention area since the city's Economic Development Council had made an agreement to let the Traditions dormitory facility drain its runoff water on the garage site. Therefore, the landscaping and the general presentation of that area could not be considered by the NRB at this time. The NRB discussed different issues pertinent to the development of the garage. The issues discussed were landscaping, bicycle parking, sidewalks, sign types, awnings, and the architecture. Commissioner Happ motioned to approve the landscaping from College Main to a portion of Second Street. The motion was seconded by NRB Member Anz and passed 5-0. Commissioner Happ motioned for the architects to investigate the parking, rack design color and signage for 20 bicycles in the parking garage. The motion was seconded by NRB member Benning and passed 5-0. Commissioner Happ motioned to accept the design and placement of the sidewalks. The motion was seconded by NRB member Benning and passed 5-0. NRB member Benning motioned to investigate the use of brick pavers instead of stamped concrete for the sidewalks. Commissioner Harris seconded and the motion passed 5-0. NRB member Benning motioned to use the Northgate logo between the buttresses and also motioned to approve the proposed sign types and their placement. Commisioner Happ seconded and the motion passed 5-0. Commissioner Happ motioned to accept the awning as presented. NRB member Anz seconded and the motion passed 5-0. Commissioner Happ motioned to accept the architectural style, mass and scale and the building color, elements and orientation. NRB member Anz seconded and the motion passed 5-0. NORTHGATE REVITALIZATION BOARD STAFF REPORT For College Main Parking Garage (00-115) All proposals involving site development or redevelopment in the Northgate District shall require a review by a review subcommittee of the Northgate Revitalization Board (NRB). Zoning District: NG-1 Location: At the corner of Church Avenue and College Main Item Summary: Urban renewal Issues/Items for Review: 1. Additional parking and traffic impact studies, a review of existing occupancy, and other reasonable appropriate data to determine the impact of the project may be required. Additional parking or landscaping may be required where studies reveal that it is necessary to relieve or mitigate this impact. 2. Bicycle Parking Location 3. Bicycle Rack Design/Color 4. Bicycle Parking Signage 5. Streetscaping/Landscaping 6. Sidewalks 7. Sign type 8. Sign Design and Placement 9. Awnings and Canopies Design and Color 10. Architectural style 11.Architectural mass and scale 12. Building color 13. Building elements 14. Building orientation City of College Station Development Services P. O. Box 9960 ~ 1101 Texas Avenue ~ College Station, Texas 77842 (409) 764-3570 NORTHGATE REVITALIZATION BOARD (NRB) REVIEW SUBCOMMITTEE MEETING October 24, 2000 TO: Mike Record and Chad Grauke, Arkitex Studio, Via fax (979) 846-8224 Mark Smith, City of College Station, Via fax (979) 764-3489 FROM: NRB Review Subcommittee: Elton Abbott, Jr., NRB Member Cheryl Anz, NRB Member Richard Benning, NRB Member Ray Harris, P&Z Commissioner Karl Mooney, P&Z Commissioner Carolyn Williams, P&Z Commissioner Staff Attending: Natalie Ruiz, Development Review Manager Molly Hitchcock, Staff Planner Jessica Jimmerson, Senior Staff Planner Tammy Macik, Secretary SUBJECT.' College Main Parking College -request for approval for the landscaping of the parking garage to be located at 309 College Main in Northgate. (00-11 S) The NRB Review Subcommittee held a meeting on Wednesday, October 11, 2000 to review the above-mentioned item. Jessica Jimmerson opened the discussion by informing the NRB Committee that this item has come before the committee previously but there were landscaping issues, bicycle racks and the type of sidewalk to be decided upon. Also, the mural needs to be voted on even though there was a consensus previously. NRB Member Benning began the discussion of how high the mural will be. Commissioner Mooney had a question about the maintenance of the mural and NRB Member Anz had questions about the cost. Mr. Gauke gave an idea of the type of mural they are planning to have and what the cost will be. Home of Texas A&M University NRB Meeting College Main Parking Garage October 29, 2000 Page 2 of 2 NRB Member Anz motioned to approve the concept of a mural instead of landscaping on the south side of the building with the design of the mural to come back to the board at a later date. NRB Member Benning seconded the motion and it passed 5-0. The next item to be considered is landscaping. Jessica mentioned some items have been approved but there were a few items left to be approved. NRB Member Anz had a question of how tall the fence was around the detention pond and how safe it was. Mr. Record stated that the fence is 4 feet tall. There was further discussion about the type of fence needed for the detention pond and for it to go with the motif of other fences in Northgate. NRB Member Anz motioned to accept the fence at 4 feet with intermittent masonry columns along Second Street. Commissioner Harris seconded and it passed 5-0. The possibility of using of brick pavers instead of stamped concrete for the sidewalks is still being investigated. Commissioner Mooney recommended that this item go before the city to find out what the standard is for sidewalks in Northgate. Commissioner Harris motioned to approve landscaping and bicycle racks with the sidewalks issue to be placed on a future agenda. Commissioner Williams seconded and it passed 5-0. NRB Member Abbott abstained from voting on this item since he is directly involved with it. Home of Texas A&M University STAFF REVIEW COMMENTS No. 1 Project: COLLEGE MAIN PARKING GARAGE (SP) (0-115) mar a... ~...-. S'vv.s_k ~ 'i .t.. ~a:~ L.~, ~\O-/~. 1. Show all existing curb cuts-for parking as well as driveways. ,+-~;~ 2. Please note: The Lutheran Church on the abutting property is determining ~~~ ~~~~ here to place a sidewalk across their frontage. Sidewalk placement against their property line should be coordinated with them. 3. Show all existing easements. ~•~.~~~ ~, ~--~ ~ ~~1N.o.+~'~C..~•,;,,~rv~. 4. Please include the building height in the project description. v~63,~.~ ~,..~.~~. ~~.. ~..o~-L 5. Parking spaces need to be dimensioned. v~~ .. ,~,~~.~~ ~„~_ ~! 6. Please identify all handicap parking spaces. Space and identification details need to be provided with a note that states they will all meet ANSII standards. 7. Dimension the distances between proposed and existing curb cuts. 8. Indicate the driveway throat lengths. ``~ ~`~'~~ N ef-k . ~' w~ v,~~c Z.,~ Q `--man the location of the ticket dispenser be adjusted to provide enoug~i queue for at least 2 cars? -~$-'Show all proposed easements on the site plan. Meters will have to be located in the public ROW or in a public utility easement. ~~~~~-~ v,~p ~~~ -- -1-1--There is an unmarked line ending on College Main on Sheet A2. What is it? 12.AIso on Sheet A2, The overhead utility lines on the west side of the building need to be shown ending at a pole. 13.On the landscaping plan, there appears to be: • Only 3 Leyland Cypresses , • Only 22 Nellie Stevens Hollies~,,,~0.1`~L ~rL ~ • And 7 Crepe Myrtles (4 more than identified in the landscape legend). 14. Trees are evaluated by their caliper size. Please remove gallon sizes from the landscape legend and replace with caliper sizes. 15. There is a 20' separation requirement between canopy trees. Please adjust the placement of the Leyland Cypresses to meet this. i. The detention pond needs to be screened from the ROW with landscaping. Please consider planting grass over the weir. ° ~^"~ ~. ~-~ -~- '.Show meter and transformer locations on the landscaping plan and show that they will be screened with landscaping. Staff Review Comments Page 1 of 1 .~-~' 18. Some type of decorative element is needed west of the garage entry on Second St. (e.g., plantings and period light standards) ~.a.*~ ~ ~ s~,~,, ~~,,~ There are five lamp posts along College Main but none along Second St. Will ~~Ov'^`~~. any be needed? hat are the hatch marks on sheet C-2? ~~ ~'~ ~~ ~~~ _ '~~ Q ,~ Reviewed by: MOLLY HITCHCOCK Date: 07/07/00 ENGINEERING REVIEW 21. A Drainage Report has not been submitted for this project. Staff has reviewed a preliminary drainage report, however, the report was not stamped and signed by a registered/ professional engineer, as is required, and some calculations were not performed as per City requirements. These calculations may affect the detention pond sizing and the outlet piping sizing. 22. A 3" domestic water meter is specified for this project. The engineer needs to tee off this line and install two separate meters; one for domestic use and one for irrigation, along with the required irrigation check valve. According to plan estimates, domestic water flow rates would require, at most, a 1" meter (PM5). Irrigation flow estimates are not provided. 23. The fire line connection to the City's water main does not appear on the plans. A 6" tap should be made onto an 8" water main to supply fire flows to the building fire system. A 2" connection is shown going to the fire pipeline (PM2). This connection should not be installed. 24. Sheet C2 shows a 6" PVC drain pipe. This pipe apparently drains the swale along the east side of the building. It is not clear whether this drain connects to the 24" storm drain or drains to the street gutter If it drains to the gutter, a 6"pipe may be too large to penetrate the curb? Reviewed by: Spencer Thompson Date: 7-Jul-00 NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. Staff Review Comments Page 2 of 1 \~" ~ A ~\ 0.J" -~ C~.>..'~v ~-~ R--~ `-' ~- ~.~~'e-- v `~_c'~-~ .~~ -, ~._ ~ <n ,~J~ ~~ . 0- ~' ~~. ~_-.