HomeMy WebLinkAboutMisc.MEMORANDUM
December 17, 1999
TO: Blake Cathey, 6345 Smith Road, Bellville, TX, 77418
FROM: Bridgette George, Asst. Development Coordinator
SUBJECT: Campus Park Ph. 1 -B - Site Plan
Staff reviewed the above - mentioned site plan as requested. The following page is a list
of staff review comments detailing items that need to be addressed. Please address
the comments and submit the following information for further staff review:
Three (3) complete sets of building construction documents for the
proposed development with the revised site and landscaping plans
attached; and
The attached redlined site plan with staff comments.
If there are comments that you are not addressing with the revised site plan, please
attach a letter explaining the details. If you have any questions or need additional
information, please call me at 764 -3570.
Attachments: Staff review comments
Electrical & W /WW comments
cc: Debbie Keating, Via fax (409) 696 -9752
Case file #99 -507
apmjai instructions:
PROJECT: CAMPUS -PARK SUBDIVISION C k>
Construction Plans with Redlines for Phases 1 -A 1 -B and Phase 2. Revised Cost Estimate for
Phase 1 -B. And Site Plan's with Redlines for Phases 1 -A and 1 -B.
TRANSMITAL LETTER
TRANSMIT.DOC 03/23/99 JAN f, 2000
1 (�
MEMORANDUM
January 28, 2000
TO: Debbie Keating, Via fax (409) 696 -9752
FROM: Bridgette George, Asst. Development Coordinato
SUBJECT: Campus Park Ph. 1B - Site Plan
Staff reviewed the above - mentioned site plan as requested. The following page is a list
of staff review comments detailing items that need to be addressed. The next submittal
will be the third and final review by staff for this round of reviews. If all items have not
been addressed on the next submittal, another $100 processing fee will need to be
submitted for the subsequent set of three (3) reviews. Please address the comments
and submit the following information for further staff review:
Two (2) revised site plans (once plans have been approved additional sets
will be requested to be stamped approved and distributed);
If there are comments that you are not addressing with the revised site plan, please
attach a letter explaining the details. If you have any questions or need additional
information, please call me at 764 -3570.
Attachments: Staff review comments
cc: Blake Cathey, 6345 Smith Road, Bellville, TX, 77418
Case file #99 -507
<nruiz @ci.college- station.tx.us >, <msmith @ci.college - station.tx.us>
qq- 5z-7
LJ3G
Urban IJesic
11 P.O. Box 10153 College Station, Texas 77842 Ph: (979)- 696 -9653 Fax: (979 696 -9752 1 1
TRANSMITTAL LETTER
TO: Jessica Jimmerson FROM: Deborah Keating rb�
Citv of Collece Station
Re: Campus Park Date: December 1, 1999
please find : ❑ attached ✓ as requested
❑ original sent via mail ❑ for your information
❑ plans ❑ for your files
❑ specifications ❑ for your approval
❑ other ❑ for your review
*"�� �E � ���i a� ` � d R ��:s� i y � �s ,. E xe E � ��+���r 3" . a � � � `� � �•�.�a� � a� 'a qFk y �� :•.
2
t:. ;� g ,..,.x�....' A , �.`�".:��x:° , h �::;.. as �'........ ...
COMMENTS:
Enclosed is the plans that you reges°7 i � 777--
p MAR 1
J L.I 77''
v
C: office /transmit. doc
DEVELOPMENT SERVICES
TRANSMITTAL LETTER
Name/Firm: Urban Design Group Date: January 10, 2000
Address: 909 Southwest Parkway East, Suite E Phone: (409) 696 -9653
College Station, Texas 77840 Fax: (409) 696 -9752
We are transmitting the Following for Development Services to review and comment: (Check all that
apply.):
• Master Development Plan
• Preliminary Plat
• Final Plats
• FEMA CLOMA/CLOMP,/LOMA/LOMR
✓ Site Plan (1 -A and 1 -B)
• Grading Plan
• Landscape Plan
• Irrigation Plan
• Building Construction Documents
w/❑
Redlines
❑
Development Permit App.
w/❑
Redlines
❑
Conditional Use Permit
w/❑
Redlines
❑
Rezoning Application
w/❑
Redlines
❑
Variance Request
w/✓
Redlines
✓
Other - Please Specify
w/❑
Redlines
Revised Site Plans: 1 -A,1 -B
w/❑
Redlines
with Redlines
w/❑
Redlines
Construction Plans: I -A, I -B,
w/❑
Redlines
and 2 with Redlines
Revised Cost Estimate: 1 -B
INFRASTRUCTURE AND ENGINEERING DOCUMENTS
All infrastructure documents must be submitted as a complete set.
The following are included in the complete set:
✓
Waterline Construction Documents w/ ✓
Redlines
✓
Sewerline Construction Documents w/ ✓
Redlines
✓
Drainage Construction Documents w/ ✓
Redlines
✓
Street Construction Documents w/ ✓
Redlines
•
Easement application with metes & bounds description
•
Drainage Letter or Report w/ ❑
Redlines
❑
Fire Flow Analysis w/ ❑
Redlines
Special Instructions:
• TxDOT Driveway Permit
• TxDOT Utility Permit
❑ Other — Please Specify
PROJECT: CAMPUS -PARK SUBDIVISION C k>
Construction Plans with Redlines for Phases 1 -A 1 -B and Phase 2. Revised Cost Estimate for
Phase 1 -B. And Site Plan's with Redlines for Phases 1 -A and 1 -B.
TRANSMITAL LETTER
TRANSMIT.noC 03/23/99 JAN 1 2000
¢- ys
Bridgette George - New Development
Page 1
From:
Jennifer Reeves
To:
Bridgette George
Date:
12/14/99 11:OOAM
Subject:
New Development
Week of 12/9/99
Texadelphia: (99 -455) Developer installs conduit per city spec and design.
VCampus Park Phase 1 -13: (99 -507) Developer installs conduit per city spec and design. Developer
needs to provide easements per electrical design.
Woodlake Subdivision Section 2 Phase 1: (99 -260) No Comment.
2 -13 Homes: (97 -441) Developer needs to provide temporary blanket easement. Developer needs to
provide load information, and service requirements.
Ordonez Residence: (99 -733) Owners need to contact Electrical Division if there is going to being
additional load to existing service.
Sweetwater Ph. 2: (99 -319) Developer installs conduit per city spec and design. Developer provides
easements per Electrical design.
Chimney Hill Townhomes: (99 -261) No Comment.
CITY OF COLLEGE STATION
PLANNING DIVISION
POST OFFICE BOX 9960 1101 TEXAS AVENUE
COLLEGE STATION, TEXAS 77842 -9960
TELEPHONE: (409) 764 -3570
MEMORANDUM
December 17, 1999
TO: Blake Cathey, 6345 Smith Road, Bellville, TX, 77418
FROM: Bridgette George, Asst. Development Coordinat
SUBJECT: Campus Park Ph. 1 -B - Site Plan
Staff reviewed the above - mentioned site plan as requested. The following page is a list
of staff review comments detailing items that need to be addressed. Please address
the comments and submit the following information for further staff review:
Three (3) complete sets of building construction documents for the
proposed development with the revised site and landscaping plans
attached; and
The attached redlined site plan with staff comments.
If there are comments that you are not addressing with the revised site plan, please
attach a letter explaining the details. If you have any questions or need additional
information, please call me at 764 -3570.
Attachments: Staff review comments
Electrical & W/WW comments
"��2�tl�ne�, C Qi�ase Pick u ,,) a}- l)ev0c eS�
cc: Debbie Keating, Via fax (409) 696 -9752 '
Case file #99 -507
a me c u y - Campus Par Gar age Containers
f�age
From:
Blake Cathey <bcathey @flash.net>
To:
Debbie Keating <udgcs @txcyber.com>
Date:
12/1/99 7:38PM
Subject:
Campus Park Garbage Containers
Debbie,
I met with Mark Smith this afternoon and we mutualy agreed on the
location /style of the garbage collection containers. It was decided to
utilize the 300 gal containers which will be placed on a 8'x8' concrete
pads. Each container will service 6 townhouse units. The location of
these containers is indicated on the sketches provided this afternoon
and described briefly as follows:
Ir Phase IA - A single container located next to townhouse unit no. 7 and
directly behind the 8x10 patio.
Phase 2 - Three containers servicing 16 townhouse units (no's 13 -28)
clustered together and located in front of unit 17 near the cul -de -sac.
Phae IB - A single container located next to townhouse unit no. 4 and
directly behind the 8x10 patio.
Blake
\Vk, i J
CC: "McCully, Sabina" <smccully @ci.college- station.tx.us >, Natalie Ruiz
<nruiz @ci.college- station.tx.us >, <msmith @ci.college- station.tx.us>