HomeMy WebLinkAboutMisc.Commerce National Bank ENGINEER ESTIMATE PUBLIC IMPROVEMENTS • DESCRIPTION 1 Fire H drant Relocation UNIT EA • 1 UNIT COST $4,200.00 TOTAL COST $4,200.50- 2 Handicap Ramps EA 2 $500.00 $1,000.00 3 6" Reinforced Concrete Paning SY 150 $32.00 $4,800.00 4 Curb & Gutter LF 90, $10.00 $900.00 5 12"X3" Tapping Sleve & Valve EA 1 $2,500.00 $2,500.00 6 24" RCP LF 57 45.00 $2,565.001 ESTIMATED CONSTRUCTION COST Contingency (15%) TOTAL CONSTRUCTION COST $7,287.00 $1,093.05 $8,380.05 NOTES CONCERNING OPINIONS OF PROBABLE CONSTRUCTION COST Urban Design Group's (UDG) opinions of probable construction cost provided for herein are made on the basis of our experience and qualifications and represent our best judgment as an experienced and qualified professional engineering firm generally familiar with the construction industry and applicable development regulations. However, since UDG has not obtained approval from the appropriate jurisdiction and UDG has no control over the cost of labor, materials, equipment or services furnished by others, or over the Contractor's methods of determining prices, or over competitive bidding or market conditions, UDG cannot and does not guarantee that proposals, bids or actual construction cost will not vary from opinions of probable construction cost prepared by UDG. 1of1 Natalie Ruiz - Re: Commerce National Bank Pa e 1 From: Veronica Morgan To: City of College Station:udgcs@[txcyber.com] Date: Mon, May 17, 1999 5:23 PM Subject: Re: Commerce National Bank still do not have any as-builts yet... i have talked with parvis vessali who is working on the shoneys inn site which was to share detention facilities with the original bank facility. i talked to him about the original pond location and that there were no easements or utilities shown on the site plan done by galindo. he has gone back to ask chris if there was an easement or utilities in front of the bank property, specifically where he located the pond. chris said that there is no easement there or utilities. does your information conflict with this? from what i remember seeing on your survey work in the predevelopment meeting i thought i saw an easement and utilities showing up.. can you shed some light on this? thanks v "Deborah L. Keating" <udgcs@txcyber.com> 05/13/99 09:24AM Veronica, has Carter & Burgess turned in their official as-builts, and if so can I get a copy? Thanks. Debbie Keating, P.E., Partner URBAN DESIGN GROUP CC: Natalie Ruiz . ,B::,,,..ank on University. Page 1 Natalie Ruiz Re uest for information re Commerce National:.:. From: Veronica Morgan To: internet:udgcs@txcyber.com Date: Fri, May 7, 1999 5:00 PM Subject: Request for information re: Commerce National Bank on University I have reviewed the site plan for Hartland Bank and QAB (which I knew had a detention pond near a drainage easement). Hartland Bank did not show the utility easement in the front of the property where they proposed to place the detention pond. They did show the 10' and 20' utility easement that runs through the property north/south. The pond had a slight encroachment into the first few feet of that utility easement but it was not a cut situation. According to the plan it showed the grades bermed up only slightly. On QAB the detention pond was constructed wholly outside the easement. The answer to your question is: if you desire to place the detention facility within the easement you will need to obtain a license to encroach, regardless of your construction type. In discusions with Tony Michalsky, their electrical is very shallow and if you remove any cover you will have to deepen their lines at your expense. I dont know the depths of the other utilities but the Carter & Burgess plans should help you with that. Also re: the drive thru canopy, you will need to obtain a license to encroach for that facility as well. have been unsuccessful in reaching lawrence carter to see if they would entertain signing a license for this use and what restrictions (height, etc.) they may require. This should give you enough information to go on to help your client make a decision on the site layout. Call if you have any further questions. v CC: Natalie Ruiz 1 • U r~ 6-a~Q-- dig-, : t~-c 4--p C,76~ . • n U a-k i. QG:~- ca„~ . v S7c~_ cam, < L dy-~~, 0 - I-n d4l- I Y-(~-, P a, c L Q12~o 7(~ ofi~~ C_yCj O a~~u~ea- vF ~.k x1 Vaic vv~ 12 0 65/09/1999 08:05 6969752 URBAN DESIGN GROUP PAGE 01 IJ 909 Southwest Parkway East, Suite E Collepe Station, Texas 77840 Phone: (409) 866.9853 Fax: (409) 6WO752 Urban Design Group Fm To: Veronica Morgan From: Deborah Keating Fwa 764-3800 Dato: May 7, 1999 Phone: 764-3570 Pages: 2 Re: Commerce National Bank CC: O urgent ❑ For Rovlew ❑ lase Comment ❑ Please Reply ❑ Please Recycle -Comments: Veronica, I told you I -Adild call you regarding the utilities on the bank site. All we know at this point is the Information I receiv Carter & Burgess (attached). I talked to Logan and Elliott, and am awaiting the survey to see if th find anything different from the Carter & Burgess as-builts. When we know more, I vAN call to discu . Thanks for all your help. Debbie .7 /V 1") plu,~ fil~e w ~Cmym~ffm O~- 45P, ~OWWu opy l ac~a 2 ~ A~R S, OA29o~ 4/069 CW,~,cnd- aw wh uy/ a-yl~a0 41(94,d- aAch y~ec~i ,tl~u pat n 0 d2~w V61v, 4it rrqt ~n~h d afpv2w du cog's) combo-; imd"4t~ I'dj a/a~cuc~ ay)d an"'TWO UY) STAFF REVIEW COMMENTS No. 1 Project: Commerce National Bank - Temporary Building/Site 1. Area around site needs to be fully curbed. Connections to future phases can have temporary knock-off curbs. 2. Add a streetscape requirement for frontage along University Drive. Parking screening will be needed along University Drive 3. Change drive-through such that vehicles exiting drive-through do not conflict with vehicles entering site from Spring Loop. As designed, vehicles pulling out of drive-through window will encroach well into entry portion of driveway to exit the site. Also, a queue of three or perhaps only two vehicles at the drive through window will block vehicles from exiting the parking area. 4. Show a Phase Line. 5. Show existing sidewalk along Spring Loop 6. Clearly show all easements on plan. Extend easement to cover a portion of the underground electric, which does not appear to be contained within an easement. 7. Show building transformer location. 8. Show irrigation meter location. 9. Show dimension line across parking spaces and travel aisle. 10. Designate one space as handicapped 11. Parking aisle needs to be 20 feet in width. 12. Show how detention will be handled. 13. Is there a fence here? If not, one will need to be installed. 14. Dumpster Location? How will trash pick-up be handled? 15. If possible, please move hydrant out of sight clearance triangle. 16. Show irrigation plan for temporary building or provide note. Reviewed by: Edwin Hard Staff Review Comments Page 1 of 1 07/20/99 U 1~ m z y ~ O r o r r r c y O y l`J Q Q ~l 0 0 Bridgette George -.Re; New develo ment..: ::....:....Pag.e..?. From: Tony Michalsky To: BGEORGE c@CITY OF COLLEGE STATION.CITY HALL Date: 7/12/99 9:15AM Subject: Re: New development -Development Comments Steeplechase Subdivision Ph. 6 (99-233) Subdivisions electrical service is now provided by the City of College Station Electrical Division as of June 28, 1999. Developer installs conduit per city design and spec. Developer installs streetlighting per city design and spec. Additional 5 foot easements will be necessary for streetlight services where necessary. Additional easement may be necessary per electrical design. Developer is responsible for 20% of the cost of electric service. Commerce National Bank (99-432) Developer installs conduit per city specs and design. Developer pours trransformer pad per city specs and design. Developer needs to coordinate the location of padmount transformer with electrical division personnel. Developer provides a temporary blanket easement for construction purposes and meets and bounds discriptive easements to release temp easement. Developer is responsible for 20% of the cost of electric servvice.. Union Pacific Resources Oil Well (99432) No Comments Bridgette George 07/07/99 01:45PM GOOD AFTERNOONI Attached is the list of new development submitted this week. Please call if you have any questions. Thanksl Thank youl Bridgette George :o) Assistant Development Coordinator City of College Station (409)764-3570 • 0 Ica, 6e-~ (-ZL4~' I-E 4 0 ♦ N h' \ \ pV , \ 100, ' g o ~,n 14 % j.r H J J. H ♦ ! V • \ . 4 gyp, ~ t D~ 64~__ ~ ~ J' •L r'~~ \ ACS `^i~aBt L a 1 \~a l ` \ ?0 • \ / 16' 4ccc SS isk4lc 'cr L V V• J. i .yam L J J J. 4 `i \y•, \ L •1 y •L' J. `L '1 •1 •1 y `L 4 L • ~ -it \ 4~~ L i i aL 4 , J. 4 •l •1 ' `L ~ J ' `J~•. ,v. ! \ pR `p S-~ r y Wr J. i •`M -L J •1 •L •1 .L •L \ ~ ~ _ Y Z \ \ p Y ^ T W V• > .A, i,Y ,y .1. J. y. y w ` R- 3. 5~' \ (~•1 ° 74. 14 57 ~ 37 69' \296 C8=551.22,d2 "E \ PROPC wooqFEMM f i ! 1 '419 k ll~ A 4- A A •d 4 6 A Z { O V^ 4 •1 ~ ~ W J,~ _ - ~ PROP06ED1 - WITER ~IE1Bt i w i J• ~ ! if 1 ' 1 1 R=425-10-' , i z 4 D=16.4P59," ~ ~l~~TZ'4;2"88 1 t 1 ti 1, T=SB 89' 1ST 1 i'C=124.43' a 1 GCB=N31.20' 5 •,w ti _ _ . i _ i11 ~ r\ ' STAFF REVIEW COMMENTS No. 1 AA Project: 1 00w,rv-et-(fe- /V ~f7 l' - Per c~zn T ~Jl~~ 1. C1. Show location of building transformer. 2. C1. End Island will need to extend to delineate a full 9'x20' parking space. Since site has excess parking, may want to consider removing last space to improve exit lane for drive through. 3. C1. Redesign ATM exit lane such that it intersects interior driving aisle at more of a 90 degree angle. Add stop sign(s) so that exit lane traffic will have to yield to all other traffic. DO NOT ENTER signs should be posted on the back side of the stop signs. A stop bar could also be added with the stop signs. 4. C1. A sidewalk will not be required along University Drive. Sidewalks will be installed by TXDOT as part of the University Dr. widening to begin next year. 5. C1. Provide additional easement to cover the portion of the underground electric line (uu) not contained within the existing easement. 6. C1. Is this a shared dumpster with the Holiday Inn? If so, please add a note to the site plan stating such. 7. C1. Please clarify easements. They are hard to distinguish from topo's and some of the utility lines. Also, please clarify the utilities in this area. (Are there two telephone lines through this area?) 8. Comment Deleted. 9. C6. Should this note refer to electric instead of sanitary sewer? 10. C1. A fire lane will need to be extended through the parking area and out to Spring Loop in order to meet coverage requirements. The fire lane will need to be a reinforced concrete or pavement section. 11. C1. A license to encroach will be needed for the drive-through canopy. The determination of the minimum height for the canopy will be determined by staff as part of the license to encroach. 12. C3. The portion of the retaining wall facing University Dr. will need to be either a streetscape structure or be screened along the south portion of that wall (within the detention pond). 13. C1. Are these utilities in an easement? If so, please show. If not, please provide an additional easement to cover them. Reviewed by: Edwin Hard Staff Review Comments Page 1 of 1 07/13/99 STAFF REVIEW COMMENTS No. 1 Project: Commerce National Bank - Temporary Building/Site 1. Area around site needs to be fully curbed. Connections to future phases can have temporary knock-off curbs. 2. Add a streetscape requirement for frontage along University Drive. Parking screening will be needed along University Drive 3. Change drive-through such that vehicles exiting drive-through do not conflict with vehicles entering site from Spring Loop. As designed, vehicles pulling out of drive-through window will encroach well into entry portion of driveway to exit the site. Also, a queue of three or perhaps only two vehicles at the drive through window will block vehicles from exiting the parking area. 4. Show a Phase Line. 5. Show existing sidewalk along Spring Loop 6. Clearly show all easements on plan. Extend easement to cover a portion of the underground electric, which does not appear to be contained within an easement. 7. Show building transformer location. 8. Show irrigation meter location. 9. Show dimension line across parking spaces and travel aisle. 10. Designate one space as handicapped 11. Parking aisle needs to be 20 feet in width. 12. Show how detention will be handled. 13. Is there a fence here? If not, one will need to be installed. 14. Dumpster Location? How will trash pick-up be handled? 15. If possible, please move hydrant out of sight clearance triangle. 16. Show irrigation plan for temporary building or provide note. Reviewed by: Edwin Hard Staff Review Comments Page 1 of 1 07/13/99 L ' 'Sur - 7lu- Alc01ILL-f0,)7-,U~x A"modM ~icho,d o STAFF REVIEW COMMENTS No. 2 Project: Commerce National Bank (site plan) #99-432 Provide an additional STOP sign with a DO NOT ENTER sign mounted on the backside of the stop sign for the ATM exit lane at its intersection with the interior drive aisle (a sign located on each side). 2. Provide FIRE LANE striping for the driveway at University Drive (include the median), and on the interior drive aisle adjacent to the parking spaces. Reviewed by: Ed Hard and Scott Hester Date: 9-9-99 Staff Review Comments Page 1 of 1 STAFF REVIEW COMMENTS No. 2 Project: Commerce National Bank (temp. bldg. site) #99-432 1. The area around the site needs to be fully curbed. Connections to future phases can have temporary knock-off curbs. The use of wheel stops is not permitted. 2. The head-in parking spaces along with the building need to be moved further into the site interior in order to provide an adequate maneuver area for vehicles backing from the head-in spaces, entering and exiting the site, and queuing in the drive-thru. With the site layout as proposed, some vehicles will back directly out onto Spring Loop and could potentially create problems for traffic on Spring Loop as well as for access into and out of the site. 3. The throat length needs to be a minimum of 25 feet. 4. Label proposed easements added to cover the underground electric and wastewater lines (as done on the permanent site plan). Reviewed by: Ed Hard and Scott Hester Date: 9/9/99 ~raT t4.~/ fU~.• 1 Ca .~ceq4dk ' P, LAC-1 r Ol ao~ / pry y r Q 3. C..31 I ~ '0~_~ 4, z 0 z ZV "'4 "U Staff Review Comments / ~ ~ Page 1 of 1 ~x.c cc 19-04 n , ~j I i3 - - STAFF REVIEW COMMENTS No. 2 Project: Commerce National Bank (site plan) #99-432 J1. Provide an additional STOP sign with a DO NOT ENTER sign mounted on the backside of the stop sign for the ATM exit lane at its intersection with the interior drive aisle (a sign located on each side). /2. Provide FIRE LANE striping for the driveway at University Drive (include the median), and on the interior drive aisle adjacent to the parking spaces. Reviewed by: Ed Hard and Scott Hester Date: 9-9-99 Staff Review Comments Page 1 of 1 STAFF REVIEW COMMENTS No. 2 Project: Commerce National Bank (temp. bldg. site) #99-432 1. The area around the site needs to be fully curbed. Connections to future phases can have temporary knock-off curbs. The use of wheel stops is not permitted. 2. The head-in parking spaces along with the building need to be moved further into the site interior in order to provide an adequate maneuver area for vehicles backing from the head-in spaces, entering and exiting the site, and queuing in the drive-thru. With the site layout as proposed, some vehicles will back directly out onto Spring Loop and could potentially create problems for traffic on Spring Loop as well as for access into and out of the site. 3. The throat length needs to be a minimum of 25 feet. 4. Label proposed easements added to cover the underground electric and wastewater lines (as done on the permanent site plan). Reviewed by: Ed Hard and Scott Hester Date: 9/9/99 Staff Review Comments Page 1 of 1 STAFF REVIEW COMMENTS No. 3 Project: - Commerce Nat'l - Temporary Building 1. Parking island needed at end of this parking row. 2. What is this? (Extraneous Line?) 3. Pavement in temporary drive-thru will need to be built to permanent standard. (In light of this, may want to consider constructing permanent drive-through and re-positioning building to make use of it.) 4. Clarify all locations on site where temporary knock-off curb is to be used. 5. Building corner creates sight distance problem for drive-thru traffic. May want to consider moving the building back or adding an end-island out past the drive-through to address problem. Reviewed by: Ed Hard / Scott Hester Date: 9/23/99 Staff Review Comments Page 1 of 1 I II _ 1 I~ k,W _ - _ _ - - _ - - _ - r, o i~ n ~O 1mim HAS' t PF f r'r" c _ cn r _ - - -i `r \ ' +PROPOSED PHASE LS Z 1,a S: r p - 3c Z ji i s i -4 UM Urban Design Group Natalie Ruiz, Development Review Coordinator Dept. of Development Services City of College Station P.O. Box 9960 College Station, Texas 77842-9960 Via: hand delivery Re: Commerce National Bank College Station, Texas Dear Natalie, June 29, 1999 Attached please find the submittal of the site plan and supporting documents for the proposed Commerce National Bank. Along with the site plan is a temporary building plan. The bank is needing some assurance that a temporary building can be approved for that site, so they can proceed with the design of the permanent building to be located as shown. Since our last meeting with staff, we have designed the detention pond to meet the ordinance requirements and avoided the easements as suggested. This design however produces a pond that we perceive is "out of scale" for the development and the location of the property. Specifically, the square footage of the pond is larger than the square footage of the bank. As such, we are requesting a meeting with the necessary personnel to discuss other design options. Allan Hanson or Tom Aughinbaugh may be calling to schedule a time. Thank you for all your assistance. We look forward to hearing from you. Please call should you have any questions. Sincerely, URBAN 7SIGN GR P Deborah L. Keating, P.E., Partner xc: Allan Hanson Tom Aughinbaugh Post Office Box 10153 • College Station, Texas 77842 • 409 • 69 6 • 9653 STAFF REVIEW COMMENTS No. 3 Project: COMMERCE NATIONAL BANK (SP)-SITE PLAN (99-82) ENGINEERING 1. There is insufficient grade change, or "High Point", at the Spring Loop entrance in order to influence the surface flow to gravitate toward the storm drain inlets. It appears that a considerable amount of the surface flow will exit the site through the drive. Please change the grading to ensure surface flows will enter the detention pond. Reviewed by: Spencer Thompson Date: February 28, 200 ,NOTE Any changes made to the plans. that have not been requested by the City of Coliege Station must be explained in your next transmittal letter and `bubbled" on your plans. Any additional changes on these plans that .have not been pointed out to the City, will constitute a completely new review. Staff Review Comments page 1 of t J 1PZTEXT\PZ04447. DOC ~ O Urban Design Group Spencer Thompson, Staff Engineer Dept. of Development Services City of College Station P.O. Box 9960 College Station, Texas 77842-9960 Via: hand delivery Re: Commerce National Bank Dear Spencer, March 6, 2001 In response to the comment received via fax 3/1/01, the area near Spring Loop is already constructed and not a part of this application for review. The shaded area as depicted on the plan (rear parking) is the only new construction proposed. The rear parking has been previously approved. This plan shows a reconfiguration of the parking spaces. Sincerely, URBAN DESIGN GROUP Deborah L. Keating, P.E., Partner Encl.: (1) reproducible plan Post Office Box 10153 . College Station, Texas 77842 • 409 • 69 6 . 9653 .r _ ~ -er... -bra..",-_~~~ ~y"i."~ i.~j~~~~ - ..`1r w ■ I l is Rj ,cam 9 w L I Il u v i i 44- 1 cl lop crb b N V' n . w U N s- w z D 2 ©'d 94t T 089 bTZ ONIiinSNUO XO11HLI"d 0519811999 08:05 6969752 URBAN DESIGN GROUP PAGE 02 o \ e~'~s 4fti 1 ORS Gl~ x25.25 4 0 3 ~w r ~0 c ~ m o U~ 8 o~ E®®©0®®~®~ l9 I I g I ~ I l ~k I a I - - - - - - - - - - - - x ASE 1 PHASE 2 oo~i 7MC l~~ Afl 119 y~1 r G i A n I D FAT LL g ~v 1_ a y-_ as . . A ,~P U1Wr^""` C 4 -A ✓ pg- \O ~ ~ q ° SPRING I-,OOP "~o~ ° y _ am 3 m 8 ~ R D tA m n O - 0 COMMERCE ' ' . IONAL BANK NA T m z C) Z m m xa UNIVERSITY PARK SECTION 11 ~ y - _ BLOCK T, LOTS 12 & 14-B o m W g= N 1 .533 ACRES u Zakc . Z V 0 C , IA Fj i rXr_nn V• r o ~ X A A X U► rn to • I .'fir ~ • - 1, ETT 6 ~ .rte l ' LJ r Y 0 i ~ ~ m (N ~ ~NIlsW U1 O ~ tRfl CC 4 ~~f fJ ~ O 0 D ` r ~ rs u ~ l ~b r~ 1 ~ i ' I • r .~r' f I , 1 .11