February 22, 1999
TO: Donald Garrett, Garrett Engineering
FROM: Bridgette George, Asst. Development Coordin to
SUBJECT: St. Matthew's Baptist Church Site and CradinS Plan
Staff has reviewed the revised site and grading plan submitted and the following items
still need to be addressed as shown on the attached site plan:
Include the parking island (a note can reflect a change if the variance is
granted);
Note distances from the center of the church drive to the edge of the opposite
and adjacent drives;
Include a 6" raised curb;
Recalculate the landscape/streetscape analysis based on corrected site area;
Show the number of streetseape trees required;
Include the required automatic irrigation system;
If changes are made to the existing sidewalk, show additional landscape and
other requirements;
Note existing utility line locations and connections;
Include shrubbery to screen parking;
Correct the ownership and current zoning information of surrounding tracts;
Increase the driveway throat width to a minimum of 23 feet;
Parking Analysis needs to reflect the affect of the island and the Foss ible change
if variance is granted; and
Handicap ramp elevation detail needs to comply with ANSI Al 17.1-1992.
Please address all of the staff comments/concerns as mentioned above and submit the
following for further review:
Two (2) copies of the revised site plan.
The attached redlined site plan with staff comments.
If you have any questions or need additional information, please call me at 764-3570.
/Cc: Donnie Helmn, St. Matthews Baptist Church, 409 Holleman Drive, College
Station, TX 77840 (No attachment)
Case file #99-402
Home of Texas A&M University
COLLEGE STATION
P. O. Box 9960 1101 Texas Avenue College Station, TX 77842
Tel: 409 764 3500
MEMORANDUM
April 1, 1999
TO: DeAnna Ordonez, Garrett Engineering, Via fax # (409)846-3094 ' .
FROM: Bridgette George, Asst. Development Coordinator
i
SUBJECT: St. Matthew's Baptist Church Site and Grading Plan
Staff has reviewed the revised site and grading plan submitted and the following items
need to be addressed:
Draw in the appropriate phase line, calculate site area for landscaping
and streetscaping from that phase line;
Need to see the irrigation plan including water demand (maximum,
minimum, and average) in GPM. Irrigation system will need to be
installed and operational before parking lot is complete and open for use;
If the sidewalk in front of the church is going to be changed, then the
phase line will need to be 20 feet from the change, resulting in an "L"
shaped phase line for the parking lot and sidewalk changes. Also, any
additional impervious cover created by sidewalk changes would need to
be accounted for;
There needs to be a note to the effect that the throat width is never less
than 23 feet; and
Show paving details.
Please address all of the items listed above and submit the following for final approval:
Three (3) copies of the revised site plan; and
Development Permit application and $100 application fee.
If you have any questions or need additional information, please call me at 764-3570.
Thank you.
cc: Donnie Helmn, St. Matthews Baptist Church, 409 Holleman Drive, College
Station, TX 77840 (Case file #99-402)
Home of Texas A&M University
MEMORANDUM
May 20, 1999
~ C_
TO: Don Garrett, Garrett Engineering
FROM: Bridgette George, Asst. Development Coordinator
SUBJECT: St. Matthew's Baptist Church - Revised Site and Grading Plan
Staff has reviewed the revised site and grading plan submitted and the following items
still need to be addressed as shown on the attached site plan:
Is the parking lot going to be asphalt or concrete?
One gallon containers do not count for landscaping points, unless clearly
labeled as miniature varieties.
The Streetscape analysis (for the number of trees required) needs to use 100'
frontage.
The proposed Asian and star jasmine are ground cover and vines, not shrubs
and will not count as shrub points. Select approved shrubs from the City of
College Station's recommended plant list to replace the ground cover with
shrubs within the phase line.
Please address all of the staff comments/concerns as mentioned above and submit the
following for further review:
Two (2) copies of the revised site plan.
The attached redlined site plan with staff comments.
$100 site plan review fee. Staff has reviewed this site plan five times and the
next submittal will be the sixth review. The original $100 site plan review fee
only covers the first three reviews.
If you have any questions or need additional information, please call me at 764-3570.
cc: Donnie Helmn, St. Matthews Baptist Church, 409 Holleman Drive, College
Station, TX 77840 (No attachment)
Case file #99-402
~ . rv, ~ s . ~ 5/~
i. ~~a
a ~
~ P~
~
3 , ~ ~ ~ l~~
C ~
5/aalq
i 0
J_t
h
F
nu Gt,~l 4-( C.i ~2k / fit t-2 G ; .
~Lfi4
3/3
cc ewe, a Lot scac-p-~,l, VL-
s~~!°'C.e-c~.9-e'-rti~~-c~
boa~
J .c~c~k
J
a ~-Q-t- ~
116c, cjutl~-C~-t
bt~ c~-GL~4
60 all,Lm
p~ o u~ L,
P-1-oum
Jessica Jimmerson - Re: New Submittals - 1/21/98 Page 1
From: Sabine McCully
To: Deborah Grace, Jane Kee, Jeff Kersten, Jessica
Date: 1/25/99 8:16AM
Subject: Re: New Submittals - 1/21/98
thank you jess, you're a BIG help!
Veronica Morgan 01/22/99 03:11 PM
jessica is reviewing the parking lot plan for the church.
Shirley Volk 01/21/99 02:07PM
Yesterday we received a plan for an existing gravel parking lot at St. Matthews Baptist Church on
Holleman to be paved. I looked up the original CUP number for this church, and it's 76-87. I've given
the new file (99-402) to Deborah to log in and to put in the plans check room for your review.
I checked on how we handled the parking lot under construction for the College Station Baptist Church,
and it was handled as a regular parking lot plan and not a CUP.
Also submitted today was drainage reports for both Johnny Carino's and Kona's Steakhouse (2 copies
each).
Deborah, as I understand it, you will be logging in each of these items as of today. Thanks.
CC: Jim Callaway, Natalie Ruiz
.1
DEVELOPMENT PERNIIT
PERMIT NO. 648
ST. MATTHEWS BAPTIST CHURCH
FOR AREAS OUTSIDE THE SPECIAL FLOOD HAZARD AREA
RE: CHAPTER 13 OF THE COLLEGE STATION CITY CODE
SITE LEGAL DESCRIPTION: SITE ADDRESS:
HRDLICKA SUBDIVISION, LOT 98110 BLOCK 3 409 HOLLEMAN DRIVE
OWNER
Thomas A Hall
409 Holleman Drive
College Station, TX 77840
(409) 775-0771
DRAINAGE BASIN: Bee Creek Trib B
TYPE OF DEVELOPMENT: SITE CONSTRUCTION AS PER APPROVED PLANS OF MAY 28,1999.
The required irrigation system is to be installed and operational concurrent with the completion and opening of the
parking lot.
The Contractor shall take all necessary precautions to prevent silt and debris from leaving the immediate
construction site in accordance with the approved erosion control plan as well as the City of College Station
Drainage Policy and Design Criteria. The Owner and/or Contractor shall assure that all disturbed areas are sodden
and establishment of vegetation occurs prior to removal of any silt fencing or hay bales used for temporary erosion
control. The Owner and/or Contractor shall also insure that any disturbed vegetation be returned to its original
condition, placement and state. The Owner and/or Contractor shall be responsible for any damage to adjacent
properties, city streets or infrastructure due to heavy machinery and/or equipment as well as erosion, siltation or
sedimentation resulting from the permitted work.
Any trees required to be protected by ordinance or as part of the landscape plan must be completely fenced before
any operations of this permit can begin.
In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall be taken to
insure that debris from construction, erosion, and sedimentation shall not be deposited in city streets, or existing
drainage facilities.
r ntative
OwnedAgent
5
Date
S- In), k-
Date
Contractor
Date
HASE.
E PROVIDED
BE PROVIDED:
) BE PROVIDED.
BUST BE
'ION SYSTEM.
•PP POWER POLE
- - -320- =•EXIS-TING CONTOURS
320-"" PROPOSED CONTOURS
tc, TOP OF CURB
sP TOP OF PAVEMENT
f0P OF WALK
PIc BACK OF CURB
1
(V oVg"y wtuerTr nn1~z' rn +NIMa l
IN LEGAL lT`' Q ,iee
NG SURFACE
IMPROVEMENTS flA W`TflI
t WOULD
MENTS. ~YG .
RE : ED F
4UIRED FOR Co LIA
►ND GRANTED. Mp 99
E E S ION
CES
LOPM ER
1` `may'... •
Vfrtff AP UNM
.
7
GRADIN~-G.
C
~L aY
t . Y
T' 4
trt41it1A~lX r
Exhibit A, Figure 3
REMOVE ENTIRE CURB AND
GUTTER SECTION
EXISTING
PAVEMENT
NEW DRIVEWAY
RESIDENTIAL DRIVEWAY
5' FLARE 10' RADIUS
MINIMUM SLOPE 5%
MAXIMUM SLOPE 10%
Zoning Ordinance Page 9 - 7
FXPANSInN .10INT
REINFORCED CONCRETE
6" THICK
#3 BARS 18" C-C
COLLEGE STATION
R O. Box 9960 1101 Texas Avenue College Station, TX 77842
Tel: 409 764 3500
MEMORANDUM
April 1, 1999
TO: DeAnna Ordonez, Garrett Engineering, Via fax # (409)846-3094
FROM: Bridgette George, Asst. Development Coordinator
i
SUBJECT: St. Matthew's Baptist Church Site and Grading Plan
Staff has reviewed the revised site and grading plan submitted and the following items
need to be addressed:
Draw in the appropriate phase line, calculate site area for landscaping
and streetscaping from that phase line;
Need to see the irrigation plan including water demand (maximum,
minimum, and average) in GPM. Irrigation system will need to be
installed and operational before parking lot is complete and open for use;
If the sidewalk in front of the church is going to be changed, then the
phase line will need to be 20 feet from the change, resulting in an "L"
shaped phase line for the parking lot and sidewalk changes. Also, any
additional impervious cover created by sidewalk changes would need to
be accounted for;
There needs to be a note to the effect that the throat width is never less
than 23 feet; and
Show paving details.
Please address all of the items listed above and submit the following for final approval:
Three (3) copies of the revised site plan; and
Development Permit application and $100 application fee.
If you have any questions or need additional information, please call me at 764-3570.
Thank you.
cc: Donnie Helmn, St. Matthews Baptist Church, 409 Holleman Drive, College
Station, TX 77840 (Case file #99-402)
Home of Texas A&M University
*:*****R*RfR*
I14 0
wl n
o
a
22!
woo
W
~ r
M
491V
W N
Q ~
W
W
4 U
~cc p v 1 `
L Y•
)
V
co
U I~
U
4J
x 44J r--4 U)
•rn~
Ott'
{d
,y.
11
En -dl 8
D
Z49LL xi'uORLIS 0601100 anuany saxal Lott 0966 x0H'Od
NOIIVLS 3D3330D
~ a
CITY OF COLLEGE STATION
CUSTOMER RECEIPT
OPER: MRODGERS CT DRAWER: 1
DATE: 1/20/99 00 RECEIPT: 0005886
DESCRIPTION QTY AMOUNT TP TM
FILING FEE/DS/BI 1 $100.00 *B7 CK
SITE PLAN APPLICATION
GARRETT ENGINEERING
SITE PLAN REVIEW
LH. 16885
TENDER DETAIL
CK $100.00
DATE: 1/20/99 TIME: 15:13:18
TOTAL PERSONAL CHECK $100.00
AMOUNT TENDERED $100.00
THANK YOU
CITY OF COLLEGE STATION
CUSTOMERR RECEIPT
OPER: MRODGERS CT DRAWER: 1
DATE: 5/24/99 00 RECEIPT: 0051594
DESCRIPTION QTY AMOUNT TP TM
FILING FEE/DS/DI 1 $100.00 *B7 CK
SITE PLAN
GARRETT ENG.-CK17106
SITE PLAN APP
ST. MATTHEWS
MR
TENDER DETAIL
CK 17186 $180.00
DATE: 5/24/99 TIME: 11:23:21
TOTAL PERSONAL CHECK $188.00
AMOUNT TENDERED $108.00
THANK YOU