Loading...
HomeMy WebLinkAboutMiscellaneousm. ENGINEER'S CONSTRUCTION COST ESTFMATE EDELWEISS ESTATES, PHASE 7-C JUNE 25, 1998 `~~ ~~ ~.9'' Item Description Unit Quantity Unit Price Total No. Paving Construction 1 Mobilization Lump Sum 1 $7,500.00 $7,500.00 2 Prepare Work Area Lump Sum 1 5,000.00 5,000.00 3 Earthwork Lump Sum 1 40,000.00 40,000.00 4 1.5" HMAC Surface Course S.Y. 10,417 4.50 46,878.62 5 6" Lime Stabilized Subgrade S.Y. .13,246 3.20 42,387.20 6 . Extra Lime Ton 88 90.00 . 7,920.00 7 6" Crushed Limestone Base S.Y. 5,549 5.95 33,016.55 8 7" Crushed Limestone Base S.Y. 4,868 6.75 32,859.00 9 Type 1 Curb and Gutter L.F. 1,977 7.50 14,827.50 10 Layback Curb and Gutter L.F. 3,475 7.50 26,062.50 11 Concrete Apron, Type A S.Y. 974 3.50 3,409.00 12 Concrete Apron, Type B S.Y. 6,760 3.50 23,660.00 13 4" Sidewalk S.F 20,425 2.75 56,168.75 14 Sidewalk Rams S.F 1,106 5.00 5,530.00 Pavin Subtotal ' $345,219.12 Drainage Construction 15 15" Reinf. Concrete Pipe, Structural Backfill L.F. 19 $36.00 $684.00 16 18" Reinf. Concrete Pipe, Structural Backfill L.F. 38 37.00 1,406.00 17 Backfill L.F. 11 23.00 253.00 18 21" Reinf. Concrete Pipe, Structural Backfill L.F. 144 41.00 5,904.00 19 Backfill L.E 233 28.00 6,524.00 20 24" Reinf. Concrete Pipe, Structural Backfill L.F. 453 45.00 20,385.00 21 27"Reinf. Concrete Pipe, Structural Backfill L.F. 209 55.00 11,495.00 22 30" Reinf. Concrete Pipe, Structural Backfill L.F. 32 67.00 2,144.00 23 10' Curb inlet EACH 7 2,750.00 19,250.00 24 5' Curb inlet EACH 8 2,000.00 16,000.00 25 Grate Inlet EACH 1 1,500.00 1,500.00 26 Sloped Headwall for 30" RCP EACH 1 1,000.00 1,000.00 27 Connect 30" RCP to Reinf. Concrete Box Culvert EACH 1 .500.00 500.00 28 Connect 27" RCP to Reinf.. Concrete Box Culvert EACH 1 500.00 500.00 29 Connect 24" RCP to Reinf.. Concrete Box Culvert EACH 5 500.00 2,500.00 30 Connect 21" RCP to Reinf. Concrete Box Culver t EACH 1 500.00 500.00 31 Connect 18" RCP to Reinf. Concrete Box Culvert EACH 2 500.00 1,000.00 32 Connect 15" RCP to Reinf. Concrete Box Culver t EACH i 500.00 500.00 33 Connect 24" RCP to Grate Inlet EACH 1 300.00 300.00 34 Remove and reinstall ex. 24" RCP` L.F. 16 20.00 32,0.00 35 Remove headwall for 24" RCP EACH 1 350.00 350.00. 36 Plu for 24" RCP EACH 2 300.00 600.00 Page 1 of 3 ' ENGINEER'S CONSTRUCTION COST ESTIMATE ~'~ TATES PHASE 7-C a EDELWEISS ES , ~~, JUNE 25, 1998 Item Description Unit Quantity . Unit Price Total No. 37 Plug for 21" .RCP EACH 1 300.00 300.00 38 Inlet Protection EACH 15 150.00 2,250.00 39 Silt Fence L.F. 1,000 2.00 2,000.00 40 Construction Exit for Silt Control S.Y. 25 10.00 250.00 41 Trench Safe storm drain L.F. 295 1.50 442.50 Drainage Subtotal $98,857.50 Water Line Construction 41 8" PVC Water Line, Non-Structural L.F. 965 $16.00 $15,440.00 42 8" PVC Water Line, .Structural Backfill L.F.. .165 3:0.00 4.,950.00 43 6" PVC Water Line, Non-Structural L.F. 1,622 14.00 22,708..00 44 6" PVC Water Line, Structural Backfill L.F. 292 28.00 8,176.00 45 6°' PVC Water Line Inserted in Existing Steel Ca. L.F. 150 20.00 3,000.00 46 Fire Hydrant Assembly, Type I EACH 2 1,800.00 3,600.00 47 Fire Hydrant Assembly, Type II EACH 2 1,800.00 3,600.00 48 8" Gate Valve EACH 3 650.00 1,950.00 49 8"x 13" Anchor Coupling EACH 4 175.00 700.00 50 8"x 6" Cross EACH 2 250.00 500.00 51 8"x 6" Tee EACH 2 300.00 600.00 52 8"x 45 deg.. Bend ,EACH 2 250.00 500.00 53 8"x 11.25 deg. Bend EACH 2 200.00.. 400.00 54 8" Retainer Glands EACH 7 50.00 350.00 55 Connect to Existing 8" Line EACH 2 100.00 200',00 56 6" Gate Valve EACH 8 400.00 3,200.00 57 6"x 13" Anchor Coupling EACH 10 100.00 1,000.00 58 6"x 18" Anchor Coupling EACH 2 175.00 350.00 59 6"x 24" Anchor Coupling EACH 1 300.00 300.00 60 6"x 48" Anchor Coupling EACH 2 400.00 800.00 61 6"x 60" Anchor Coupling .EACH 1 600.00 600.00 62 6"x 45 deg. Bend EACH 14 200.00 2,800.00. 63 b"x 11.25 deg. Bend EACH 1 125.00 125.00 64 6"x 6" Tee EACH 2 100A0 ' 200.00 b5 6"x 1.5" Tapped Tee EACH 2 100.00 200.00 66 6" Plug EACH 2 150.00 300.00 67 6" Retainer Glands EACH 9 50.00 450.00 68 2" Blow-Off Assembly EACH 1 500.00 500.00 69 1" Type K Copper Water Ser. <10 ft. (T Avg. Le EACH 1 300.00 300.00 70 1" Type K Copper Water Ser. >10 ft. (49.3' Avg. EACH 3 750.00 .2,250.00 71 1.5" Type K Copper Water Ser. < 55 ft. (52.9' Av EACH 11 750.00 8,250.00 72 I.5" T e K Co er Water Ser. > 55 ft. 70' Av . EACH 2 800.00 1,600.00 Page 2 of 3 ' ENGINEER'S CONSTRUCTION COST ESTIMATE EDELWEISS ESTATES, PHASE 7-C JUNE 25, 1998 Item Description Unit Quantity Unit Price Total No. 73 Remove existing blow-off assembly EACH 2 250.00 500.00 74 Trench Saf (water line L.F.. 1,875 1.00 1,875.00 Water Line Subtotal $92,274.00 Sewer Line Construction 74 6" PVC, ASTM D-3034, non-structural backfill L.F. 1,274 $14.00 $17,836.00 75 6" PVC, ASTM D-3034, structural backfill L.F. 194 32.00 6,208.00 76 6" PVC, ASTM D-2241, structural backfill L.F. 119 34.00 4,046.00 77 Standard Manhole, 6-8 ft. deep EACH 3 1,250.00 3,750.00 78 Standard Manhole, 8-10 ft. deep EACH 4 1;500.00 6,000.00 79 Adjust Manhole Top EACH 3 500.00 1,500.00 80 4" PVC Sewer Service, Type I, < 10 ft., (6.5 ft. a~ EACH 3 300.00 ..900.00 81 4" PVC. Sewer Service, Type I, > 10 ft., (47 ft. av EACH 5 850.00 4,250.00 82 4" PVC Sewer Service, Type II, < 10 ft., (7.2 ft. a EACH 3 300.00 900.00 83 4" PVC Sewer Service, Type II, > 10 ft., (73.4 ft. EACH 4 800.00 3;200.00 84 Trench Safe sewer line L.F. 1,675 1.50 2,512.50 Sewer Line Subtotal $51,102.50 Total Construction Cost $587,453.12 Page 3 of 3 ~, . - ~~ ./lwnl 1 InC Chll'_*9f~ICCC?IAI(~ If~l(~ ®~ IVIIrVLV1i1_ L_Itl~.1~iv"........., ...v. June 8, 1998 Mrs. Natalie Ruiz Assistant Development Coordinator CITY OF COLLEGE STATION P.O. Box 9960 College Station, Texas 77842 RE: Edelweiss Estates, Phase 7-C Final Plat 6/2/98 Staff Comments Letter Dear Natalie: I have reviewed the staff comments on the above referenced final plat. The two items that were listed will be taken care of before the mylar is submitted for filing. As requested, attached please find ten (10) blueline prints of the plat. The mylar will be submitted as soon as the signatures are obtained and the two conditions have been met. Should you have any questions, please advise. Very truly yours, ~~~~~ chael R. McClure, P.E., R.P.L.S. MRMlmlm attachments 1722 Broadmoor, Suite 210 Bryan, Texas 77802 (409) 776-6700 FAX (409) 776-6699 \ MINIMUM REp UIREMENTS FOR FINAL PLATS ~~ ``~~ (ALL CTI'Y ORDINANCES MUST BE METl ~ INCLTJ~ING BUT NOT LIMITED TO THE FOLLOWING: (Re uirernents based on field survey and marked by monuments and markers) ~~ 1. Drawn on 24" x 36" sheet to scale of 100' per inch. /~ a. vicinity map which .includes enough of surrounding area to show general location of subject property in relationship to College Station and .its City Limits. No scale requred but include north arrow. ~~ 2. Name & address of subdivider, recorded owner, planner, engineer -and surveyor. / ~ 3. Name & address of all lenders on the property. / 4. Name & address of all easement holders. C~'' S. Proposed name of subdivision (not spelled or pronounced similarly to any other subdivision f in Brazos County, Texas). ~/ ~ 6. Date of preparation, scale in feet and north arrow.. ~~ 7. Application fee. +~~. 8., Construction documents on 24" x 36" sheets. ~~--~ 9. Paid tax certificates from City of College Station, Brazos County and the C.S.LS.D. ~C'd'~~~- 10. Tgtal area intended to be developed. ~~'" 11. Subdivision boundary lines indicated by heavy lines... - 12. .fie >ificate of Ownership & Dedication; ~` rcate of Surveyorship and/or Engineer; ~.~e~~>ficate of City Engineer, /Approval of Commission; /~~- proval of City Council; '"Certificate of the County Clerk. + (Owner(s)' signature(s) must be in place before taking plat to P&Z for consideration). ~~'®''" 13: Number of lots. number of lots by Zoning District. li~ b.-average acreage of each residential lot by Zoning District. ~C~}-"`" 14. Approximate area of street right-of-way. ~~ 15. Proposed parkland dedication information. 16. Requested oversize participation. items, if any.. `-~~ 17. Location of the One Hundred Yr. Floodplain according to the most recent available date- N/~ 18. If-more than 1 sheet, an index sheet showing entire subdivision at a scale of 500 feet per inch. ;g " ~ 19. Exact location,. dimensions, name and legal description of all existing or recorded streets, alleys, reservations, easements or other R.O.W. within the subdivision, intersecting or contiguous~with boundary or forming boundary with accurate dimensions, bearings or deflection angles and radii, area, center angle, degree of curvature, tangent distance and length of all curves. 20. Same information for proposed streets, alleys, etc. as preliminary plats. ~ '~~ data i ied t b d b l ® 21. . c survey as o ) an t o Lot corner markers and survey monuments (by sym ~~®--'~" 22. Street, alley, and sidewalk plans, profiles and sections, with specifications and detail cost estimates. ~-~`~ 23. Sanitary sewer plat with 2 foot contours, plan and profile lines, showing depth and grades, with cost estimates. "Et" 24. Water line plat showing fire hydrants, valves, etc. with specifications and a detailed cost estimate. ~~ 25. Storm drainage system plat with 2 foot contours, street lines, inlets, storm sewer and drainage channels, with profiles and sections, and showing drainage and runoff areas, and runoff based on 5, 10, and 25 year rain intensity. Detail drainage structure design .and channel lining. design if used, with specification and .detail cost estimate. ~' ,~.~ 26. ~ Street lighting plan showing location of lights, design,. and with specifications anti detail cost l .estimate. 27. Submit a statement addressing any differences between the final plat and approved Master Preliminary Plat & Plan. ~~"` 28. Indicate any variances requested and reasons for same. ~~ ~~ 30. Are there i pact fe associated with this development i~ ~ n~' 31. Add a general note that no private sewage facility may be installed on any lot in this subdivision without the issuance of a license by the Brazos. County Health Unit under the :provisions of the private facility regulations adopted by the Commissioners Court of Brazos County, pursuant to the provisions of Section 21.004 of the Texas Water Code. ~~ a~~a~~ McCLURE ENGINEERING, INC. June 19, 1998 Mr. Paul Kaspar City of College Station P.O. Box 9960 College Station, TX 77842-9960 RE: Edelweiss Estates Phase 7C Water Distribution Study Dear Paul: ~~~~ r~ t1~bC1--~ ~-- ~'"~' ~~~ ~ p~~,~ . ,~-- f The fire flow study you requested in your redline comments was entitled WATER DISTRIBUTION AND SEWER IMPACT STUDIES FOR EDELWEISS ESTATES AND ROCK PRAIRIE ESTATES and completed in October of 1994. The study was based on the master plan lot layout which has been slightly modified with phase 7C. Please note that the changes to the layout (looping some water lines and decreasing the lot density) will improve the fire flows throughout the subdivision. With that report, we studied the most hydraulically remote nodes and did not attempt to calculate the flows of every hydrant. From that study, I see that the most remote node had 65 psi under fire flow conditions, well in excess of the required 20 psi. Based on that study, I feel that we have complied with the requirements of the City of College Station for fire flows. Should you have any questions or clarifications on any of the above issues please notify us. Very truly yours, /~~~ oel J. Mitchell, P.E. Chief Design Engineer Enclosures JJM/mlm F:\VR\P7C\DOCUME~l\FII2EFI.OW. WPD ® .• ~'; JOELJ. MITCHELL •~~~oooootoosootoosoi ('O~~ $0649 ~0~•;~p1g~Q-~ ~tw4`~a~ ~KMtiLLE~ 1722 Broadmoor, Suite 210 Bryan, Texas 77802 {409) 776-6700 FAX (409) 776-6699 ~~ TRANSMITTAL LETTER MCCLURE ENGINEERING, INC. 1722 BROADMOOR, SUITE 2 I O ~~~ BRYAN, TEXA$ .77802 ,~;~~~* (409> 776-67007\'~_r/" ~i~~ FAx: (409) 776-6699 ~`~+ DATE: June 26,1998 TO: Mr. Paul Kaspar Development Services Department CITY OF COLLEGE STATION FROM: Michael R. McClure, P.E., R.P.L.S. PROJECT NAME: EDELWEISS ESTATES, PHASE 7-C COMMENTS: Attached please find the following: 1. One (1) set of construction plans, revisedper staffred-line comments ~ 2. Two (2) sets of staff red-lined construction plans t/ 3. Water Distribution Letter 4. Two (2) copies of Engineer's Construction Cost Estimate Please review the revised set against the staff red-lined sets. If they. are OK, I will forward additional sets for your use and for the contractor's use on the job. Paul Kaspar Re `Edelweiss Phase 7c From: Paul Kaspar To: "McClure cLDmyriad.net"City of College Station.SMTP Date: 6/17/98 3:44PM Subject: Re: Edelweiss Phase 7c Joel, In response to your email attached below: 1. You are correct. 1 may have missed it, but as 1 recall, the reason for the comment was that there appeared to be an area that did not drain to a protected inlet. If that is not the case, then dis-regard the comment. 2. 1 was unaware of that Master Fire Flow study being perforr»ed, that was a "little bit" before my time here at the City. r) 1 went and pulled the file and it contained the original impact study with a revision in 1994. The 1994 revision was based on street layout changes and an upgrade to a 12 inch line, wrhich was to improve the situation. The streef layout has changed in Phase 7-C since the 1994' update. That update did not provide an updated waterline layout and it is difficult to determine if the waterline "KYPIPE"layout and sizes have remained generally the same as in the study. If you can show that they have. or provide an addendum or letter to those reports that would clarify the issue, those original reports can be used. Please call me 'on this one if you have a befter way of taking care of this, who knows, I could be looking at the wrong study as well This study was the one entitled "~Iliams Park and Rock Prairie Estates" -which as l understand it has become Edelweiss.. The update was entitled "Edelweiss Estates and Rock Prairie Estates." 3. The comment was made since some sheets showed the service connections and others did not. There is no requirement for showing those connections; however in cases where the7ocation of existing or proposed sidewalks. will conflict with making connections to those service lines, we have asked for those to be shown on the plans. to assure that sidewalks will not have to be "ripped up" in order to make the connection. As Veronica mentioned to me, Cypress Meadows would be an example. In this case you are correct, it is not a requirement, but if a conflict with sidewalks or other utilities exist, we would like to see them shown. 4. No, it is acceptable. 1 was .unaware that we had accepted 4' wide 4' back of curb previously. In fact looking at our future design guidelines it specifically spells it out that way in residential areas. It is my understanding"that we accepf it only in residential areas, though. 1 think you have answered all my concerns on these comments except for number 2, if you have any questions call me. Thanks. PK »> "Joel J. Mitchell" <McClure cLDmyriad.net> Of~16/9810:23AM »> Pauf Some quick and easy questions on your comments: 1. On sheet 1 (overall and SWPPP) you comment to show silt fence downstream of grading. My understanding of the requirements is that all graded areas must be "protected", so wherever possible, I show Inlet Protection where stormwater from the graded area would enter the storm drain. Is this not legal? 2. Also on sheet 1, .you. ask for fire flow calculations.. We did afire flow study for this area with the Impact Studies when we did the master ~~Page 2 ', ~ Paul Kas ar Re• Edelweiss Phase 7c plan. The character of development has not changed: why do we need to resubmit the same data? 3. You call for us to show a sewer service on all lots. I know that the new standards wilF require this,. but they are- not in place yet. I have rovided a way for each lot to sewer, but in many cases the plumber must p tap the main. Is this not acceptable? 4. You ask about the locations of sidewalks on the 28' streets. Per our previous discussion we have been putting the sidewalks 4' from the back of curb. Is this no longer acceptable? Please call if we need to discuss these Items. Joel j CC: Veronica. Morgan .`~ ENGINEER'S. CONSTRUCTION :COST ESTIMATE ,k~ ~' :EDELWEISS ESTATES, PHASE 7-C ~f,~,0''1~~~' ~` JUNE 25, 1998 ' " ~ ~` Item Description Unit Quantity Unit Price Total No. Paving Construction 1 Mobilization L ump Sum 1 $7,500.00 $7,500.00 2 Prepare Work Area L ump Sum 1 5,000.00 5,000.00 3 Earthwork Lump Sum 1 40 ,000.00 40,000.00 4 5" HMAC Surface Course 1 S.Y. .10,417 4.50 46,878.62 5 . 6" Lime Stabilized Subgrade S.Y. 13,246 3.20 42,387.20 Ton 88 90.00 7,920.00 6 Extra Lime Y S 5,549 5.95 33,016.55 7 6" Crushed Limestone Base . . 8 7" Crushed Limestone Base S.Y. 4,868 6.75 32,859.00 9 Type l Curb and Gutter L.F. 1,977 7.,50 14,827.50 10 Layback Curb and Gutter L.F. 3,475 7.50 26,062.50 11 Concrete Apron, Type A S.Y. 974 3:50 3,409.00 12 Concrete Apron, Type B S.Y. 6,760 3',.50 23,660.00 F S 425 20 2.75 56,168.75 13 4" Sidewalk . F S , 106 1 00 5 5,530.00 14 Sidewalk Rams . ., . 12 Pa vin Subto tal $345,219. Drainage Construction 15 15" Reinf. Concrete Pipe, Structural Backfill L.F. 19 $36.00 $684.00 16 18" Reinf. Concrete Pipe, Structural Backfill L.F. 38 37.00 1,406.00 L.F 11 23.00 253.00 17 Backfill . 18 21" Reinf. Concrete Pipe, Structural Backfill L.F. 144 41.00 5,904.00 L F 233 28.00 6,524.00 19 Backfill . . 20 24" Reinf. Concrete Pipe, Structural Backfill. L.F. 453 45.00 20,385.00 21 27" Reinf. Concrete Pipe, Structural Backfill L.F. .209 55.00 11,495.00 22 30" Reinf. Concrete Pipe, .Structural. Backfill. L.F. 32 67.00 2,144.00 23 10' Curb inlet EACH 7 2,750.00 19,250.00 24 5' Curb inlet EACH 8 2,000.00 16,000.00 25 Grate Inlet EACH 1 1,500.00 1,500.00 26 Sloped'Headwallfnr 30" RCP EACH 1 1,000.00 1,000.00 27 Connect 30" RCP to Reinf. Concrete Box Culvert EACH 1 500.00 500.00 28 Connect 27" RCP to Reinf. Concrete Box Culvert EACH 1 500.00 500.00 29 Connect 24" RCP to Reinf. Concrete Box Culvert EACH 5 .500.00 2,500.00 30 Connect 21" RCP to Reinf. Concrete Box Culvert EACH 1 500.00 500.00 31 Connect 18" RCP to Reinf Concrete Box Culvert EACH 2 500.00 1,000.00 32 Connect I S" RCP to Rein£ Concrete Box Culvert EACH 1 500.00 500.00 33 Connect 24" RCP to Grate Inlet EACH I 300.00 300.00 34 Remove and reinstall ex. 24" RCP L.F. 16 20.00 320.00 35 Remove headwall for 24" RCP EACH 1 350.00 350.00 36 Plu for 24" RCP EACH 2 .300.00 600.00 Page 1 of 3 ENGINEER'S CONSTRUCTION-COST ESTIMATE ' EDELWEISS ESTATES, PHASE 7-C JUNE 25, .1998 Item Description Unit Quantity Unit Price Total No, EACH 1 300.00 300.00 37 Plug for 21" RCP EACH 15 150.00 .2,250.00 38 Inlet Protection 1,000 2.00 L.F 2,000.00 39 . Silt Fence 25 10.00 Y S 250.00 40 . . Construction Exit for Silt Control 41 Trench Safe storm drain L.F. 295 1.50 442.50 Drama a Subtotal $98,857.50 Water L ine Construction 41 g " PVC Water Line, Non-Structural L.F. 965 $16.00 $15,440.00 42 8 " PVC Water Line, Structural Backfill L.F.. 165 30.00 4,950.00 43 6 " PVC Water Line, Non-Structural L.F.. 1,622 14.00 22,708.00 44 6" PVC Water Line, Structural Backfill L.F. 292 28.00 8,176.00 45 6" PVC Water Line Inserted in Existing Steel Ca. L.F. 150 20.00 3,000.00 0 46 Fire Hydrant Assembly, Type I EACH 2 1,80Q.00 3,600.0 47 Fire Hydrant Assembly, Type II EACH 2 .1,800.00 3,600.00 EACH 3 650.00 1,950.00 48 8" Gate Valve EACH 4 175.00 700.00 49 8"x 13" Anchor Coupling EACH 2 250.00 500.00 50 8"x 6" Cross 00 EACH 2 300.00 600. 51 8"x 6" Tee EACH 2 250.00 500.00 52 8"x 45 deg. Bend 53 8"x 11.25 deg. Bend EACH 2 200.00 400.00 54 8" Retainer Glands EACH 7 50.00 350.00 55 Connect to Existing 8" Line EACH 2 100.00 200.00 EACH 8 400.00 3,200.00 56 6"Gate Valve EACH 10 100.00 1,000.00 57 6"x i3" Anchor Coupling 58 6"x 18" Anchor Coupling EACH 2 175.00 350.00 59 6"x 24" Anchor Coupling EACH 1 300.00 300.00 60 6"x 48" Anchor Coupling EACH 2 400.00 800.00 61 6"x 60" Anchor Coupling EACH 1 600.00 600.00 62 6"x 45 deg. Bend EACH 14 200.00 2,800.00 63 6"x i 1.25 deg. Bend EACH 1 125.00 125.00 64 6"x 6" Tee EACH 2 100.00 200.00 65 6"x 1.5" Tapped Tee EACH 2 100.00 200.00 6b 6" Plug EACH 2 150.00 300.00 67 b" Retainer Glands EACH 9 50.00 450.00 68 2" Blow-Off Assembly EACH 1 500.00 500.00. 69 1" Type K Copper Water Ser. <10 ft. (T Avg. L e: EACH 1 300.00 . 300.00 70 1" Type K Copper Water Ser..>10 ft. (49..3' Avg. EACH 3 750.00 2,250.00 71 1.5" Type K Copper Water Ser. < 55 ft. (52.9' A v EACH I 1 750.0 0 8,250.00 72 i.5" T e K Co er Water Ser. > 55 ft. 70' Av . EACH 2 800.0 0 1,600.00 Yage l of j ENGINEER'S CONSTRUCTION COST ESTIMATE } EDELWEISS ESTATES, PHASE 7-C JUNE 25, 1998 Item Description Unit Quantity Unit Price Total No. 73 Remove existing blow-off assembly EACH 2 250.00 500.00 74 Trench Safe .water line L.F. 1,875 1.00 1,875.00 Water Line Subtotal $92,274.00 '~~Vl L 74 aaav vv~..----___ ASTM D-3034, non-structural backfill 6" PVC L.F. 1,274 .$14.00 $17,836.00 75 , ASTM D-3034, structural backfill b" PVC L.F. 194 32.00 6,208°00 76 , ASTM D-2241, structural backfill 6" PVC L.F. 119 34.00 4,046.00 77 , Standard Manhole, 6-8 ft. deep EACH 3 1,250.00 3,750.00 78 Standard Manhole, 8-10 ft. deep EACH 4 1,500.00 6,000.00 79 Adjust Manhole Top EACH 3 500.00 1,500.00 80 4" PVC Sewer Service, Type I, < 10 ft., (6.5 ft. a EACH 3 300.00 :.900.00 81 4" PVC Sewer Service, Type I, > 10 ft., (47 ft. av EACH 5 850.00 4,250.00 82 4" PVC Sewer Service, Type II, < 10 ft., (7.2 ft. a EACH 3 300.00 900.00' 83 4" PVC Sewer Service, Type II, > 10 ft., (73.4 ft. EACH 4 800.00 3,200.00 84 Trench Safe sewer line L.F. .1,675 . 1.50 2,512.50 Sewer Line Subtotal $51,102.50 Total Construction Cost $587,453.12 Page 3 of 3 ,~.,, ._ , JHN-~~-1 yyy ~ r~u 1 1 ~ ~ t HI'I l:. ~. t'UtfL 1 C WUKKJ h HX NU. 4Uy +dy ~yn~ N, U~ LETTER OF COMPLETION CITY ENGINEER CITY OF COLLEGE STATION COLLEGE STATION, TE.~AS DATE: RE: COMPLETION OF_ Edelweiss Estate Phase 7-C _ _ dear Sir: ur ose of our letter is to request that the .following listed improvements be approved The p p and accepted as being constructed under. city inspection and completed acco~diX g to"I`h sns and specifications as approved and requireuest din olyderf thatlrwe may finalize any sub- approval and acceptance by.the C~.ty is req contracts and to affirm their warranty on the work. ~ This approval and rant e for the the City of the improvements listed below does hereby ~ oid the letter of ~ listed improvements on the above reference project. Young Contractors and The one year warranty is horby affirmed and agreed to by by their sub-contractors as indicated by signatures below. WORK COMPLETED Edelweiss Ave. Augsburg LA. Bernbu LA. Gleeson DATE Storm Sewer Water Line Sanitary Sewer Owner: Be onia Cor Address: 4103 Texas Avenue Contractor' Young Contractors P.O. Box 674 Address: Bryan, TX 778050000 Bryan, TX 77802 Signatur `~~ ~ / Signature: ;~~ - / . F ?~( ; ~~ ~- ~ f 4 ~ ~ 2 ~' J- lily 1 resenla.liue ACCEPTANCE & APPROVAL it,~ City l~,n~inecr N ..~. :~t ' ~. is ;• :~~ :y ,'y~ 'in '~y ~~~~ ~~W COLLEGE STATION P. O. Box 9960 1101 Texas Avenue Tel: 409 764 3500 MEMORANDUM College Station, TX 77842 TO: Mike McClure, McClure Engineering ' FROM: Natalie Ruiz, Assistant Development Coor i for DATE: June 2, 1998 ~; Edelweiss Estates Phase 7-C Final Plat. Staff reviewed the above mentioned final plat and had the following two comments: Note the volume and page number of the off-site 10' public utility easement ® located along the .south side of Edelweiss Avenue. This easement must be filed for record prior to filing the final plat. ® Impact fees are required for this phase of Edelweiss Estates. The total amount due prior t® filing is $12,170.34 ($289.77 x 42 lots ° $12,170.34). Please address the comments above and submit the following information by noon on Tuesday, June 9, 1998: 10 copies of the revised final plat; and, the revised mylar original. The Planning and Zoning Commission meeting will be at 7:00 p.m. on Thursday, June 18, 1998 in the City Hall Council Room, 1.101 Texas Avenue South. If you have any questions. er need additional information, please call me at 764®3570. Thank you. cc: Steve Arden, Brazosland Realty, 4103 South Texas Avenue, Suite 100, Bryan, TX 77802 Jim Crowell, Begonia Corporation, 1901 San: Jacinto, Houston, TX 77002 Case file #98-219 Home of Texas A&M University