PROJECT REVIEW COMMITTEE REPORT
July 23, .1997
TO: W. C. Scarmardo
2402 Broadmoor, D-1, Suite 102, Bryan, TX
FROM: Project Review Committee
Jane Kee, City Planner
Kent Laza, City Engineer
Ron Silvia, P&Z Representativ
Others Attending
Natalie Thomas, Planning Technician
Shirley Volk, Development Coordinator
Jon Mies, Fire Marshal
Tony Michalsky, Electrical Operations Coordinator
Laverne Akin, GTE Representative
SUBJECT: Parking Lot Plan - Kapser Office Park; proposed three office buildiings totaling
13,735. square feet to be located at 524 University Drive, south of Audio Video
and David Gardner Jewelers. (97-419)
A Project Review Committee meeting was held Wednesday, July 23, 1996 to discuss the above
mentioned parking lot plan. City Engineer Laza moved to approve. the site plan with the
following ordinance requirements and comments. The following is a list of ordinance
requirements and comments identified by the Project Review Committee. This list does not
relieve the applicant of total compliance with all current ordinance requirements.
CONDITIONS OF APPROVAL
Ordinance Requirements:
Sheet C-1
_ Provide a legend of symbols.
Provide utility demands for the new construction. (Include domestic. and irrigation water
demands in maximum gallons per minute and sewer demands in average gallons per day.)
The existing dumpster ize and location will need to be analyzed for the entire site.
Show the fire lane. markings throughout the site.
Show existing and proposed utilities and their location. Label the fire hydrants as existing
or proposed.
Show the location of water meters.
Note that the overhang in the fire lane must have a minimum 14' clearance.
Sheet ME-L•
Show the location of the water. and sanitary sewer service lines.
J
PRC Report
Case #97-419
Page 2 of 2
Ordinance Requirements (cont.):.
Sheet C-2:
Submit a drainage. report for the site.
_ Provide a drainage analysis of the 12" pipe between David Gardner's and building A to
ensure capacity.
Show where the 6" storm pipe near the front of building A drains.
Remove the. following note from sheet C-2 and place on sheet C-1 "This project is not
located in a 100 year flood plain".
Comments/Concerns:
_ Note on the landscape plan that any areas disturbed during construction must be returned
to the natural condition.
_ Coordinate the electrical service requirements with Electrical Operations .Coordinator
Tony Michalsky at (409) 764-3660:
_ The developer/owner. is responsible. for providing and placing two 4" conduits with pull
string from each building to the existing overhead line along the northwest side of the
property. The conduits shall stub up 4' of the outside building location and 6" at the
power pole.. The conduits shall have no sharp bends. Outside termination shall be within
20' of power - if not, the owner is responsible for providing and placing a 8' x 5/8" copper
ground rod at the base of the outside termination. GTE's termmnation (DMARC) will be
on the outside of each building. Coordinate details with Laverne Akin at (409) 821-4723..
_ Gas service is available to all three buildings. Coordinate details with Lone Star Gas
Representative Don Fazzino at (409) 776-0627.
Planning and Zoning Commission Representative Silvia seconded the motion to approve the site
plan with the above mentioned conditions which. passed unopposed (3 - 0).
SUBMIT 4 COMPLETE SETS OF CONSTRUCTION DOCUMENTS WITH THE REVISED
SITE PLAN ATTACHED AND 3 COPIES OF THE REVISED SITE PLAN & LANDSCAPE
PLAN ONLY TO CONTINUE WITH PHASE II OF THE. BUII,DING PERMIT PROCESS:
COORDINATE DETAILS WITH DEVELOPMENT COORDINATOR SHIRLEY VOLK AT
(409) 764-3570..
APPEAL PROCESSt An applicant may appeal the decision of the Project Review Committee
to the Planning and Zoning Commission within five days after the PRC Committee meeting.
Failure to appeal the PRC action shall constitute a contractual .acceptance of all conditions
imposed, and a waiver and surrender of all complaints, defects, or potential invalidity, whether
under state or federal law.: An applicant. appealing the decision of the PRC shall file ten. copies of
the final site. plan as approved by the PRC, showing all changes. and requirements imposed by the
PRC, and accompanied by a written explanation of those items being appealed: Until said copies
are on file, no further development approval shall occur, and no further action by the Commission`
shall .take.. place. An applicant may appeal only certain aspects of site plan review, and in the
absence of discretionary review by the Commission, or review pursuant to a petition, all other
aspects of the site plan shall be final. Any notice of appeal shall state with particularity the aspects
which are to be appealed, Coordinate. appeal process through :Development Coordinator Shirley
Volk at (409) 764-3741.
~~~pFT
«-a )
~ .2~~
STAFF NOTES ~ ~ ~ ~`2.
Kapser Office Park ~~~~~-
Case #97-419 1 i ~-
Ordinance Requirements: ~ C n ~ ``
a- ~~
Sheet C-1
r2~ ~.
~/ Provide a legend of symbols. _ ln~~ ~~
1~~
Provide utility demands for the new construction. (Include domestic and irrigate n water
demands in maximum gallons per minute and sewer demands in average gallons per day.)
The exi ing du ps er size and location will need to be anal zed for the entire site.
c,~ ~~
Show the fire lane marlcmgs throughout the site.
Show existing and proposed utilities and their location. Label the fire hydrants as existing
or proposed.
Show the location of water meters.
pmg is sed ctly ove ater line.
Sheet C-2:
Submit a drainage report for the site.
Provide a drainage analysis of the 12" pipe between David Gardner's and building A to
ensure. capacity.
Show where the 6" storm pipe near the front of building A drains.
Remove the following note from sheet C-2 and place on sheet C-1 "This project is not
located in a 100 year flood plain".
/~ Sheet ME-1:
~/ Show the location of the water and sanitary sewer service lines.
Comments/Concerns:
_~ There are several .notes on sheet C-5 and ME-1 that must be addressed. Resubmit the
redlined sheet'with the revised drawings.
_~ Coordinate the electrical service requirements with Electrical Operations Coordinator
Tony Michalsky at (409) 764-3 660:
Coordinate necessary easements, conduit placement and t lephone service details with
G.T.E. Representative Laverne Akin at (409) 821-4723. ~ ~ .
_/ Gas service is available to all three buildings. Coordinate details with Lone Star Gas
Representative Don. Fazzino at (409) 776-0627. ~ ~ ~~~~
SUBMIT 4 COMPLETE .SETS OF CONSTRUCTION DOCUMENTS WI'~il~-i-i THE REVISED
SITE PLAN ATTACHED AND 3 .COPIES OF THE REVISED SITE/PLAN ONLY TO
CONTINUE WITH PHASE II OF THE BUII,DING PERMIT PROCESS. COORDINATE
DETAILS WITH DEVELOPMENT COORDINATOR SHIRLEY YOLK AT {409) 764-3570.