PROJECT REVIEW COMMITTEE REPORT
July 20, 1994
TO: George McLean, Director of Operations
2000 Welsh Avenue, College. Station, TX 77840
Harry W. Bostic
4500 Carter Creek Parkway, Bryan, TX 77802
FROM:. Project Review.Committe
Jane Kee, City Plan
Brett McCully,. Project ineer
Mike Lane, P&Z Representative
Others Attending
Natalie Thomas, Planning Technician
Shirley Volk, Development Coordinator
Samantha Smith, Engineering Assistant
Don Lusk, Electrical Line Coordinator
Tim DeDear, Fire Protection Specialist
SUBJECT: Parking Lot Plan. - A ce: M Consolidated High School; .proposed addition of portable
buildings to be located along the F.M. 2818 frontage road near the teacher's parking lot.
(94-413)
A Project Review Committee Meeting was. held Wednesday, .July 20, .1994 to discuss the above mentioned
parking lot plan. The Committee recommended approval of the final. plat as submitted with the following
conditions:
CONDITIONS OF APPROVAL:
Discretionary .Items:
The. proposed portable buildings should be painted so that they blend with the existing site and
are aesthetically. pleasing from F.M. 2818.
The Committee suggested that the proposed landscape timbers be removed and the proposed
shrubs spread .out along the frontage for more effective screening of the addition.
Ordinance Requirements:
_ Relocate the proposed fire hydrant to align with the center parking. aisle so that it is not
potentially blocked. by occupied parking spaces. ,Construction documents prepared by a registered
..professional engineer must be reviewed 'and approved by staff prior to installation of the
proposed fire ,hydrant. The fire hydrant must be installed and operable prior to moving the
temporary buildings. on site.
r w
PRC Report
A&M Consolidated
Case #94-413.
Page Z of Z
CONDITIONS OF APPROVAL. (cons):
Comments/Concerns:
_ This item. will not require a formal conditional use ..permit request due to the proposed use of the
buildings and. the size of the expansion compared to the overall site.
_ A representative of CSISD should meet with Electrica Operations Coordinator Tony Michalsky
at (409) 764-3660 to determine electrical service needs.
COORDINATE. FUTURE CONSTRUCTION PLAN SUBMITTAL WITH DEVELOPMENT
COORDINATOR SHIRLEY YOLK AT (409) 764-3570.