HomeMy WebLinkAboutMinutes.- `~. PROJECT REVIEW CONIIVIITTEE REPORT March 25, 1993 TO: Ray Mart,. Inc., Ken. Riggs 3800. Texas Avenue South, College Station, TX 77845 Constantin Barbu 1722 Broadmoor, Ste 100, Bryan, TX 77802 FROM: Project Review Committee: Sabine Kuenzel, Staff Planner Veronica Morgan, .Assistant to the City Engineer Mike Lane, P & Z Representative Others Attending: .Natalie Thomas, Planning Technician Samantha Smith, Engineering Assistant Tony Michalsky, Electrical Operations Coordinator Shirley Volk, Development Coordinator Ed Hard, Transportation .Planner Brad Clark, Fire Inspector Laverne Akin, GTE Representative SUBJECT: PARKING LOT PLAN. - .Ray. Mart; proposed change in use of approximately 20,000 square feet from warehouse storage to sales area. (93-404) The Project Review Committee met on Wednesday, March 24, 1993 to discuss the above mentioned parking .lot plan. Staff reviewed the plan with the assumption that the variances requested to the parking number and setback requirements are granted. If the variances are not granted, a revised site plan must be submitted for further review and approval. The following comments were made by the various reviewing agents: ENGINEERING: _ Submit. a letter stating that there will not be increased runoff in order to obtain a drainage development permit. Coordinate details with Assistant to the City Engineer Veronica Morgan. at (409) 764-3570. _ Construction documents .will be needed for all new water. lines and the fire sprinkler vault. ELECTRICAL: _ Show the transformer location and where the service connects to the building. _ Show all underground utility lines and pole locations. Coordinate locations with Electrical Operations Coordinator Tony Michalsky at (409) 764-3660.. Show all public utility easements. PRC Report Ray Mart Case #93-404 Page 2 FIRE• All areas of the building must be within 300' of a fire hydrant (as the hose lays). Coordinate fire hydrant coverage and details with Fire Inspector George Spain at (409) 764-3781. _ Designate fire lanes within the parking lot. _ Show the proposed sprinkler vault. The proposed fire sprinkler line, vault and any additional fire hydrants must be located within easements. WATERJWASTE WATER: _ Show existing and proposed water and sanitary lines. Coordinate locations with Engineering Assistant Samantha Smith at (409) 764-3660. Correct the spelling of "Pinon" Drive. PLANNING: Close the curb openings closest to the corner of Pinon Drive .and Texas Avenue. The throat .length. of the entrance drive ..needs to be lengthened .to include _the .first two parking spaces on either side of the drive. _ Frovide an end .parking island at the end of the .row closest. to the existing 9000 square feet warehouse. The island that abuts the building can be removed. _ Provide the scientific names and point requirements in the landscape legend. Coordinate details with Mapping Specialist Nanette Manhart at (409) 764-3570. _ Show the property lines specifically with respect to the front property line and its relationship to the existing parking area. _ Show adjacent ownership and zoning. _ Adjust the numbers on the parking legend to reflect the changes to the site plan. _ Coordinate dumpster location, screening and service with Operations Manager Jim Smith at (409) .764-3690. Show the proposed location and screening on the plan including. elevation drawings. IF THE REQUESTED VARIANCES ARE GRANTED, SUBMIT 4 COPIES OF COMPLETE CONSTRUCTION DOCUMENTS WITH THE REVISED SITE. PLAN ATTACHED AND 3 ADDITIONAL COPIES OF THE REVISED SITE PLAN .ONLY TO CONTINUE WITH PHASE II OF THE BUILDING PERMIT PROCESS.