HomeMy WebLinkAboutMinutesPROJECT .REVIEW COMMITTEE REPORT
March 4, 1994
TO: North B. Barden Jr., Municipal Development Group
203 Holleman East, College Station, TX 77840
First Federal Savings & Loan
2202 Longmire, College Station, TX 77845
FROM: Project Review Committe
- Jane Kee, City Pla e
David Pullen, City er
Craig. Hall, P & Z Re re entative
Others Attending
Natalie Thomas, Planning Tec ni '
Shirley Volk, Development Co d at
Tony Michalsky, Electrical Operatr s Coordinator
Samantha Smith, Engineering Assistant
Pete Vanacek, Parks Senior Planner
Tim DeDear, Fire Protection Specialist
Brett McCully, Project Engineer
Laverne Akin, GTE Representative
George McLean, CSISD Representative
SUBJECT: Parking Lot Plan -First Federal Savings Bank; proposed drive-in addition
to the existing banking facility at 2202 .Longmire, previously First American
Bank. (94-403)
A Project Review Committee meeting was .held Wednesday, March 2, 1994 to discuss
the above mentioned parking lot plan. City Engineer David Pullen moved to approve
the site plan with the following conditions:
CONDITIONS OF APPROVAL:
_ A sidewalk must be installed along the frontage of Longmire Drive..
_ Provide an access and parking easement to cover the portion of the parking lot
addition located on the west side between this lot and lot 4R. Reference the
volume and page of the easement dedication prior to issuance of a certificate of
occupancy.
Label Longmire Drive.
_ Relocation of any existing utilities will be at the cost of the developer.
.~
PRC Report
First Federal
Case #94-403
Page 2
P&Z Representative Hall seconded the motion .which passed unopposed (3 - 0). The
following comments were made by the various reviewing agents:
COMMENTS/CONCERNS:
_ Relocate the existing meter.
_ Coordinate telephone service with G.T.E. Representative Laverne Akin at (409)
821-4723.
_ Submit revised landscape plan.
SUBMIT 4 COMPLETE SETS OF CONSTRUCTION DOCUMENTS WITH THE
REVISED SITE AND LANDSCAPE PLAN ATTACHED AND 4 ADDITIONAL
REVISED SITE PLANS ONLY TO CONTINUE WITH PHASE II OF THE
BUILDING PERMIT PROCESS.
APPEAL PROCESS: An applicant may- appeal the' decision of the Project Review
Committee to the Planning and Zoning Commission within five. days after the PRC
Committee meeting. .Failure to appeal the PRC action shall constitute a contractual
acceptance of all conditions imposed, and. a waiver and surrender of all complaints,
defects, or potential invalidity, whether ..under state or .federal law. An .applicant
appealing the. decision of the PRC shall file ten .copies ofthe final site plan as approved
by the PRC, showing all changes and requirements imposed by the PRC, and
accompanied by a written. explanation of those items being appealed.. Until said copies
are on file, no further development approval shall occur,. and no further action by the
Commission sha1L take place. An applicant may` appeal only certain aspects of -site plan
review, and in the absence of discretionary review by the Commission, or review
pursuant to a petition, all other aspects of the site plan shall be final. Any notice of
appeal shah state with .particularity the aspects which are to be appealed. Coordinate
appeal process through Development Coordinator Shirley Volk at (409) 764-3741.
- ;
d
~~.
~:~~
,~
Commissioner Hall opened the public hearing.
Representative of the applicant Russ Hutchins of 2207 Woodsong Trail in Arlington, approached
the Commission and offered to answer questions about the proposed development. A total of 136
units°are planned consisting of 13 buildings with 12 living units per building. He stated that the
proposed retirement community will consist of 70% affordable housing retirees and the remaining
30% of the units will be at market rate. The rents will range from $350 - $SSO per month. Mr.
Hutchins stated .that the actual density of the project is less than 10 units per acre. Access to the
site will be from a proposed. street that will connect to Wellborn Road. There will. be no .direct
access from the proposed site to Wellborn Road.
Commissioner Hall closed the public hearing.
Commissioner Gribou moved to recommend approval of a rezoning .request for 4.314 acres
located along the east side of Wellborn.: Road approximately 500' north of the Graham Road.
intersection from C-2 Commercial. Industrial to`R 5 Medium Density. Apartments. Commissioner
Lightfoot seconded the motion which passed unopposed (6 - 0).
AGENDA ITEM NO.3: ' Consideration of a variance request to the minimum. parking
lot standards for the First Federal Savings and. Loan .building located of 2202 Longmire
Drive. (94-403)
Project. Engineer McCully informed the Commission that the .parking lot plan-for the First Federal
..Banking facility on Longmire Drive was approved by staff. in the course of the normal review
process. The Project Review .Committee (PRC) approved the ..site plan on March 4, 1994.
However, approval of the site plan does not exempt an applicant from meeting all ordinance
requirements even if certain requirements were not mentioned in the PRC review. At .the
completion of site construction, an inspection. was made and it was found that .the southern limit
of the original parking area, which extends a length of approximately 180 feet, had not been
curbed in accordance with the Zoning Ordinance. It was determined that the marking on the
plans was consistent with that of a proposed curb, but no note or direction was included on the
plans which would ensure that the curb would be `installed.: The applicant and contractor were
notified of the deficiency, and directed to install the curbing as required. Instead,. the. contractor
installed concrete. wheel. stops along the edge of paving, believing that the wheel. stops would
meet our' Ordinance. Because the discrepancy was not specifically noted during the original plan
review, and due to the concerns of staff to not hinder the occupancy of the building,. a temporary
certificate of occupancy was prepared, with the curbing required to be bonded by the applicant.
This agreement has not:.been signed by the applicant because a variance to the standards is
pending. ;There is therefore no certificate of occupancy at this time and technically .the building
should not be occupied. Since the: occupancy of the building, the .applicant. has. resisted efforts to
install the curbing based on the following reasoning: the original parking lot was not curbed, the
intention of the applicant is to further expand to the south and would have to remove this curbing
at some point and ,because the comment-was not made during the original plan review process.
Several telephone meetings were 'held to inform the applicant of the :City's intention to pursue
code. enforcement options to have the curb installed. `During the course of these meetings, rt was
decided that because the curbing requirement- could have been appealed xo the Planning and
Zoning Commission after PRC> and since the applicant was not aware of his opportunity, that the
applicant should be allowed to request a `variance to the Zoning Ordinance. Normally,.. a variance
request .must be submitted no later: than ten days after. PRC review. The variance request is based
upon the opinion of the applicant that the wheel stops are the same as curbing, that the openings
between he stops will allow drainage to -exit the site .better,: and that the replacement of the stops ,
with curbing is an unnecessary expense.
P & Z Mrtz~tes September I S, 1994 Page 2 of .S
..
,_
~:
~'~-~ Project Engineer McCully stated that section 9.2.D of the Zoning Ordinance requires that-all on
site driveway and parking areas. be surrounded by a raised 6" high concrete. curb. Concrete wheel
stops are not acceptable options.:because they do not adequately meet. the intent of curbing. It is
staffs opinion hat the curbing should be installed to meet the aesthetic intentions of the
Ordinance; to prevent the loss of control over the edge of the parking area. by the eventual loss
and or destruction of the wheel stops; and to .confine the drainage outflow from the parking into
the two established paths- which.: existed prior to the expansion. Based upon these facts, staff
recommended denial of the variance. request and. requested direction to the applicant to install the
curbing.
Stan Stevens and -Bobby Williamson, representatives of the First Federal Savings and Loan
Association, approached the "Commission and. stated that they.. have complied with .all of the
improvements Ghat they proposed. There was never any plan to .curb that particular .section of the
existing parking lot to allow for future expansion.. If the curbing was .installed, it would have to
be removed wrtlun;the next three to five. years when the site is expanded. Mr. Stevens apologized
for .any misunderstanding and explained than having to install the curb would require the bank o
go through another approval process through the regulatory agencies in Dallas. If the problem
would have been identified dunng construction,. then. the problem could have been resolved at that
time. However, he was not notified until after the fact of the requirement to install. the curb. Mr.
Stevens stated that he would install the curb if for some reasonthe facilitgr is not expanded within.
the next five years.:
Staff Planner Kuenzel explained that on June 10, 1994 the site was inspected: and the missing curb
section was identified. On June 13th, the contractor was notified of the problem. At that time, a
°` ~ temporary certificate. of occupancy was drafted to require a bond for -that section of the curb that
'~. ' was never signed by the applicant.
`-
Commissioner Lightfoot stated that the local architect or engineer should have been aware of the
City ordinances. Any variances to the current standards should have been identified during the
site planning stage.
Commissioner Gribou moved to deny the variance request to the minimum parking lot standards
for the First Federal Savings and Loan building located at 2202 Longmire Dnve. Commissioner
Lane seconded the motion.
Commissioner Hall stated that the site has been brought up to code with the exception of the curb
.:which was a'misunderstanding, He suggested that the variance be denied with the condition that.
the applicant have a three to four year time period of compliance. This would allow the wheel
stops to remain until the site: is expanded.
The original motion to deny the variance .request failed {3 - 2 - 1). Commissioners Lightfoot and
Hall voted against the motion. and Commissioner Garner abstained.
Commissioner Smith explained that he voted in favor of the motion with the understanding that
the three to five year. time period: of compliance was part of the motion. Since that condition was
not part of the motion, Commissioner Smith requested to change his vote against the original
motion: to deny the variance. request.
Commissioner: Smith moved to deny the variance request with the condition: that .the applicant is
allowed a four.. year time period to come into compliance with the City standards. Commissioner
;~~~~ Lightfoot seconded the motion with a second'condrtion that the wheel stops must be installed in a
continuous fashion placed end to end to give the appearance of a curb with. only two gaps in the
.wheel stops to allow for drainage. Commissioner Smith agreed to the amendment. The motion
passed (4 - 1 - 1); Commissioner Gribou voted in opposrt~on to the motion and Commissioner.
Garner abstained:
P & Z Minutes September 15, 1994 Page 3 of S