HomeMy WebLinkAboutStaff CommentsCITY OF COLLEGE STATION
DEVELOPMENT SERVICES
1101 Texas Avenue South, PO Box 9960
College Station, Texas 77842
Phone 979.764.3570 / Fax 979.764.3496
It4I:IMRIC7_1kiIbig 1k41
March 3. 2003
TO: Grant Barnby, Via fax 764-6975
FROM: Bridgette George, Assistant Development Manager
SUBJECT: DP -SIGNS NOW— Development Permit
Staff reviewed the above -mentioned construction documents as requested. The
following page is a list of staff review comments detailing items that need to be
addressed. Please address the comments and submit the following information for
further staff review, approval and issuance of the development permit:
Clarification on the Drainage Report
One (1) Erosion Control Plan
If there are comments that you are not addressing with the revised construction
documents, please attach a letter explaining the details. If you have any questions or
need additional information, please call Carol Cotter at 764-3570.
Attachments: Staff review comments
cc: Michael McClure, McClure Engineering Inc., Via fax 693-2554
Case file # ( 03-00100011)
Home of Texas A&M University
STAFF REVIEW COMMENTS NO. 1
Project: DP -SIGNS NOW -DEVELOPMENT PERMIT( 03-00100011)
ENGINEERING
1. It does not appear from the Site Plan that energy dissipation will be included. Exit
velocities were not provided in the Drainage Report, so I am assuming that they do
not exceed maximum allowed per the City's Drainage Policy and Design Standards.
Please verify.
2. A Roof Gutter Splash Block is shown on the Site Plan. What impact does this have
on Drainage Area 5?
3. Please submit an Erosion Control Plan.
Reviewed by: Carol Cotter Date: March 3, 2003
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
Staff Review comments Page 2 of 4