Ms. Carol Cotter
City of College Station Water Services Department
1101 Texas Avenue
College Station, TX 77842
Re: Engineering Cost Estimate
Proposed College Station ISD Transportation Center
Rock Prairie and William D. Fitch
College Station, Texas
Gessner Engineering Job No.: 09-0317
Dear Ms. Cotter:
Based on current estimations for direct material and direct labor costs, the prime
cost of the public infrastructure for the above referenced project is estimated to
be $204,782. Values used to determine this estimate are included in the
attached table. This estimate does not include indirect costs due to overhead or
indirect manufacturing expenses.
Please contact us if you have any questions or if we can be of further assistance.
Sincerely,
GESSNER ENGINEERING, LLP F-7451
I y 1. 0 :M��
Melissa P. Thomas, P.E.
II0-d
Morgan S. Lund, E.I.T.
Attached: Estimated Cost Table
�PZtiQFlF,t��!!
Gessner
...........................
:e
MELISSA.P. THOMAS.� Engineering
1732 I'ksvy
Su4[ 105
College Swtion,Tcsas 77840
CO. B4 . 10763, 77342-0763
979.680.S340-
FA\ 979.680,8811
2204 S. Chappell Hill So.
I3cnham,7esas 778.33
979,836.6855
FAX 979.836-6847
Probable Estimate of Sitework Construction Costs
CSISD Transportation Center
Gessner Engineering, LLP
GE Job #: 09-0317
WATER
Item Quantity Units Unit Cost Total
12" PVC
1250
LF
$ 60
$ 75,000
8" PVC
315
LF
$ 40
$ 12,600
18x18x12 Tee Cut to Existing
1
EA
$ 6,160
$ 6,160
Fittings
1.5
TON
$ 4,310
$ 6,465
18" Gate Valve
2
EA
$ 2,756
$ 5,513
12" Gate Valve
4
EA
$ 1,838
$ 7,350
8" Gate Valve
4
EA
$ 1,225
$ 4,900
6" Gate Valve
1
EA
$ 919
$ 919
4" Gate Valve
2
EA
$ 459
$ 919
3" Meter
2
EA
$ 110
$ 220
Fire Hydrant Assembl
3
EA
3 3,149
$ 9,447
Pressure Testing and Disenfecting
1 EA
$ 5,500
$ 5,500
Trench Safety
1,565 LF
$ 2
$ 3,130
Sub Total -Water
$ 138,122
SANITARY SEWER ,
Item QuantityUnits Unit Cost Total
Boring under William D. Fitch
1
LF
$ 50,000
$ 50,000
16"x318" Steel Casing
85
LF
$ 100
$ 8,500
8" PVC
204
LF
$ 40
$ 8,160
Sub Total - Sanitary Sewer
$ 66,660
Total Construction Cost
$ 204,782
Gessner Engineering