MEMORANDUM
TO: Wallace Phillips IV; via:
FROM: Jason Schubert, AICP, Principal Planner
SUBJECT: CASTLEGATE II SECTION 202 (FP-REPLAT)
Staff reviewed the above -mentioned final plat as requested. The following page is a list
of staff review comments detailing items that need to be addressed. If all comments
have been addressed and the following information submitted by Monday, August 12,
10:00 a.m., your project will be placed on the next available Planning and Zoning
Commission meeting held in the City Hall Council Chambers, 1101 Texas Avenue.
One (1) 24"x36" copy of the revised final plat;
Thirteen (13) 11 "x17" copies of the revised final plat;
PIP application for the improvements in the ROW;
One (1) Mylar original of the revised final plat (required after P&Z
approval); and
One (1) copy of the digital file of the final plat on diskette or e-mail to:
PddsdigitalsubmittalCcilcstx.gov. //
PC: New Vision Custom Homes; via: giltor81@aol.comV
Joe Schultz, Schultz Engineering, LLC; via: joeschultz84@verizon.netV
P&DS Project No. 13-00900154
Planning d- Development Services
P.O. BOX 9960 - 1101 TEXAS AVENUE. - COLLEGE STATION • TEXAS - 77842
TE1. 979.764.3570 , FAX. 979.764.3496
cstx.gov/devservices
STAFF REVIEW COMMENTS NO. 1
Project: Castlegate II Section 202 (Fp-Replat) (13-00900154)
PLANNING
1. Title Block: Under Replat portion of description change "Block 1, Lot." to "Block 11,
Lots."
2. Please note that any changes made to the plans, that have not been requested by
the City of College Station, must be explained in your next transmittal letter and
"bubbled" on your plans. Any additional changes on these plans that the City has not
been made aware of will constitute a completely new review.
3. Please note that you may be required to submit paid tax certificates if they are not
current prior to the filing of your plat.
Reviewed by: Matt Robinson Date: 8/5/13
ENGINEERING COMMENTS NO. 1
1. Please show the 20' PUE line in the common area on the original plat.
2. Please show the existing ROW lines on Greens Prairie Road on the original plat.
3. Please submit a PIP application for the improvements in the ROW.
4. Please provide verification that the pipeline company is fine with the sidewalk
construction.
5. Please provide a detail on your construction plans showing the profile view for
the wall, column, sign and the fence. Separate sign and building permits will be
required.
6. An easement needs to be dedicated in the common area for the future waterline
in Section 207, on Block 11, Lots 6 & 7 as we would prefer this water line be
located in the common area and not in back yards. If there are future plans for
walls in this area, I would recommend an easement offset from the lot lines with
enough room to allow the wall to be constructed between the easement and lot
lines. The easement would need to connect to the area where the future
sidewalk is shown to be constructed.
Reviewed by: Danielle Singh Date: 8/02/2013
ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION
1. SITE PLAN/PLAT: Developer will provide CSU with a digital, AutoCAD dwg format,
version of plat and / or site plan as soon as it is available. Email
to:ehorton(n-cstx.gov .
2. LOAD DATA: The developer will provide load data to CSU as soon as it is available.
This information is critical for CSU to accurately determine the size and number of
transformers, and other equipment, required to provide service to the project. Failure
to provide load data will result in construction delays and, due to clearance
requirements, could affect the final building footprint. Delivery time for transformers
and other equipment not in stock is approximate 26 weeks.
3. EASEMENTS: All easements on site are existing. Electric facilities will be designed
within existing easements.
4. EASEMENTS: Developer provides descriptive easements for electric infrastructure
as designed by CSU, as shown on plat or site plan.
5. If easements are existing, the developer will be responsible for locating easements
on site to insure that electrical infrastructure is installed within easement boundaries.
6. The following easements will be required:
• The lots that have the 20' PUE will. As future lots develop we will need a 20' PUE
on them as well. Just the lots going down Greens Prairie RD,
GENERAL ELECTRICAL COMMENTS
1. Developer installs conduit per CSU specs and design.
2. CSU will provide drawings for electrical installation.
3. Developer provides 30' of rigid or IMC conduit for each riser conduit. CSU installs
riser.
4. Developer will intercept existing conduit at designated transformers or other existing
devices and extend as required.
5. If conduit does not exist at designated transformer or other existing devices,
developer will furnish and install conduit as shown on CSU electrical layout.
6. Developer pours electric device pads or footings, i.e. transformers, pull boxes, or
other device, per CSU specs and design.
7. Developer installs pull boxes and secondary pedestals per CSU specs and design,
Pull boxes and secondary pedestals provided by CSU.
8. Final site plan must show all proposed electrical facilities necessary to provide
electrical service, i.e. transformers, pull boxes, or switchgears, all meter locations,
and conduit routing as designed by CSU.
9. To discuss any of the above electrical comments please contact Eric Horton at
979.764.6280.
Reviewed by: Eric Horton Date: 8/2/13
SANITATION
1. Sanitation is ok with this project.
Reviewed by: Wally Urrutia Date: July 31, 2013
V r
CITY OF COLLEGE STATION
Home ofTexxA6-M University"
MEMORANDUM
July 26, 2013
TO: Wallace Phillips IV; via: dustyphillips52@yahoo.com
FROM: Matt Robinson, AICP, Senior Planner
SUBJECT: CASTLEGATE II SECTION 202 (FP-REPLAT)
Thank you for the submittal of your FINAL PLAT - RESIDENTIAL application.
be distributed to staff next week for their review.
PC: New Vision Custom Homes; via: giltor8l@aol.com
Joe Schultz, Schultz Engineering, LLC; via: joeschultz84@verizon.net
P&DS Project No. 13-00900154