HomeMy WebLinkAboutCorrespondenceTeresa Rogers
From: Jason Schubert
Sent: Monday, June 03, 2013 5:17 PM
To: Danielle Singh, Teresa Rogers, Bob Cowell
Cc: Alan Gibbs; Carol Cotter
Subject: RE: Pebble Creek PP
Attachments: Pebble Creek Ph 7 documents from 1998.pdf; Warranty Deed dedication of parkland in
1988.pdf; Pebble Creek Ph 4B plat.pdf
23
I've done some research for this and found the Phase 7 preliminary plat that was approved in 1998. The proposed
Phases 7C & 7D that are under review is the same area as Phase 7C in the 1998 preliminary. I've attached the documents
and also a copy of the Warranty Deed that dedicated the parkland in 1988. I'm not sure if we had all this information
when previous discussions with the developer were held.
As you will see, Pebble Creek Pkwy was required to be built with Phase 7C which never developed (until now). As phases
along Pebble Creek Pkwy developed, they designated 100 feet of the property that was dedicated as Pebble Creek ROW
and the remaining -65 feet as parkland (see example in attached Ph 46). From the Warranty Deed, I don't believe there
is a need for additional parkland to be dedicated as the 65-foot area can accommodate a pedestrian walkway and this
seems to be how it was done with previous phases. I think we should revise the comment we make but with this
information it is clear to me that Pebble Creek Pkwy is required with this project. Let's discuss as needed.
Thanks,
Jason
From: Jason Schubert
Sent: Monday, June 03, 2013 2:16 PM
To: Danielle Singh; Teresa Rogers
Cc: Alan Gibbs; Carol Cotter
Subject: RE: Pebble Creek PP
Teresa and Danielle, please do not send back comments yet. I am researching the Pebble Creek Pkwy issue.
From: Danielle Singh
Sent: Monday, June 03, 2013 10:56 AM
To: Alan Gibbs; Carol Cotter
Cc: Teresa Rogers; Jason Schubert
Subject: Pebble Creek PP
Below is my comment for the Pebble Creek PP, please let me know if you would like me to change or add anything.
There is not enough information on this plan to constitute a full review. Please see article 3.3 of the LIDO for a full list of
submittal requirements. Please note that there are concerns regarding the overall access to this phase and adjacent
phases. The City is expecting the developer to construct the extension of Pebble Creek Parkway with this phase which
may also require new Parkland Dedication. Also, the initial phase will be required to connect Royal Adelade Loop to St.
Andrews Drive in order to provide adequate access to Phase 7 which contains over 100 lots and only one external street
connection.
Danielle Singh, P.E., CFM