HomeMy WebLinkAboutCost EstimateTHE BARRACKS II SUBDIVISION - PARK 1
Parking Lot
31
lGrading
LS
l
$
500.00
1 $
500.00
32
5" Reinforced Concrete Pavement w/Standard Curb, complete in place
I SY
1 140
$
30.00
1 $
4,200.00
33
1 Stri in & Si na a
LS
l
$
500.00
1 $
500.00
Irrigation System
34
l" Water Service
EA
1
$800.00
$
800.00
35
Water Meter
EA
1
$500.00
$
500.00
36
Irrigation Sleeve
LF
3
$10.00
$
30.00
37
Irrigation System
LS
1
$2,500.00
$
2,500.00
Landscape
38
Non -Canopy Trees >1.25" Caliper)
EA
5
$100.00
$
500.00
39
Canopy Trees (>2.5" Caliper)
EA
10
$250.00
$
2,500,60
40
Shrub min.5 Gallon)
EA
25
$25,00
$
625.00
41
Bermuda Grass Seeding Inside Disturbed Area Limits)
SY
9401
$0,10
$
94.00
Site Preparation & Grading Subtotal
$
2,500.00
Park Features Subtotal
$
21,378.00
Fitness Equipment Subtotal
$
30,800.00
Pavement Subtotal
$
5,200.00
Irrigation System Subtotal
$
3,830.00
Landscape Subtotal
$
3,719.00
Performance & Payment Bonds
$
2,724.00
TOTALPROJECTI
1 $
70,151.00
Page 3 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
THE BARRACKS II SUBDIVISION - PARK 6
Engineer's Estimate of Final Construction Cost
Item
Description
Unit
Estimated
Quantity
Unit Price
Total
Site Preparation & Grading
t
Mobilization & Construction Staking
LS
1
$1,000.001
$ 1,000.00
2
Site Grading
LS
I
$1,000,001
$ 1,000.00
3
Silt Fence, Construction Exit, and Erosion & Sediment Control
LS
1
$750.001
$ 750.00
Park Features
4
Park Bench
EA
1 4
$1,250.00
$ 5,000.00
5
6' Concrete Sidewalk, 4" Thick
SF
1,975
F $4.20
$ 8,295.00
6
Park Tables
EA
1
$1,531.00
$ 1,531.00
7
14'x22' Shade Structure
EA
1
1 %5,000.00
$ 5,000.00
Volleyball
Court Equipment
8
Volleyball Sand
SF
1 4,9021
$0.501
$ 2,451.00
9
Sand Volleyball Edge Guard
LF
4101
$9.251
$ 3,792.50
10
Volleyball Nets and Poles
EA
1 2
$2,000.001
$ 4,000.00
Irrigation System
11
I" Water Service
EA
I
$800.00
$ 800.00
12
Water Meter
EA
I
$500.00
$ 500.00
13
Irrigation Sleeve
LF
2
$10.00
$ 20.00
14
Irrigation System
LS
1
$2,500.00
$ 2,500.00
Landscape
IS
Non-CanopyTrees >1.25" Caliper)
EA
13
$100.001
$ 1,300.00
16
Cano Trees >2.5" Caliper)
EA
10
$250,00
$ 2,500.00
17
Bermuda Grass Seeding Inside Disturbed Area Limits
SY
1 9701
$0.101
$ 97.00
Site Preparation & Grading Subtotal
$ 2,750.00
Park Features Subtotal
$ 19,826.00
Volleyball Court Equipment Subtotal
$ 10,243.50
Irrigation System Subtotal
$ 3,820.00
Landscape Subtotal
$ 3,897.00
Performance & Payment Bonds
$ 811.00
TOTAL CONSTRUCTION1 $ 4047.50
Page 4 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction Summary
February 28, 2013
Item
Description
Total
1
Site Preparation & Grading
$ 2,500.00
2
Park Features
$ 22,498.00
3
Fitness Equipment
$ 30,800.00
4
Parkin Lot
$ 5,200.00
5
Irrigation System
$ 4,040.00
6
Landscape
$ 3,719.00
7
Performance & Payment Bonds
$ 1,375.00
Total: $ 70,132.00
THE BARRACKS II SUBDIVISION - PARK 6
Item
Description
Total
1
Site Preparation & Grading Subtotal
$ 2,750.00
2
Park Features Subtotal
$ 21,357.00
3
Volleyball Court Equipment
$ 10,243.50
4
Irrigation System Subtotal
$ 3,960.00
5 1
Landscape Subtotal
1 $ 3,897.00
6 1
Performance & Payraent Bonds
$ 844.00
31: $ 43,051.50
V F=12327 2--z
SCHULTZ ENGINE MNG LLC
Page 1 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction
February 28,2013
Item
Description
Unit
Estimated
uanti
Unit Price
Total
Site Preparation & Grading
1
Mobilization & Construction Staking
LS
1
$750.001
$ 750.00
2
Site Grading
L
1,000-001
$ 1,000.00
3
1 Silt Fence, Construction Exit, and Erosion & Sediment Control
LS
1
$750.001
$ 750.00
Park Features
4
Park Bench
EA
2
$1,250.00
$ 2,500.00
5
6' Concrete Sidewalk, 4" Thick
SF
900
$4.20
$ 3,780.00
6
4" Wide Recycled Plastic Edging
LF
274
$4.00
$ 1,096.00
7
Crushed Granite
SF
4,328
$1.25
$ 5,410.00
8
14'x22' Shade Structure
EA
1
$5,000.00
$ 5,000.00
9
1 Park Tables
EA
I 2
$1,531.00
$ 3,062.no
10
ADASign
EA
1
$250.00
$ 250,00
11
Wheel Stop
EA
2
$100.00
$ 200.00
12 ADA Ramp EA 2 $600.00 $ 1,200.00
Fitness Equipment
13
Combo Press and Pull - CSPB - Sta. 1
EA
1
$3,970.00
$ 3,970.00
14
Leg Press - LEGP2 - Sta. 2
EA
1
$2,680.00
$ 2,680.00
15
Sit -Up Board -SITB1-Sta. 3
EA
1
$1,155.00
$ 1,155.00
16
17
Sit -Up Bench -STUP-Sta. 4
Back Extension Apparatus - BEXT- Sta, 5
EA
EA
1
l
$1,585.00
$1,295.00
$ 1,585.00
$ 1,295.00
18
Power Rower -RWRS-Sta. 6
EA
1
$1,625.00
$ 1,625.00
19
Rowing Machine -ROWR-Sta. 7
EA
1
$1,480.00
$ 1,480.00
20
21
War -Up Station -WMUP-Sta. 8
Rider - Single - RDRS - Sta. 9
EA
EA
1
1
$3,290.00
$1,420.00
$ 3,290,00
$ 1,420.00
22
23
24
Two -Person Rotator -TSOR- Sta. 10
Pull -Up & Dip Station - PDIP - Sta. 11
Push -Up Bar -PSUP- Sta. 12
EA
EA
EA
1
1
1
$1,715.00
$1,690.00
$565.00
$ 1,715.00
$ 1,690.00
$ 565.00
25
Parallel Bars- PBAR- Sta. 13
EA
l
$850.00
$ 850.00
26
Horizontal Bar - Single -HBARI- Sta. 14
EA
1
$855.00
$ 855.00
27
28 1PlYo
Horizontal Ladder -HLAD- Sta. 15
Boxes - Set of 3 - PBOX - Sta.16
EA
EA
i
1
$2,275.00
$1,945.00
$ 2,275.00
$ 1,945.00
29
Multi -Bars- MBAR - Sta. 17
EA
1
$1,550.00
$ 1,550.00
30 1
Balance Beam - BABM - Sta. 18
EA
1
$855.001
$ 855,00
Page 2 of 4
THE BARRACKS II SUBDIVISION - PARK 1
Parking Lot
31
Grading
LS
l
$ 500.00
$ 500.00
32
5" Reinforced Concrete Pavement w/Standard Curb, complete in place
SY
140
$ 30.00
$ 4,200.00
33
1 Stri in & Si na e
LS
1
$ 500.00
$ 500.00
Irrigation System
34
I" Water Service
EA
1
$800.00
$ 800.00
35
Water Meter
EA
1
$500.00
$ 500.00
36
Irrigation Sleeve
LF
24
$10.00
$ 240.00
37
Irrigation System
LS
1
$2,500.00
$ 2,500.00
Landscape
38
Non -Canopy Trees (>1.25" Caliper)
EA
5
$100.00
$ 500.00
39
Canopy Trees >2.5" Caliper)
EA
10
$250.00
$ 2,500.00
40
Shrub min.5 Gallon
EA
25
$25.00
$ 625.00
41
Bermuda Grass Seeding (Inside Disturbed Area Limits)
SY
9401
$0.10
$ 94.00
Site Preparation & Grading Subtotal
$
2,500.00
Park Features Subtotal
$
22,498.00
Fitness Equipment Subtotal
$
30,800.00
Pavement Subtotal
$
5,200:00
Irrigation System Subtotal
$
4,040.00
Landscape Subtotal
$
3,719.00
Performance & Pa ment Bonds
$
1,375.00
TOTAL CONSTRUCTION $ 70,132.00
Page 3 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
THE BARRACKS II SUBDIVISION - PARK 6
Engineer's Estimate of Construction
Fphruam 78 7t1t2
Item
Description
Unit
Estimated
uanti
Unit Price
Total
Site Preparation &Grading
I Mobilization Z.Construction StakingLS 1 $1,000.00 $ 1,000.00
2 Site Grading LS 1 $1,000.00 $ 1,000.00
3 1 Silt Fence, Construction Exit, and Erosion & Sediment Control I LS 1 $750.00 $ 750.00
Park Features
4 Park Bench
EA 4 $1,250.00
$ 5,000.00
5 6' Concrete Sidewalk, 4" Thick
SF 1,975 $4.20
$ 8,295.00
6 Park Tables
EA 2 $1,531.00
$ 3,062.00
7 14'x22' Shade Structure
EA 1 $5,000.00
$ 5,000.00
Volleyball Court Equipmeut
8 Volleyball Sand SF 4,902 $0.50 $ 2,451.00
9 Sand Volleyball Edge Guard LF 410 $9.25 $ 3,792.50
10 IVolleyball Nets and Poles EA 2 $2,000.00 $ 4,000.00
Irrigation System
11
1" Water Service
EA I
$800.00
$ 800.00
12
Water Meter
EA 1
$500.05
$ 500.00
13
Irrigation Sleeve
LF 16
$10.00
$ 160.00
14
Irrigation System
LS 1
$2,500.00
$ 2,560.00
Landscape
15
Non -Caro Trees >1.25" Caliper)EA
13
$100.00
$ 1,300.00
16
Cano Trees >2.5" Caliper)EA
10
$250.00
$ 2,500.00
17
Bermuda Grass Seeding Inside Disturbed Area Limits
SY
970
$0. t0
$ 97.00
Site Preparation & Grading Subtotal
Park Features Subtotal
Volleyball Court Equipment Subtotal
Irrigation System Subtotal
Landscape Subtotal
Performance & Payment Bonds
$
2,750.00
$
21,357.00
$
10,243.50
$
3,960.00
$
3,897.00
$
844.00
TOTAL CONSTRUCTION $ 43,051.50,
Page 4 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction Summary
February 28,2013
Item
Description
Total
1
Site Preparation & Grading
$ 2,500. 10
2
Park Features
$ 22,498.00
3
Fitness Equipment
$ 30,800.00
4
Parkin Lot
$ 5,200.00
5
Irrigation System
$ 4,040.00
6
JLandscape
$ 3,719.00
7 1
Performance & Payment Bonds
$ 1,375.00
Total: $ 70,132.00
THE BARRACKS II SUBDIVISION - PARK 6
Item
Description
Total
1
Site Preparation & Grading Subtotal
$ 2,750.00
2
Park Features Subtotal
$ 21,357.00
3
Volleyball Court Equipment
$ 10,243.50
4
Irrigation System Subtotal
$ 3,960.00
5
1 Landscape Subtotal
I $ 3,897.00
6
1 Performance & Payment Bonds 1
$ 844.00
al: $ 43,051.50
5CHULTZ ENGINEERING, LLC:
Page 1 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction
February 28,2013
Item
Descri tion
P
Unit
Estimated
Price
Total
QuantityUnit
Site Preparation &Grading
1
Mobilization & Construction StakingLS
l
$750.00
$ 750.00
2
Site Grading
LS
1
$1,000.00
$ 1,000.0O
3
1 Silt Fence, Construction Exit, and Erosion & Sediment Control
LS
I
$750.00
$ 750.00
Park Features
4
Park Bench
EA
2
$1,250.00
$ 2,500.00
5
6' Concrete Sidewalk, 4" Thick
SF
900
$4.20
$ 3,780,00
6
4" Wide Recycled Plastic Edging
LF
274
$4.00
$ 1,096.00
7
Crushed Granite
SF
4,328
$1.25
$ 5,410.00
8
14'x22' Shade Structure
EA
l
$5,000.00
$ 5,000.00
9
Park Tables
EA
7,1
ki ;-41 nni
$ 3,062.no
10
ADA Sin
EA
I
$250A0
$ 250.00
11
Wheel Stop
EA
2
$100.00
$ 200.00
12 ADA Ram EA 1 2 $600.00 $ 1,200.00
Fitness Equipment
13
Combo Press and Pull - CSPB - Sta. 1
EA
1
$3,970.00
$ 3,970.00
14
Leg Press - LEGP2 - Sta. 2
EA
1
$2,680.00
$ 2,680.00
15
Sit -Up Board -SITB1-Sta. 3
EA
l
$1,155.00
$ 1,155.00
16
Sit -Up Bench -STUP-Sta. 4
EA
1
$1,585.00
$ 1,585.00
17
Back Extension Apparatus - BEXT - Sta. S
EA
1
$1,295.00
$ 1,295,00
18
Power Rower -RWRS-Sta. 6
EA
1
$1,625.00
$ 1,625.00
19
Rowing Machine -ROWR-Sta. 7
EA
l
$1,480.00
$ 1,480.00
20
War -Up Station -WMUP-Sta. 8
EA
1
$3,290.00
$ 3,290.00
21
Rider - Single -RDRI-Sta. 9
EA
1
$1,420.00
$ 1,420.00
22
Two -Person Rotator -TSOR- Sta. 10
EA
1
$1,715.00
$ 1,715.00
23
Pull -Up & Dip Station - PDIP - Sta. it
EA
1
$1,690.00
$ 1,690.00
24
Push -Up Bar - PSUP - Sta. 12
EA
1
$565.00
$ 565,00
25
Parallel Bars- PEAR- Sta. 13
EA
1
$850.00
$ 850.00
26
HorizontalBar - Single -HBAR1- Sta. 14
EA
1
$855.00
$ 855,00
27
Horizontal Ladder -HLAD- Sta. 15
EA
1
$2,275.00
$ 2,275.00
28
Plyo Boxes - Set of 3 - PBOX - Sta. 16
EA
1
$1,945.00
$ 1,945.00
29
Multi -Bars - MBAR - Sta. 17
EA
1
$1,550.00
$ 1,550,00
30
Balance Beam - BABM - Sta. 18
EA
1
$855.00
$ 855.22
Page 2 of 4
THE BARRACKS II SUBDIVISION - PARK i
Parking Lot
31
Grading
LS
I
$ 500.00
$ 500.00
32
5" Reinforced Concrete Pavement w/Standard Curb, complete in place
SY
i40
$ 30.00
$ 4,200.00
33
1 Stri in & Si na a
LS
1
$ 500.00
$ 500.00
Irrigation System
34
1" Water Service
EA
I I
$800.00
$ 800.00
35
Water Meter
EA
1
$500.00
$ 500.00
36
Irrigation Sleeve
LF
24
$10.001
$ 240,00
37
Irrigation System
LS
1
$2,500.001
$ 2,500.00
Landscape
38
Non -Cann Trees >1.25"Caliper)
EA
5
$100.00
$ 500.00
39
Canopy Trees >2.5" Caliper)
EA
10
$250.001
$ 2,500.00
40
Shrub min. 5 Gallon
EA
25
$25.001
$ 625.00
41
Bermuda Grass Seeding Inside Disturbed Area Limits
SY
940
$0.10
$ 94.00
Site Preparation & Grading Subtotal
$
2,500.00
Park Features Subtotal
$
22,498.00
Fitness Equipment Subtotal
$
30,800.00
Pavement Subtotal
$
5,200:00
Irrigation System Subtotal
$
4,040.00
Landscape Subtotal
$
3,719.00
Performance & Payment Bonds
$
1,375.00
TOTAL CONSTRUCTION1 $ 70,132.00
Page 3 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS 11 SUBDIVISION - PARK 6
Engineer's Estimate of Construction
February 28, 2013
Item
Description
Unit
Estimated
uantit
Unit Price
Total
Site Preparation &Grading
t
ization & Construction StakingLS
1
$1,000.00
$ 1,000.00
2
3nce,
radin
FISiltConstruction Exit, and Erosion &Sediment Control
LS
LS
i
1
$1,000.00
$750.001
$ 1,000.00
$ 750.00
Park Features
4
Park Bench
EA
4
$1,250,00
$ 5,000.00
5
6' Concrete Sidewalk, 4" Thick
SF
1,975
$4.20
$ 8,295.00
6
Park Tables
EA
2
$1,531.00
$ 3,062.00
7 14'x22' Shade Structure EA 1 $5,000.00 $ 5,000.00
Volleyball Court Equipment
8 Volleyball Sand SF 4,902 $0.50 $ 2,451.00
9 Sand Volleyball Edge Guard LF 410 $9.25 $ 3,792,50
]0 Volleyball Nets and Poles EA 2 $2,000.00 $ 4,000.00
Irrigation System
I1
1" Water Service
EA
1
$800.00
$ 800,00
12
1 Water Meter
EA
1
$500.00
$ 500.00
13
Irri ationSleeve
LF
16
$10.00
$ 160,00
14 Irri ation System LS 1 $2,500.00 $ 2,500.00
Landscape
15
16
17 1
Non-CanopyTrees >1.25" Cali er
Cano Trees >2.5" Caliper)
Bermuda Grass Seeding Inside Disturbed Area Limits
EA
EA
SY
t3
l0
970
$100.001
$250.001
$0.101
$ 1,300.00
$ 2,500.00
$ 97.00
Site Preparation & Grading Subtotal
Park Features Subtotal
Volleyball Court Equipment Subtotal
Irrigation System Subtotal
Landscape Subtotal
Performance & Payment Bonds
$ 2,750.00
$ 21,357.00
$ 10,243.50
$ 3,960.00
$ 3,897.00
$ 844.00
TOTAL CONSTRUCTION $ 43,051.50
Page 4 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction Summary
February 4, 2013
Item
Description
Total
1
Site Preparation & Grading
$ 2,500.00
2
Park Features
$ 19,070.00
3
Fitness Equipment
$ 30,800.00
4
Parkin Lot
$ 5,200.00
5
Irrigation System
$ 3,800.00
6
ILandscape
$ 4,465.00
7
Performance & Payment Bonds
$ 1,316.70
Total: $ 67,151.70
THE BARRACKS II SUBDIVISION - PARK 6
Item
Description
Total
1
Site Preparation & Grading Subtotal
$ 2,750.00
2
Park Features Subtotal
$ 14,049.00
3
Volleyball Court Equipment
$ 8,269.50
4
Pavement Subtotal
$ 7,400.00
5
1 Irrigation System Subtotal
$ 3,800.00
6
JLandscape Subtotal
$ 4,615.00
7
lPerformance & Payment Bonds
$ 817.67
Total: $ 41,701.17
y3
F-12327
SCHULTZ ENGINEERING, LLC.
Page 1 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction
February 4, 2013
Item
Description
Unit
Estimated
uantit
Unit Price
Total
Site Preparation & Grading
1
Mobilization & Construction Staking
LS
1
$750.001
$ 750.00
2
ISiteGrading
LS
I
$1,000ml
$ 1,000.00
3
Silt Fence, Construction Exit, and Erosion & Sediment Control
LS
l
$750.001
$ 750.00
Park Features
4
Park Bench
EA
2
$1,250.00
$ 2,500.00
5
6' Concrete Path, 4" Thick
SF
900
$4.20
$ 3,780.00
6
6" Wide Ribbon Curb
LF
270
$5.00
$ 1,350.00
7
Crushed Granite
SF
4,192
$1.25
$ 5,240.00
8
14'x22' Shade Structure
EA
1
$5,000.00
$ 5,000.00
10
1 ADA Ramp
EA
2
$600.00
$ 1,200.00
Fitness Equipment
11
Combo Press and Pull - CSPB - Sta. 1
EA
1
$3,970.00
$ 3,970.00
12
Leg Press - LEGP2 - Sta. 2
EA
1
$2,680.00
$ 2,680.00
13
Sit -Up Board -SITB1-Sta. 3
EA
1
$1,155.00
$ 1,155.00
14
Sit -Up Bench -STUP-Sta. 4
EA
1
$1,585.00
$ 1,585.00
15
Back Extension Apparatus - BEXT- Sta. 5
EA
1
$1,295.00
$ 1,295.00
16
Power Rower - RWRS - Sta. 6
EA
1
$1,625.00
$ 1,625.00
17
Rowing Machine -ROWR-Sta. 7
EA
1
$1,480.00
$ 1,480.00
18
lWar-Up Station -WMUP-Sta. 8
EA
1
$3,290.00
$ 3,290.00
19
lRider- Single -RDR1-Sta. 9
EA
1
$1,420.00
$ 1,420.00
20
Two -Person Rotator -TSOR- Sta. 10
EA
1
$1,715.00
$ 1,715.00
21
Pull -Up & Dip Station - PDIP - Sta. 11
EA
1
$1,690.00
$ 1,690.00
22
Push -Up Bar -PSUP- Sta. 12
EA
1
$565.00
$ 565.00
23
ParallelBars- PBAR- Sta. 13
EA
1
$850.00
$ 850.00
24
Horizontal Bar - Single -HBAR1- Sta. 14
EA
1
$855.00
$ 855.00
25
Horizontal Ladder -HLAD- Sta. 15
EA
I 1
$2,275.00
$ 2,275.00
26
PI o Boxes - Set of 3 - PBOX - Sta. 16
EA
1
$1,945.00
$ 1,945.00
27
Multi -Bars- MBAR - Sta. 17
EA
1
$1,550.00
$ 1,550.00
28
jBalance Beam - BABM - Sta.18
EA
I
$855.00
$ 855.00
Parking Lot
29
lGrading I
LS
l
$ 500.00
$ 500.00
30
5" Reinforced Concrete Pavement w/Standard Curb, complete in place I
SY 1
140
$ 30.00
$ 4,200.00
31
IStriping&Signage I
LS 1
1
$ 500.00
$ 500.00
Irrigation System
32
1" Water Service
EA
1
$800.00
$ 800.00
33
Water Meter
EA
1
$500.00
$ 500.00
34
lIrrigation System
LS
l
$2,500.00
$ 2,500.00
Page 2 of 4
THE BARRACKS II SUBDIVISION - PARK 1
Landscape
35
Non -Cann Trees (>1.25" Caliper)
EA
5
$100.00
$ 500.00
36
Canopy Trees (>2.5" Caliper)
EA
10
$250.00
$ 2,500.00
37
Shrub min. 5 Gallon)
EA
25
$25.00
$ 625.00
38
Bermuda Grass Seeding (Inside Disturbed Area Limits)
SY
8.4001
$0.10
$ 840.00
Site Preparation & Grading Subtotal
$
2,500.00
Park Features Subtotal
$
19 070.00
Fitness Equipment Subtotal
$
30,800.00
Pavement Subtotal
$
5,200:00
Irrigation System Subtotal
$
3,800.00
Landscape Subtotal
$
4,465.00
Performance & Payment Bonds
$
1,316.70
TOTAL CONSTRUCTIONI $ 67,151.70
Page 3 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 6
Engineer's Estimate of Construction
February 4. 2013
Item
Description
P
Unit
Estimated
uantit
Unit Price
Total
Site Preparation & Grading
1
Mobilization & Construction Staking
LS
1
$1,000.00
$ 1,000.00
2
SiteGradin
LS
i
$1,000.00
$ 1,000.00
3
Silt Fence, Construction Exit, and Erosion & Sediment Control
LS
L
$750.00
$ 750.00
Park Features
4
Park Bench
EA
1 4
$1.250.00
$ 5,000.00
5
6' Concrete Path, 4" Thick
SF
235
$4.20
$ 987.00
6
Park Tables
EA
2
$1,531.00
$ 3,062.00
7
14'x22' Shade Structure
EA
i
1 $5,000.00
$ 5,000.00
Volleyball
Court Equipment
8
Volleyball Sand
SF
2,730
$0.50
$ 1,365.00
9
Sand Volleyball Edge Guard
LF
314
$9.25
$ 2,904.50
TO
Volle ball Nets and Poles
EA
2
$2,000.001
$ 4,000.00
Parking Lot
11
lGrading
1
$ 500.00
$ 500.00
12
5" Reinforced Concrete Pavement w/Standard Curb, co m lete in lace
SY
210
$ 30.00
$ 6,300.00
13
S triping & Si na e
LS
1
$ 600.00
$ 600.00
Irrigation System
14
1" Water Service
EA
1
$800.001
$ 800.00
11
Water Meter
EA
1
$500.00
$ 500.00
16
Lri ation System
LS
1
$2,500.001
$ 2,500.00
Landscape
17
Non -Canopy Trees (>1.25" Caliper)
EA
8
$100.00
$ 800.00
18
Canopy Trees >25' Caliper)
EA
10
$250.00
$ 21500.00
19
Shrub min. 5 Gallon
EA
21
$25.00
$ 525.00
20
Bermuda Grass SeedingInside Disturbed Area Limits
SY
7,900
$0.10
$ 790.00
Site Preparation & Grading Subtotal
Park Features Subtotal
Volleyball Court Equipment Subtotal
Pavement Subtotal
Irrigation System Subtotal
Landscape Subtotal
Performance & Payment Bonds
$ 2,730.00
$ 14,049.00
$ 8,269.50
$ 7,400.00
$ 3,800.00
$ 4,615.00
$ 817.67
TOTAL CONSTRUCTION $ 41,701.17
Page 4 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction Summary
February 4, 2013
Item
Description
Total
1
Site Preparation & Grading
$ 2,500.00
2
Park Features
$ 19,070.00
3
Fitness Equipment
$ 30,800.00
4
Parkin Lot
$ 5,200.00
5
Irrigation System
$ 3,800.00
6
ILandscape
$ 4,465.00
7
jPerformance & Pa ment Bonds
$ 1,316.70
Total: $ 67,151.70
THE BARRACKS II SUBDIVISION - PARK 6
Item
Description
Total
1
Site Preparation & Grading Subtotal
$ 2,750.00
2
Park Features Subtotal
$ 14,049.00
3
Volleyball Court Equipment
$ 8,269.50
4
Pavement Subtotal
$ 7,400.00
5
Ilrrigation System Subtotal
I $ 3,800.00
6
Landsca e Subtotal
$ 4,615.00
7
Performance & Payment Bonds
$ 817.67
Total: $ 41,701.17
.�-13
F-12327
SCHULTZ ENGINEERING, LLC.
Page i of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction
February 4,2013
Item
Description
Unit
Estimated
uantit
Unit Price
Total
Site Preparation & Grading
1
Mobilization & Construction Staking
LS
1
$750.001
$ 750.00
2
Site Grading
LS
1
$1,000.001
$ 1,000.00
3
1 Silt Fence, Construction Exit, and Erosion & Sediment Control
LS
1
$750.001
$ 750.00
Park Features
4
Park Bench
EA
2
$1,250.00
$ 2,500.00
5
6' Concrete Path, 4" Thick
SF
900
$4.20
$ 3,780.00
6
6" Wide Ribbon Curb
LF
270
$5.00
$ 1,350.00
7
Crushed Granite
SF
4,192
$1.25
$ 5,240.00
8
14'x22' Shade Structure
EA
1
$5,000.00
$ 5,000.00
10
1ADA Ramp
EA
2
$600.00
$ 1,200.00
Fitness Equipment
I l
Combo Press and Pull - CSPB - Sta. 1
EA
1
$3,970.00
$ 3,970.00
12
Leg Press - LEGP2 - Sta. 2
EA
1
$2,680.00
$ 2,680.00
13
Sit -Up Board -SITB1-Sta. 3
EA
l
$1,155.00
$ 1,155.00
14
Sit -Up Bench -STUP-Sta. 4
EA
l
$1,585.00
$ 1,585.00
15
Back Extension Apparatus - BEXT- Sta. 5
EA
1
$1,295.00
$ 1,295.00
16
Power Rower -RWRS-Sta. 6
EA
1
$1,625.00
$ 1,625.00
17
Rowing Machine -ROWR-Sta. 7
EA
t
$1,480.00
$ 1,480.00
18
lWar-Up Station -WMUP-Sta. 8
EA
1
$3,290.00
$ 3,290.00
19
Rider - Single -RDR1-Sta. 9
EA
l
$1,420.00
$ 1,420.00
20
Two -Person Rotator -TSOR- Sta. 10
EA
1
$1,715.05
$ 1,715.00
21
Pull -Up & Di Station - PDIP - Sta. 11
EA
l
$1,690.00
$ 1,690.00
22
Push -Up Bar - PSUP - Sta. 12
EA
1
$565.00
$ 565.00
23
Parallel Bars- PEAR - Sta. 13
EA
1
$850.00
$ 850.00
24
Horizontal Bar - Single -HBARI- Sta. 14
EA
1
$855.00
$ 855.00
25
Horizontal Ladder- HLAD - Sta. IS
EA
1
$2,275.00
$ 2,275.00
26
1 PI o Boxes - Set of 3 - PBOX - Sta. 16
EA
1
$1,945.00
$ 1,945.00
27
Multi-Bars-MBAR-Sta.17
EA
1
$1,550.00
$ 1,550.00
28
jBalance Beam - BABM -Sta. 18
EA
L
$855.00
$ 855.00
Parking Lot
29
lGrading
LS
1
$ 500.00
$ 500.00
30
5" Reinforced Concrete Pavement w/Standard Curb, complete in place
SY
140
$ 30.00
$ 4,200.00
31 1
Stri in & Si na e
LS
I
$ 500.00
$ 500.00
Irrigation System
32 11"
Water Service
EA
1
$800.001
$ 800.00
33 lWater
Meter
EA
1
$500.001
$ 500.00
34 11rrigation
System
LS
l
$2,500.001
$ 2,500.00
Page 2 of 4
THE BARRACKS II SUBDIVISION - PARK 1
Landscape
35
Non -Canopy Trees (>L25" Caliper)
EA
5
$100.00
$ 500.00
36
Canopy Trees (>2.5" Caliper)
EA
10
$250.00
$ 2,500.00
37
Shrub (min. 5 Gallon
EA
25
1
$25.00
$ 625.00
38
Bermuda Grass Seeding Inside Disturbed Area Limits)
SY
8.400
$0.10
$ 840.00
Site Preparation & Grading Subtotal
$
2,500.00
Park Features Subtotal
$
19,070.00
Fitness Equipment Subtotal
$
30,800.00
Pavement Subtotal
$
5,200:00
Irrigation System Subtotal
$
3,800.00
Landscape Subtotal
$
4,465.00
Performance & Payment Bonds
$
1316.70
TOTAL CONSTRUCTION $ 67,151.7
—01
Page 3 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 6
Engineer's Estimate of Construction
February 4.2013
Item
Description
p
Unit
Estimated
Quantity
Unit Price
Total
Site Preparation & Grading
1
Mobilization & Construction Staking
LS
I
$1,000.001
$ 1,600.00
2
Site Grading
LS
l
1 $1,000.001
$ 1,000.00
3
1 Silt Fence, Construction Exit, and Erosion & Sediment Control
LS
l
$750-001
$ 750.00
Park Features
4
Park Bench
EA
1 4
$1.250.001
$ 5.000.00
5
6' Concrete Path, 4" Thick
SF
235
$4.20
$ 987.00
6
Park Tables
EA
2
$1,531.00
$ 3,062.00
7
14'x22' Shade Structure
EA
1
$5,000.00
$ 5,000.00
Volleyball
Court Equipment
8
Volleyball Sand
SF
1 2,7301
$0.50
$ 1,365.00
9
Sand Volleyball Edge Guard
LF
1 3141
$9.251
$ 2,904.50
l0
Volle ball Nets and Poles
EA
1 2
$2,000.001
$ 4,000.00
Parking Lot
11
lGrading
LS
1
$ 500.00
$ 500.00
12
5" Reinforced Concrete Pavement w/Standard Curb, complete in place
SY
210
$ 30.00
1 $ 6,300.00
13
1 Stri in & Si na e
LS J
1
$ 600.00
1 $ 600.00
Irrigation System
14
1" Water Service
EA
1
$800.001
$ 800.00
15
Water Meter
Mon
EA
l
$500.00
$ 500.00
16
System
LS
1
$2,500.001
$ 2,500.00
Landscape
17
Non -Canopy Trees >1.25" Caliper)
EA
8
$100.00
$ 800.00
18
Canopy Trees >25' Caliper)
EA
10
$250.00
$ 2,500.00
19
Shrub min. 5 Gallon
EA
21
$25.00
$ 525.00
20
Bermuda Grass Seeding Inside Disturbed Area Limits
SY
7,900
$0.10
$ 790.00
Site Preparation & Grading Subtotal
Park Features Subtotal
Volleyball Court Equipment Subtotal
Pavement Subtotal
Irrigation System Subtotal
Landscape Subtotal
Performance & Payment Bonds
$ 2,790.00
$ 14 049.00
$ 8,269.50
$ 7,400.00
$ 3,800.00
$ 4,615.00
$ 817.67
TOTAL CONSTRUCTION $ 41,701.17
Page 4 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Final Construction Cost
Item
Description
Total
1
Site Preparation & Grading
$ 2,500.00
2
Park Features
$ 21,378.00
3
Fitness Equipment
$ 30,800.00
4
Parkin Lot
$ 5,200.00
5
Irrigation System
$ 3,830.00
6
ILandscape
$ 3,719.00
7
lPerformance & Payment Bonds
$ 2,724.00
Total: $ 70,151.00
THE BARRACKS II SUBDIVISION - PARK 6
Item
Description
Total
1
Site Preparation & Grading Subtotal
$ 2,750.00
2
Park Features Subtotal
$ 19,826.00
3
Volleyball Court Equipment
Subtotal
$ 10 243.50
4
Irrigation System Subtotal
$ 3,820.00
5
Landscape Subtotal
$ 3,897.00
6
Performance & Pa ent Bonds
$ 811.00
Total: $ 41,347.50
r-193 i
SCHULTZ. ENQINEERINGa M9,
Page 1 of 1
THE BARRACKS II SUBDIVISION - PARK I
Parking Lot
31
lGrading
LS
l
$ 500.00
1 $
500.00
32
5" Reinforced Concrete Pavement w/Standard Curb, complete in place
I SY
1 140
$ 30.00
1 $
4,200.00
33
1 Stri in & Si na a
LS
l
$ 500.00
1 $
500.00
Irrigation System
34
I" Water Service
EA
1
$800.001
$
800.00
35
Water Meter
EA
l
$500.00
$
500.00
36
Irrigation Sleeve
LF
3
$10.00
$
30.00
37
Irrigation System
LS
1
$2,500.001
$
2,500.00
Landscape
38
Non -Canopy Trees >1.25"Caliper)
EA
5
$100.00
$
500.00
39
CanopyTrees >2.5" Caliper)
EA
10
$250.00
$
2,500.00
40
Shrub min. 5 Gallon
EA
25
$25.00
$
625.00
41
Bermuda Grass Seeding Inside Disturbed Area Limits
SY
9401
$0.10
$
94.00
Site Preparation & Grading Subtotal
$
2,500.00
Park Features Subtotal
$
21,378.00
Fitness Equipment Subtotal
$
30,800.00
Pavement Subtotal
$
5,200.00
Irrigation System Subtotal
$
3,830.00
Landscape Subtotal
$
3,719.00
Performance & Payment Bonds
$
2,724.00
TOTAL PROJECTI
$
70,151.00
Page 3 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
THE BARRACKS II SUBDIVISION - PARK 6
Engineer's Estimate of Final Construction Cost
Item
Description
Unit
Estimated
Quantity
Unit Price
Total
Site Preparation & Grading
1
I Mobilization & Construction Staking
LS
1
$1,000.001
$ 1,000.00
2
2!Le Grading
I LS
I 1
1 $1,000.001
$ 1,000.00
3
Silt Fence, Construction Exit, and Erosion & Sediment Control
I LS
I 1
$750.001
$ 750.00
Park Features
4
Park Bench
EA
4
$1,250.00
$ 5,000.00
5
6' Concrete Sidewalk, 4" Thick
SF
1,975
$4.20
$ 8,295.00
6
Park Tables
EA
1
$1,531.00
$ 1,531.00
7
14'x22' Shade Structure
EA
1
$5,000.00
$ 5,000.00
Volleyball
Court Equipment
8
lVolleyball Sand
SF
1 4,9021
$0.50
$ 2,451.00
9
Sand Volleyball Edge Guard
LF
410
$9.25
$ 3,792.50
(0
Volleyball Nets and Poles
I EA
1 2
$2,000.00
$ 4,000.00
Irrigation System
11
1" Water Service
EA
1
$800,00
$ 800.00
12
Water Meter
EA
1
$500.00
$ 500.00
13
Irri ationSleeve
LF
2
$10.00
$ 20.00
14
Irrigation System
LS
1
$2,500.001
$ 2,500.00
Landscape
15
Non -Canopy Trees >1.25" Caliper)
EA
1 13
$100.001
$ 1,300.00
16
Canopy Trees >2.5"Caliper)
I EA
1 10
$250.001
$ 2,500.00
17
Bermuda Grass Seeding Inside Disturbed Area Limits
SY
1 9701
$0.101
$ 97.00
Site Preparation & Grading Subtotal
$
2,750.00
Park Features Subtotal
$
19,826.00
Volleyball Court Equipment Subtotal
$
10,243.50
Irrigation System Subtotal
$
3,820.00
Landscape Subtotal
$
3,897.00
Performance & Payment Bonds
$
811.00
TOTAL CONSTRUCTION1 $ 41,347.50
Page 4 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Final Construction Cost
Item
Description
Unit
Installed
QuantityUnit
Price
Total
Site Preparation & Grading
1
Mobilization & Construction Staking
LS
l
$750.001
$ 750.00
2
Site GradingLS
1
$1,000.00
$ 1,000.00
3
Silt Fence, Construction Exit, and Erosion & Sediment Control
I LS
1
$750,001
$ 750.00
Park Features
4
Park Bench
EA
2
$1,250.00
$ 2,500.00
5
6' Concrete Sidewalk, 4" Thick
SF
900
$4.20
$ 3,780.00
6
11" Mow Strip around Crushed Granite
LF
274
$5.50
$ 1,507.00
7
Crushed Granite
SF
4,328
$1.25
$ 5,410.00
8
14'x22' Shade Structure
EA
l
$5,000.00
$ 5,000.00
9
Park Tables
EA
1
$1,531.00
$ 1,531.00
10
ADA Si n
EA
1
$250.00
$ 250.00
11
Wheel Stop
EA
2
$100.00
$ 200.00
12
ADA Ramp
EA
2
$600.00
$ 1,200.00
Fitness Equipment
13
Combo Press and Pull - CSPB - Sta. 1
EA
1
$3,970.00
$ 3,970.00
14
Leg Press - LEGP2 - Sta. 2
EA
1
$2,680.00
$ 2,680.00
15
Sit -Up Board -SITB1-Sta. 3
EA
I
$1,155.00
$ 1,155.00
16
Sit -Up Bench -STUP-Sta. 4
EA
1
$1,585.00
$ 1,585.00
17
Back Extension Apparatus -BEXT-Sta.5
EA
1
$1,295.00
$ 1,295.00
18
Power Rower -RWRS-Sta. 6
EA
1
$1,625.00
$ 1,625.00
19
RowingMachine -ROWR-Sta. 7
EA
1
$1,480.00
$ 1,480.00
20
lWar-Up Station -WMUP-Sta. 8
EA
1
$3,290.00
$ 3,290.00
21]Rider
- Single -RDR1-Sta. 9
EA
1
$1,420.00
$ 1,420.00
22
Two -Person Rotator -TSOR- Sta. 10
EA
1
$1,715.00
$ 1,715.00
23
Pull -Up & Dip Station -PDIP- Sta. 11
EA
1
$1,690.00
$ 1,690.00
24
Push -Up Bar -PSUP- Sta. 12
EA
1
$565.00
$ 565.00
25
Parallel Bars - PBAR - Sta. 13
EA
1
$850.00
$ 850.00
26
Horizontal Bar -Single-HBARI- Sta. 14
EA
1
$855.00
$ 855.00
27
Horizontal Ladder -HLAD- Sta. 15
EA 1
$2,275.00
$ 2,275,50
28
Plyo Boxes - Set of 3 - PBOX - Sta. 16
EA
t
$1,945.00
$ 1,945.00
29
Multi -Bars- MBAR - Sta. 17
EA
1
$1,550.00
$ 1,550.00
30
Balance Beam- BABM - Sta.18
EA
1
$855.00
$ 855.00
Page 2 of 4
THE BARRACKS II SUBDIVISION - PARK 1
Parking Lot
31
lGrading
LS
t
$ 500.00
$ 500.00
32
5" Reinforced Concrete Pavement w/Standard Curb, com lete in place
SY
140
$ 30.00
$ 4,200.00
33
1 Striping & Si na a
LS
1
$ 500.00
$ 500.00
Irrigation System
34
1" Water Service
I EA
1 11
$800.00
$ 800.00
35
Water Meter
EA
i
$500.00
$ 500,00
36
Irri ation Sleeve
LF
24
240.00
37
Irrigation System
LS2,500.00
Landscape
38
Non -Canopy Trees >1.25" Caliper)
EA
5
$100.00
$ 500.00
39
Canopy Trees >2.5" Caliper)
EA
l0
$250.00
$ 2,500.00
40
Shrub min.5 Gallon)EA
25
$25.001
$ 625.00
41
Bermuda Grass Seeding Inside Disturbed Area Limits
SY
940
$0.101
$ 94.00
Site Preparation & Grading Subtotal
$
2,500.00
Park Features Subtotal
$
22,498.00
Fitness Equipment Subtotal
$
30,800.00
Pavement Subtotal
$
5,200:00
Irrigation System Subtotal
$
4,040.00
Landscape Subtotal
$
3,719.00
Performance & Payment Bonds
$
1,375.00
TOTAL CONSTRUCTION $ 70,132.00
Page 3 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
THE BARRACKS II SUBDIVISION - PARK 6
Engineer's Estimate of Construction
Fehruary 2R_ 2013
Item
Description
IUnit
Estimated
Unit Price
Total
uanti
Site Preparation &Grading
t Imobilization & Construction Staking LS I 1 $I,000.00 $ 1,000.00
2 ISiteGradin LS I 1 $1,000.00 $ 1,000.00
3 1 Silt Fence, Construction Exit, and Erosion & Sediment Control I LS 1 $750.00 $ 750.00
Park Features
4
Park Bench
EA
4
$1,250.00
$ 5,000.00
5
6' Concrete Sidewalk, 4" Thick
SF
1,975
$4.20
$ 8,295.00
6
Park Tables
EA
2
$1,531.00
$ 3,062.00
7 14'x22' Shade Structure EA 1 $5,000.00 $ 5,000.00
Volleyball Court Equipment
8 JVolleyball Sand SF 4,902 $0.50 $ 2,451.00
9 Sand VolleyballEdge Guard LF 410 $9.25 $ 3,792.50
IO Volleyball Nets and Poles EA 2 $2,000.00 $ 4,000,00
Irrigation System
1I
V Water Service
EA 1
$800.00
$ 800,00
12
Water Meter
EA 1
$500.00
$ 500.00
13
Irrigation Sleeve
LF 16
$10.00
$ 160.00
14
Irrigation System
LS t
$2,500.00
$ 2,500.00
Landscape
15
Non -Can o Trees >1.25" Cali er
EA 1
13
$100.00
$ 1,300.00
16
Canopy Trees >2.5"Caliper) I
EA2,500.00
17
Bermuda Grass SeedingInside Disturbed Area Limits
SY
970
$0.10
$ 9 .00
Site Preparation & Grading Subtotal
Park Features Subtotal
Volleyball Court Equipment Subtotal
Irrigation System Subtotal
Landscape Subtotal
Performance & Payment Bonds
$
2,750.00
$
21,357.00
$
10,243.50
$
3,960.00
$
3,897.00
$
844.00
TOTAL CONSTRUCTION r$ 43,051.507
Page 4 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction
February 28,2013
Item
Description
P
Unit
Estimated
U nit Price
Tota(
uanti
Site Preparation &Grading
I
Mobilization & Construction Stakin
LS
l
750.00
2
ISiteGradingLS
1
$1,000.00
$ 1,000.0O
3
1 Silt Fence, Construction Exit, and Erosion & Sediment Control
LS
t
$750.001
$ 750.00
Park Features
4
Park Bench
EA
2
$1,250.00
$ 2,500.00
5
6' Concrete Sidewalk, 4" Thick
SF
900
$4.20
$ 3,780.00
6
4" Wide Recycled Plastic Ed in
LF
274
$4.00
$ 1,096.00
7
Crushed Granite
SF
4,328
$1.25
$ 5,410.00
8
14'x22' Shade Structure
EA
1
$5,000.00
$ 5,000.00
9
IParkTables
EA
2
$1,531.00
$ 3,062.00
10
ADA Sign
EA
1
$250,00
$ 250.00
11
Wheel Stop
EA
2
$100.00
$ 200,00
12 ADA Ramp EA 2 $600,00 $ 1,200.00
Fitness Equipment
13
Combo Press and Pull - CSPB - Ste. 1
EA
1
$3,970.00
$ 3,970.00
14
Leg Press - LEGP2 - Ste. 2
EA
1
$2,680.00
$ 2,680.00
15
Sit -Up Board -SITB3-Sta. 3
EA
1
$1,155.00
$ 1,155.00
16
Sit -Up Bench -STUP-Sta. 4
EA
I
$1,585.00
$ 1,585.00
17
Back Extension Apparatus -BEXT-Sta. 5
EA
1
$1,295.00
$ 1,295.00
18
Power Rower - RWRS - Sta. 6
EA
I
$1,625.00
$ 1,625.00
19
Rowing Machine -ROWR-Sta. 7
EA
1
$1,480.00
$ 1,480,00
20
War -Up Station - WMUP - Sta. 8
EA
1
$3,290.00
$ 3,290.00
21
Rider - Single -RDR1-Sta. 9
EA
l
$1,420.00
$ 1,420.00
22
Two -Person Rotator -TSOR- Sta. 10
EA
I
$1,715.00
$ 1,715.00
23
Pull -Up & Dip Station -PDIP- Sta. 11
EA
1
$1,690.00
$ 1,690.00
24
Push -Up Bar -PSUP- Sta. 12
EA
1
$565.00
$ 565.00
25
Parallel Bars- PBAR- Sta. 13
EA
1
$850.00
$ 850.00
26
Horizontal Bar - Single -HBAR1- Sta. 14
EA
1
$855.00
$ 855.00
27 1
Horizontal Ladder -HLAD- Ste. 15
EA
l
$2,275.00
$ 2,275.00
28
Plyo Boxes - Set of 3 - PBOX - Sta. 16
EA
1
$1,945.00
$ 1,945.00
29
Multi -Bars- MBAR - Sta. 17
EA
l
$1,550.00
$ 1,550,00
30 1
Balance Beam - BABM - Sta. 18
EA
1
$855.00
$ 855.00
Page 2 of 4
SCHULTZ ENGINEERING, LLC,
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No.12327
THE BARRACKS II SUBDIVISION - PARK 1
Engineer's Estimate of Construction Summary
February 28, 2013
Item
Description
Total
1
Site Preparation & Grading
$ 2,500.00
2
Park Features
$ 22,498.00
3
Fitness Equipment
$ 30,800.00
4
Parkin Lot
$ 5,200.00
5
Irrigation System
$ 4,040.00
6
ILandscape
$ 3,719.00
7 1
Performance & Payment Bonds
$ 1,375.00
Total: $ 70,132.00
THE BARRACKS II SUBDIVISION - PARK 6
Item
Description
Total
1
Site Preparation & Grading Subtotal
$ 2,750.00
2
Park Features Subtotal
$ 21,357.00
3
Volleyball Court Equipment
$ 10,243.50
4
Irri ation System Subtotal
$ 3,960.00
5
Landsca a Subtotal
$ 3,897.00
6
Performance & Payment Bonds
$ 844.00
al: $ 43,051.50
5CHULTZ ENGINEEFIINO LLC.
Page 1 of 4
(* 41
CITY OF COLLP:GH STATION
Home of Texas A6M University'
MEMORANDUM
February 28, 2013 /AL—
TO: Heath Phillips; via: heath@barrackstownhomes.com�//
FROM: Matt Robinson, Staff Planner
SUBJECT: The Barracks II Parks 1 & 6 (Sp) - Site Plan
Staff reviewed the above -mentioned site plan as requested. The following page is a list of staff
review comments detailing items that need to be addressed. The next submittal will be the third
and final review by staff for this round of reviews. Please address the comments and submit the
following information by any Monday at 10:00 a.m. for further staff review:
City of College Station Transmittal Letter
Seven (7) complete sets of site civil construction documents for the proposed
development with the revised site and landscaping plans attached (one set will
be returned to you, please submit additional copies if you want more than one
approved set)
Letter of credit
Please note that this application will expire in 90 days from the date of this memo, if the
applicant has not provided written response comments and revised documents to the
Administrator that seek to address the staff review comments contained herein. If there are
comments that you are not addressing with the revised site plan, please attach a letter
explaining the details. If you have any questions or need additional information, please call me
at 979.764.3570.
Attachments: Staff review comments
cc: Joe Schultz, Schultz Engineering, LLC; via: joeschultz84@verizon.net
Case file #13-00900033
Planning & Development Services
P.O. BOX 9960 • 1 [01 TEXAS ANT.NUL. • COI LEGE STATION - TEXAS • 77942
TEL 979.764, i570 - IAX. 479.764.3496
cstx.gov/devservices
STAFF REVIEW COMMENTS NO. 2
Project: The Barracks II Parks 1 & 6 (Sp) - 13-00900033
PLANNING
1. Based on the cost estimate provided, 313 lots will be credited towards meeting the
neighborhood parkland development fees (113,183.50 / 362 = 313).
2. Please note that any changes made to the plans, that have not been requested by the City
of College Station, must be explained in your next transmittal letter and "bubbled" on your
plans. Any additional changes on these plans that the City has not been made aware of will
constitute a completely new review.
Reviewed by: Matt Robinson
ENGINEERING COMMENTS NO. 2
Date: 2/28/13
1. FYI -The sidewalk on Park 1 does not line up correctly with the existing parkland across the
alley. If constructed in this way, it may need to be demolished and reconstructed in the
future.
Reviewed by: Danielle Singh Date: 2/28/13
ro 0�9
w.
CITY Olz COI LFCGP. STATION
Home of Texas A6,M Uninersiiy'
MEMORANDUM
February 22, 2013
TO: Heath Phillips; via: heath@barrackstownhomes.com
FROM: Matt Robinson, AICP, Senior Planner
SUBJECT: The Barracks II Parks 7 & 6 (SP) - Site Plan
Staff reviewed the above -mentioned site plan as requested. The following page is a list of staff
review comments detailing items that need to be addressed. Please address the comments and
submit the following information by any Monday at 10:00 a.m. for further staff review:
City of College Station Transmittal Letter;
Memo providing written responses to all of staff's comments (identify the specific
page that each comment was addressed on or the reason for not addressing the
comment);
Two (2) revised site plans;
One (1) landscaping plan;
One (1) 11x17 grading and erosion control plan.
Please note that this application will expire in 90 days from the date of this memo, if the
applicant has not provided written response comments and revised documents to the
Administrator that seek to address the staff review comments contained herein. If there are
comments that you are not addressing with the revised site plan, please attach a letter
explaining the details. If you have any questions or need additional information, please contact
me at 979.764.3570,
Attachments: Staff review comments
PC: Joe Schultz, Schultz Engineering, LLC; via: joeschultz84@verizon.ne
Case file #13-00900033
Planning & Development Services
V.O. BOX 9960 - 1101 TT.XAS AVENIT - COLUGF. STATION • FFXAS - 77542
'I F.L. 979.761.7570 • FAX. 979.7Gti.3496
cstx.gov/devservices
STAFF REVIEW COMMENTS NO. 1
Project: The Barracks II Parks 1 & 6 (SP) — 13-00900033
PLANNING
1. We will calculate the lot credit for the neighborhood park development fee, when the cost
estimate is revised. Lots platted after approval of this site plan will be credited towards
meeting this requirement, any plats filed prior to approval of this site plan will not be credited
back.
The sidewalk shown on the preliminary plan (Park 6) is not reflected on the site plan (only a
callout that does not point to a sidewalk).
Please note that any changes made to the plans, that have not been requested by the City
of College Station, must be explained in your next transmittal letter and "bubbled" on your
plans. Any additional changes on these plans that the City has not be made of aware of will
constitute a completely new review.
Reviewed by: Matt Robinson Date: 2/21/13
LAN DSCAPING/STREETSCAPING/BUFFER
The areas surrounding the volleyball court and workout stations will need to be treated with
groundcover (no label is provided in the legend/on plan).
Provide a general note that 100% coverage of groundcover, decorative paving, decorative
rock (not loose), or a perennial grass is required in parking lot islands, swales and drainage
areas, the parking lot setback, rights -of -way, and adjacent property disturbed during
construction.
Reviewed by: Matt Robinson Date: 2/21/13
MISCELLANEOUS
1. Irrigation system must be protected by either a Pressure Vacuum Breaker, a Reduced
Pressure Principle Back Flow Device, or a Double -Check Back Flow Device, and installed
as per City Ordinance 2394.
2. All BackFlow devices must be installed and tested upon installation as per City Ordinance
2394.
ENGINEERING
1. Please provide a grading plan with existing contours.
2. Please label the surface material surrounding the exercise stations in Park 1.
3. Based on the notes, will each station be located on a concrete pad? Please label
dimensions.
Based on the engineer's estimate, I assume the border for Park 1 is a ribbon curb. Please
label and provide a detail.
What is the surface and border surrounding the volleyball courts? Details are needed for
this.
The scale at the bottom of sheet C2 is not correct.
Parking maneuvers are required to be made onsite, unless there is access off of an alley.
Park 6 will need to remove the parking or provide an area to accommodate parking and
onsite maneuvering.
8. On the preliminary plan, the sidewalk in Park 1 is intended to connect to the nearby
parkland. I think the end of the sidewalk may need to be adjusted to accommodate the
future connection.
9. Please provide an acknowledgement that the project was designed according to City
standards.
Reviewed by: Danielle Singh
SANITATION
1. Sanitation is ok with this project.
Date: 2/14/2013
Reviewed by: Wally Urrutia Date: February 13, 2013
may.
CITY OF Coi i FiGF STATION
Hoare ofTexra l cW University`
MEMORANDUM
February 7, 2013
TO: Heath Phillips; via: heath@barrackstownhomes.com
FROM: Jason Schubert, AICP
Principal Planner
SUBJECT: THE BARRACKS II PARKS 1 & 6 (SP)
Thank you for the submittal of your SITE PLAN application. This project will be distributed to
staff next week for their review.
cc: Joe Schultz, Schultz Engineering, LLC; via: joeschultz84@verizon.net f/
Case file no. 13-00900033
Planning & Development Services
P.O. BOX9960 • 1101 "PEXAS AVENIIE - COLLEGESIAI ION •'PE;XAS •'7784a
117.1. 979.764.3570 -FAX, 979.764.349(,
cs6(.gov/devse rvices