August 27, 2012
TO: Mike Coontz. Weiner Development, via email:mcoontz@weinerdevelopment.com
FROM: Erika Bridges, Graduate Civil Engineer
SUBJECT: Engineering Document Comments for Tower Point Phase 11 B Lot 9 & 10
Block 3
Staff reviewed the above -mentioned engineering documents as requested. The following page
is a list of staff review comments detailing items that need to be addressed. Please address the
comments and submit the following information by any Monday at 10:00 a.m. for further staff
review and approval of the plans:
One (1)set of revised construction documents.
Please note that the Development Permit Balance (Public Infrastructure Review and Inspection
Fee), will be calculated and requested once the construction documents and engineer's
estimates have been reviewed and approved.
If you have any questions or need additional information, please call me at 979.764.3570.
Attachments: Staff review comments
cc: Kling Engineering & Surveying, via email: stewart@klingeng.com
Alfred Lehtonen, via email: lehtonenitd@verizon.net
Case File No. 12-00500172
ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION
1. SITE PLAN/PLAT: Developer will provide CSU with a digital, AutoCAD dwg format, version
of plat and / or site plan as soon as it is available. Email to: gmartinez(cD-cstx.gov.
2. LOAD DATA: The developer will provide load data to CSU as soon as it is available. This
information is critical for CSU to accurately determine the size and number of transformers,
and other equipment, required to provide service to the project. Failure to provide load data
will result in construction delays and, due to clearance requirements, could affect the final
building footprint. Delivery time for transformers and other equipment not in stock is
approximate 26 weeks.
3. CONDUIT INSTALLATION: Conduits for electrical routing as designed by CSU will be
provided and installed under private drives or roadways within the project site by
Developer/Contractor. CSU will make every effort to place conduits where necessary so
they can be installed before private drives or roadways are built. If site plans or building
layouts change as the project develops the developer/contractor will be responsible for
boring conduit under private drives or roadways as necessary.
4. EASEMENTS: Developer provides temporary blanket easement for construction purposes
and upon completion of project must provide descriptive easements for electric infrastructure
as designed by CSU.
5. If easements are existing, the developer will be responsible for locating easements on site to
insure that electrical infrastructure is installed within easement boundaries.
GENERAL ELECTRICAL COMMENTS
1. Developer installs conduit per CSU specs and design.
2. CSU will provide drawings for electrical installation.
3. Developer provides 30' of rigid or IMC conduit for each riser conduit. CSU installs riser.
4. Developer will intercept existing conduit at designated transformers or other existing devices
and extend as required.
5. If conduit does not exist at designated transformer or other existing devices, developer will
furnish and install conduit as shown on CSU electrical layout.
6. Developer pours electric device pads or footings, i.e. transformers, pull boxes, or other
device, per CSU specs and design.
7. Developer installs pull boxes per CSU specs and design, Pull boxes provided by CSU.
8. Final site plan must show all proposed electrical facilities necessary to provide electrical
service, i.e. transformers, pull boxes, or switchgears, all meter locations, and conduit routing
as designed by CSU.
9. To discuss any of the above electrical comments please contact Gilbert Martinez at
979.764.6255.
Reviewed by: Gilbert Martinez Date: 08.27.2012
ENGINEERING COMMENTS NO. 1
1. Per Fire, the proposed drive may not be labeled as a fire line until the median along
Drive A is removed.
2. Paver crosswalks and ramps need to be added at the intersection with Drives A & D.
3. Sh.C2.1 — Please change sheet title from SWP3 to Erosion Control Plan.
4. Sh.C3.1 — Please show and label the plan view of the proposed grate inlets, including
dimensions.
5. Sh.C2.1 — Please reference Spec 32 92 19 "Seeding for Erosion Control' in the notes
regarding re -vegetation.
6. Drainage Letter — While we do not find it necessary to re -analyze the storm system
along Drives A & D, please include in your drainage letter the capacity of the storm
sewer being removed compared to the capacity of the storm sewer being added. This
letter should also be sealed.
Reviewed by: Erika Bridges Date: 8/27/12
SANITATION
1. Sanitation is ok with this project.
Reviewed by: Wally Urrutia Date: August 23, 2012
TxDOT Comments
1. - No Comment (no additional access to state system)
Reviewed by: Chad Bohne Date: 8/24/2012