Engineer's Cost Estimate
CREEK MEADOWS -SECTION 3, PHASE TWO
G.P.T. BAR-DITCH
COLLEGE STATION, BRAZOS COUNTY, TEXAS
UNIT
DESCRIPTION QUANTITY UNIT COST
Mobilization, Construction Staking & All Required 1 LS $1 ,200.00 Testing by Contractor
SWPP Measures (Rock Rip-Rap & Hydro-Mulch 1 LS $2,500.00 Seeding)
Remove Existing CMP Driveway Culvert 2 EA $500.00
In-Place Earthwork Excavation 1,670 CY $4.00
In-Pace Earthwork Embankment 150 CY $4.50
6:1 SET (18" Pipe) 2 EA $800.00
18" RCP (CL 3) Storm Sewer w/Cement Stabilized 40 LF $75.00 Sand Bedding & Structural Backfill
Remove & Reinstall Existing 18" RCP (CL 3) Storm
Sewer w/Cement Stabilized Sand Bedding &
Structural Backfill w/6:1 SET (Both Sides)
Emergency Roadway Patch
,,,,,,, ,,
40 LF $50.00
1 LS $800.00
ESTIMATED CONSTRUCTION COST =
10% CONTINGENCY=
TOTAL
COST
$1,200.00
$2,500.00
$1,000.00
$6,680.00
$675.00
$1 ,600.00
$3,000.00
$2,000.00
$800.00
$19,455.00
$1,945.50
GRAND TOTAL= $21,400.50
,
RME Consulting Engineers
TEXAS FIRM REGISTRATION No. F-4695
POST OFFICE BOX 9253
COLLEGE STATION, TEXAS 77842
OFF/FAX: (979) 764-0704
E-mail: civil@rmengineer.com
Estimates and projections prepared by RME Consulting Engineers relating to construction costs and schedules, operation and
maintenance costs, equipment characteristics and performance, and operating results are based on this office's experience,
qualifications and judgment as a design professional. Since RME has no control over weather, cost and availability of labor,
material and equipment, labor productivity, construction contractor's procedures and methods, unavoidable delays,
construction contractor's methods of determining prices, economic conditions, competitive bidding or market conditions and
other factors affecting such estimates or projections, this office does not guarantee that actual rates, costs, performance,
schedules, etc., will not vary from estimates and projections prepared by the Engineer ofrecord.