HomeMy WebLinkAboutSTAFF COMMENTSCITY OF COLLEGE STATION Home ofTe A6M University' 1101 Texas Avenue, P.O. Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM March 15, 2012 TO: Jason Kinnard, Jim Singleton Architects, via email Jason(cDisarchitects.com FROM: Jason Schubert, AICP Principal Planner SUBJECT: BCS REGIONAL ASSOCIATION OF REALTORS (SP/NRA) Thank you for the submittal of your SITE PLAN - COMMERCIAL and NON-RESIDENTIAL ARCHITECTURE STANDARDS applications. This project will be distributed to staff next week for their review. cc: B/CS Regional Association of Realtors, via email: executiveofficer(cDbcsreaIto r.com Fred Paine, Kling Engineering & Surveying, via email fred(cDklingeng.com Case file no. 12-00500056 (SP) Case file no. 12-00500057 (NRA) 1101 Texas Avenue, P.O. Box 9960 1/ College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 r n UAI J:GIS STATION Jr —ABM Uxlwniry' MEMORANDUM March 29, 2012 TO: Jason Kinnard, Jim Singleton Architects, via email: Jason(cDisarchitects.com FROM: Teresa Rogers, Staff Planner Jason Schubert, AICP, Principal Planner SUBJECT: B/CS Regional Association of Realtors (SP) Staff reviewed the above -mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. Please address the comments and submit the following information by any Monday at 10:00 a.m. for further staff review: City of College Station Transmittal Letter; Memo providing written responses to all of staff's comments (identify the specific page that each comment was addressed on or the reason for not addressing the comment); Seven (7) complete sets of site civil construction documents for the proposed development with the revised site and landscaping plans attached (one set will be returned to you, please submit additional copies if you want more than one approved set); Two (2) revised site plans; One (1) landscaping plan; One (1) 11x17 grading and erosion control plan; Easement Dedication Sheet and required documents (please note that the Site Plan will not be stamped approved until the Blanket Easement, or all other appropriate easements, have been dedicated to the City of College Station). Please note that this application will expire in 90 days from the date of this memo, if the applicant has not provided written response comments and revised documents to the Administrator that seek to address the staff review comments contained herein. If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please contact Teresa Rogers at 979.764.3570. Attachments: Staff review comments PC: B/CS Regional Association of Realtors, via email: executiveofficer(cDbcsreaIto r.com Fred Paine, Kling Engineering & Surveying, via email: fred(ftlingeng.com Case file no. 12-00500056 (SP) Home of TexasA&M University, STAFF REVIEW COMMENTS NO. 1 Project: B/CS Regional Association of Realtors (SP — 12-00500056) PLANNING 1. According to the Crescent Pointe Protective Covenants the minimum requirements for parking and paving setbacks have not been met. Please review these requirements and revise as necessary. 2. The end parking space located closest to Lot 9R is approximately 15 feet in depth and interferes with the drive aisle. Revise the parking space to meet the minimum size requirements of 9 feet by 18 feet and additionally insure the drive aisle has a minimum 23 foot clearance. The end island dimensions must also continue to meet the 180 square feet minimum size requirement. 3. Label parking setback distance from R.O.W. to curb of parking lot. 4. Label the striping across the driveway. It appears to be a painted handicapped accessible route. 5. Provide temporary curbing, according to Site Design Standards, at the Phase Line boundary. 6. Revise the bike rack detail on C4.1 and Site Notes # 81 to match. 7. Please clarify how sanitation will be served for Phase 1. Phasing must be completed so that each individual phase meets all requirements. Currently, the dumpster is included in Phase 2 construction, but it may be necessary as part of Phase 1. 8. Verify the proposed hammerhead for dumpster access meets the Site Design Standards required for a turnaround. 9. Site Specific Note #7 should be amended to include the proposed use and improvements. 10. Add a label on the Site Plan noting the gross square footage of the building. 11. Revise the general note on the site plan that all roof and ground -mounted mechanical equipment shall be screened from view or isolated so as not to be visible from any public right-of-way or residential district within 150' of the subject lot, measured from a point five feet above grade. Such screening shall be coordinated with the building architecture and scale to maintain a unified appearance. 12. Please note that any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter. Any additional changes on these plans that the City has not be made of aware of will constitute a completely new review. 13. Item # 30 is missing from the Verizon & Suddenlink Cable Notes. Is this intended to be item # 33? Reviewed by: Teresa Rogers Date: March 28, 2012 LANDSCAPING/STREETSCAPING/BUFFER 1. Point totals provided for the shrubs, as part of the plant list, should be revised giving Maiden Grass 270 points and Texas Sage 740 points, for a total of 1,010 points. 2. Revise General Notes to include the following: Irrigation system must be protected by either a Pressure Vacuum Breaker, a Reduced Pressure Principle Back Flow Device, or a Double - Check Back Flow Device, and installed as per City Ordinance 2394. 3. Revise General Notes to include the following: All back flow devices will be installed and tested upon installation as per City Ordinance 2394. Reviewed by: Teresa Rogers Date: March 28, 2012 Page 2 of 2 ENGINEERING COMMENTS NO. 1 1. Please submit an NOI. 2. Please submit an Engineer's Cost Estimate. 3. Please submit a Letter of Acknowledgment. 4. C1.1 —What portion of the storm will be built with Phase I construction? 5. C1.1 — Label the water meter sizes. 6. C1.1 — Add a note indicating building size, construction material type, whether or not the building will be sprinkled, and the required fire flow per the 2012 IFC. 7. C1.1 — Please label each fire hydrant with required fire flow to achieve the necessary total. 8. C1.1 — Add note specifying the material of the private water, sanitary sewer, and storm sewer lines. 9. C1.1 — Label the volume and page number of the 10-ft Verizon Easement. 10. C2.1 —Add IPB to curb inlet just downstream of property. 11. C2.1 — Please remove "SWPY from the title block. 12. C2.1 — Add City Standard Details for Erosion Control. 13. C3.1 — Use City Standard Details for public curb ramps and storm sewer. 14. C3.1 — Please show the fire hydrant and water, phone, and sanitary sewer lines in profile crossing the storm. It looks like there may be some conflicts. 15. C3.1 — Although the possibility of running a parallel HDPE storm sewer was previously discussed, we feel that the other option you proposed of tying into the original storm sewer and upsizing a portion of that pipe is actually preferable. At that time, we were unaware of numerous utilities including storm, water, fire hydrant, sanitary sewer, gas, telephone, and cable running in that portion of the right-of-way with little separation distance and potential crossing conflicts. Please revise. Reviewed by: Erika Bridges Date: 3/30/12 GENERAL ELECTRICAL COMMENTS NO. 2 1. Developer installs conduit per CSU specs and design. 2. CSU will provide drawings for electrical installation. 3. Developer will intercept existing conduit at designated transformers or other existing devices and extend as required. 4. If conduit does not exist at designated transformer or other existing devices, developer will furnish and install conduit as shown on CSU electrical layout. 5. Developer provides load data to CSU as soon as it is available to avoid construction delays. Delivery time for transformers not in stock is approximately 24 weeks. 6. Final site plan must show all proposed electrical facilities necessary to provide electrical service, i.e. transformer(s), pull box(es), switchgear(s), meter location and conduit routing as designed by CSU. 7. To discuss any of the above electrical comments please contact Sam Weido at 979.764.6314. Reviewed by: Sam Weido Date: 5.10.12 1101 Texas Avenue, P.O. Box 9960 1/ College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 r n UAI J:GIS STATION Jr —ABM Uxlwniry' MEMORANDUM April 2, 2012 TO: Jason Kinnard, Jim Singleton Architects, via email: Jason(cDisarchitects.com FROM: Teresa Rogers, Staff Planner Jason Schubert, AICP, Principal Planner SUBJECT: B/CS Regional Association of Realtors (SP) Staff reviewed the above -mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. Please address the comments and submit the following information by any Monday at 10:00 a.m. for further staff review: City of College Station Transmittal Letter; Memo providing written responses to all of staff's comments (identify the specific page that each comment was addressed on or the reason for not addressing the comment); Seven (7) complete sets of site civil construction documents for the proposed development with the revised site and landscaping plans attached (one set will be returned to you, please submit additional copies if you want more than one approved set); Two (2) revised site plans; One (1) landscaping plan; One (1) 11x17 grading and erosion control plan; Please note that this application will expire in 90 days from the date of this memo, if the applicant has not provided written response comments and revised documents to the Administrator that seek to address the staff review comments contained herein. If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please contact Teresa Rogers at 979.764.3570. Attachments: Staff review comments PC: B/CS Regional Association of Realtors, via email: executiveofficer(cDbcsreaIto r.com Fred Paine, Kling Engineering & Surveying, via email: fred(ftlingeng.com Case file no. 12-00500056 (SP) STAFF REVIEW COMMENTS NO. 1 Project: B/CS Regional Association of Realtors (SP — 12-00500056) PLANNING COMMENTS 1. According to the Crescent Pointe Protective Covenants the minimum requirements for parking and paving setbacks have not been met. Please review these requirements and revise as necessary. 2. The end parking space located closest to Lot 9R is approximately 15 feet in depth and interferes with the drive aisle. Revise the parking space to meet the minimum size requirements of 9 feet by 18 feet and additionally insure the drive aisle has a minimum 23 foot clearance. The end island dimensions must also continue to meet the 180 square feet minimum size requirement. 3. Label parking setback distance from R.O.W. to curb of parking lot. 4. Label the striping across the driveway. It appears to be a painted handicapped accessible route. 5. Provide temporary curbing, according to Site Design Standards, at the Phase Line boundary. 6. Revise the bike rack detail on C4.1 and Site Notes # 81 to match. 7. Please clarify how sanitation will be served for Phase 1. Phasing must be completed so that each individual phase meets all requirements. Currently, the dumpster is included in Phase 2 construction, but it may be necessary as part of Phase 1. 8. Verify the proposed hammerhead for dumpster access meets the Site Design Standards required for a turnaround. 9. Site Specific Note #7 should be amended to include the proposed use and improvements. 10. Add a label on the Site Plan noting the gross square footage of the building. 11. Revise the general note on the site plan that all roof and ground -mounted mechanical equipment shall be screened from view or isolated so as not to be visible from any public right-of-way or residential district within 150' of the subject lot, measured from a point five feet above grade. Such screening shall be coordinated with the building architecture and scale to maintain a unified appearance. 12. Please note that any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter. Any additional changes on these plans that the City has not be made of aware of will constitute a completely new review. 13. Item # 30 is missing from the Verizon & Suddenlink Cable Notes. Is this intended to be item # 33? Reviewed by: Teresa Rogers Date: March 28, 2012 LANDSCAPING/STREETSCAPING/BUFFER COMMENTS 1. Point totals provided for the shrubs, as part of the plant list, should be revised giving Maiden Grass 270 points and Texas Sage 740 points, for a total of 1,010 points. 2. Revise General Notes to include the following: Irrigation system must be protected by either a Pressure Vacuum Breaker, a Reduced Pressure Principle Back Flow Device, or a Double - Check Back Flow Device, and installed as per City Ordinance 2394. 3. Revise General Notes to include the following: All back flow devices will be installed and tested upon installation as per City Ordinance 2394. Reviewed by: Teresa Rogers Date: March 28, 2012 Page 2 of 4 ENGINEERING COMMENTS 1. Please submit an NOI. 2. Please submit an Engineer's Cost Estimate. 3. Please submit a Letter of Acknowledgment. 4. C1.1 -What portion of the storm will be built with Phase I construction? 5. C1.1 - Label the water meter sizes. 6. C1.1 - Add a note indicating building size, construction material type, whether or not the building will be sprinkled, and the required fire flow per the 2012 IFC. 7. C1.1 - Please label each fire hydrant with required fire flow to achieve the necessary total. 8. C1.1 - Add note specifying the material of the private water, sanitary sewer, and storm sewer lines. 9. C1.1 - Label the volume and page number of the 10-ft Verizon Easement. 10. C2.1 - Add IPB to curb inlet just downstream of property. 11. C2.1 - Please remove "SWPY from the title block. 12. C2.1 - Add City Standard Details for Erosion Control. 13. C3.1 - Use City Standard Details for public curb ramps and storm sewer. 14. C3.1 - Please show the fire hydrant and water, phone, and sanitary sewer lines in profile crossing the storm. It looks like there may be some conflicts. 15. C3.1 - Although the possibility of running a parallel HDPE storm sewer was previously discussed, we feel that the other option you proposed of tying into the original storm sewer and upsizing a portion of that pipe is actually preferable. At that time, we were unaware of numerous utilities including storm, water, fire hydrant, sanitary sewer, gas, telephone, and cable running in that portion of the right-of-way with little separation distance and potential crossing conflicts. Please revise. Reviewed by: Erika Bridges Date: March 30, 2012 GENERAL ELECTRICAL COMMENTS 1. Developer installs conduit per CSU specs and design. 2. CSU will provide drawings for electrical installation. 3. Developer will intercept existing conduit at designated transformers or other existing devices and extend as required. 4. If conduit does not exist at designated transformer or other existing devices, developer will furnish and install conduit as shown on CSU electrical layout. 5. Developer provides digital AutoCAD 2000 or later version of plat and / or site plan. Email to: sweido@csbc.gov. 6. Developer provides load data to CSU as soon as it is available to avoid construction delays. Delivery time for transformers not in stock is approximately 24 weeks. 7. Final site plan must show all proposed electrical facilities necessary to provide electrical service, i.e. transformer(s), pull box(es), switchgear(s), meter location and conduit routing as designed by CSU. 8. To discuss any of the above electrical comments please contact Sam Weido at 979.764.6314. Reviewed by: Sam Weido Date: March 21, 2012 TxDOT COMMENTS 1. No Comment (off state system, no anticipated impact) Reviewed by: Chad Bohne Date: March 23, 2012 (*- /� l � a G M P.Gl: STATION April 30, 2012 1101 Texas Avenue, P.O. Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM TO: Jason Kinnard, Jim Singleton Architects; via email: Jason(cDisarchitects.com FROM: Teresa Rogers, Staff Planner Jason Schubert, AICP, Principal Planner SUBJECT: B/CS Regional Association of Realtors (SP) Staff reviewed the above -mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. The next submittal will be the third and final review by staff for this round of reviews. If all items have not been addressed on the next submittal, another $932 processing fee will need to be submitted for the subsequent set of three (3) reviews. Please address the comments and submit the following information by any Monday at 10:00 a.m. for further staff review: City of College Station Transmittal Letter Seven (7) complete sets of site civil construction documents for the proposed development with the revised site and landscaping plans attached (one set will be returned to you, please submit additional copies if you want more than one approved set) Four (4) revised site plans One (1) landscaping plan One (1) 11x17 grading and erosion control plan Please note that this application will expire in 90 days from the date of this memo, if the applicant has not provided written response comments and revised documents to the Administrator that seek to address the staff review comments contained herein. If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please contact Teresa Rogers at 979.764.3570. Attachments: Staff review comments cc: B/CS Regional Association of Realtors; via email: executiveofficer(cDbcsrealtor.com Fred Paine, Kling Engineering & Surveying; via email: fred(cDklingeng.com Case file no. 12-00500056 STAFF REVIEW COMMENTS NO. 2 Project: B/CS Regional Association of Realtors (SP) PLANNING 1. The minimum parking setback distance from the R.O.W. to the curb of the parking lot is ten feet. Revise the Site Plan to show this requirement has been met. 2. Please note that we are still waiting for a response to NRA comments pertaining to this project. 3. Please note that any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that the City has not been made aware of will constitute a completely new review. Reviewed by: Teresa Rogers Date: April 25, 2012 ENGINEERING COMMENTS NO. 2 1. Since minimum cover is not being provided over storm sewer pipe, Class IV RCP will be required. Please revise C3.1 and cost estimate to reflect this change. Reviewed by: Erika Bridges Date: April 27, 2012 GENERAL ELECTRICAL COMMENTS 1. Developer installs conduit per CSU specs and design. 2. CSU will provide drawings for electrical installation. 3. Developer will intercept existing conduit at designated transformers or other existing devices and extend as required. 4. If conduit does not exist at designated transformer or other existing devices, developer will furnish and install conduit as shown on CSU electrical layout. 5. Developer provides digital AutoCAD 2000 or later version of plat and / or site plan. Email to: sweido@csbc.gov. 6. Developer provides load data to CSU as soon as it is available to avoid construction delays. Delivery time for transformers not in stock is approximately 24 weeks. 7. Final site plan must show all proposed electrical facilities necessary to provide electrical service, i.e. transformer(s), pull box(es), switchgear(s), meter location and conduit routing as designed by CSU. 8. To discuss any of the above electrical comments please contact Sam Weido at 979.764.6314. Reviewed by: Sam Weido Date: 3-21-12 ENGINEERING COMMENTS NO. 2 1. Since minimum cover is not being provided over storm sewer pipe, Class IV RCP will be required. Please revise C3.1 and cost estimate to reflect this change. Reviewed by: Erika Bridges Date: 4/27/12 TxDOT Comments 1. No Comment (off state system, no anticipated impact) Reviewed by: Chad Bohne Date: March 23, 2012 1101 Texas Avenue, P.O. Box 9960 1/ College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 i 11 C, M P.Gl: STATION MEMORANDUM April 25, 2012 TO: Jason Kinnard, Jim Singleton Architects, via email: Jason@jsarchitects.com FROM: Teresa Rogers, Staff Planner Jason Schubert, AICP, Principal Planner SUBJECT: B/CS Regional Association of Realtors (SP) Staff reviewed the above -mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. The next submittal will be the third and final review by staff for this round of reviews. If all items have not been addressed on the next submittal, another $932 processing fee will need to be submitted for the subsequent set of three (3) reviews. Please address the comments and submit the following information by any Monday at 10:00 a.m. for further staff review: City of College Station Transmittal Letter Seven (7) complete sets of site civil construction documents for the proposed development with the revised site and landscaping plans attached (one set will be returned to you, please submit additional copies if you want more than one approved set) Four (4) revised site plans One (1) landscaping plan One (1) 11x17 grading and erosion control plan Please note that this application will expire in 90 days from the date of this memo, if the applicant has not provided written response comments and revised documents to the Administrator that seek to address the staff review comments contained herein. If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please contact Teresa Rogers at 979.764.3570. Attachments: Staff review comments cc: B/CS Regional Association of Realtors, via email: executiveofficer(cDbcsrealtor.com Fred Paine, Kling Engineering & Surveying, via email: fred(cD_klingeng.com Case file no. 12-00500056 STAFF REVIEW COMMENTS NO. 2 Project: B/CS Regional Association of Realtors (SP) PLANNING 1. The minimum parking setback distance from the R.O.W. to the curb of the parking lot is ten feet. Revise the Site Plan to show this requirement has been met. 2. Please note that any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that the City has not been made aware of will constitute a completely new review. Reviewed by: Teresa Rogers Date: SANITATION 1. Sanitation is ok with this project. Reviewed by: Wally Urrutia Date: May 15, 2012