August 11, 2011
l'1.A TI ROBINSON. PLANNER
CITY OF COLLEGE STATION
Williamson Group Architects
SIDEWALK COMPLETION AT POST OAK VILLAGE
COMPLETION OF C1 REZONING REQUIREMENTS
Page 1 of 1
Matt: Please find attached a completed inspection form from the City Inspector on the Post Oak
Village Sidewalk. If I understand the re-zoning correctly this 1s the last requirement in order to
implement t he CI zon ing.
Please take whatever steps are necessary to activate the C I zoning and give us some document
that supports the City's dec1s1on to activate the CI zoning .
If we need further documents, please advise
Thanks for your help.
C. Leon Wil/1amson