HomeMy WebLinkAboutCost EstimatePublic Infrastructure Required for Total
Lot 4R -University Park
Preliminary Engineering Estimate of Costs at 100% Design -"':> MD 6
P d W t Ufrt S repose a er I ICY erv1ce
Item No. Item Quanitv
1 6" PVC Water Line (DR14 Class 200, AWWA C909) 1480
2 6" MJ TEE 6
3 6" 45° MJ Bend 18
4 6" 90° MJ Bend 1
5 6" Gate valve w/ Box 7
7 Fire Hydrant Assemblies 4
8 Trench Safety 1424
9 3" PVC Water Line (SDR21 ASTM 2241) 255
10 Fire Hydrant removal and discard 2
11 Structural backfill Under Pavement 855
12 Domestic Water Meter 73
13 lrriqation Water Meter w/ backflow preventers 4
14 AC Waterline: removal and grout fill 300
15 Remove existinq AC waterline and replace with 6" PVC 120
16 Cap existinq AC waterline (6") 1
Total Cost Estimate:
Unit Unit Price Total
LF $21 .00 $31,080.00
EA $259.00 $1 ,554.00
EA $203.00 $3,654.00
EA $285.00 $285.00
EA $600.00 $4,200.00
EA $2,500.00 $10,000.00
LF $1 .00 $1,424.00
LF $15.00 $3,825.00
EA $1 ,200.00 $2,400.00
LF $2.50 $2,137.50
EA $800.00 $58,400.00
EA $1,000.00 $4,000.00
LF $6.00 $1 ,800.00
LF $27.00 $3,240.00
EA $200.00 $200.00
$128,199.50