Engineer's Cost Estimate
SLEEP INN & SUITES
WATER IMPROVEMENTS
COLLEGE STATION, BRAZOS COUNTY, TEXAS
UNIT
DESCRIPTION QUANTITY UNIT COST
WATER IMPROVEMENTS
Mobilization, Staking, All Required Testing by 1 LS $1 ,500.00 Contractor & Trench Safety (Water Line)
8" PVC Water Line (C909, CL 200) -Non Structural 40 LF $17.00 Backfill
Standard Fire Hydrant Assembly 2 EA $3,000.00
18" x 8" (MJ) Tapping Valve & Sleeve 2 EA $1 ,800.00
8" (MJ) Gate Valve & Box 2 EA $900.00
6" (MJ) Gate Valve & Box 3 EA $750.00
8" x 6" (MJ) Tee 2 EA $400.00
8" (MJ) Plug 1 EA $300.00
Water Services & Taps 1 LS $1 ,200.00
ESTIMATED CONSTRUCTION COST=
10% CONTINGENCY=
TOTAL
COST
$1 ,500.00
$680.00
$6,000.00
$3,600.00
$1 ,800.00
$2,250.00
$800.00
$300.00
$1 ,200.00
$18,130.00
$1,813.00
GRAND TOTAL= $19,943.00
public infrastructure cost projections.
CD1-231 -0351-E02
RME Consulting Engineers
Texas Registration Firm No. F-004695
P.O. Box 9253
College Station, TX 77842
Off/Fax: (979) 690-0329
Email : civil@rmengineer.com
June 22, 2009
Josh Norton, P.E.
Assistant City Engineer
City of College Station
Planning & Development Services
1101 Texas A venue South
College, Station, 77840
P.O. Box 9253, College Station, TX 77842
Off/Fax: (979) 690-0329
email: civil@rmengineer.com
RE: Sleep Inn & Suites -1195 Earl Rudder Freeway South, College Station, TX
Lot 2B, Block One -High Ridge Subdivision -Brazos County
Utility Availability Analysis -Revision No. 1
RME No. 231-0351
Josh:
The purpose of this letter is to acknowledge that the construction plans for the public
infrastructure improvements, for the above referenced project, to the best of my knowledge, do
not deviate from the latest B/CS Design Guideline Manual.
I also acknowledge, to the best of my knowledge that the details provided in the construction
plans are in accordance with the B/CS Standard Details.
Please do not hesitate to call if you have any questions.
Sincerely,
CDl-231-0351-Ll 0 Page I of 1