HomeMy WebLinkAboutEngineer's Cost EstimateNovember 16, 2011
Mr. Josh Norton, P.E.
City of College Station Engineering Department
1101 Texas Avenue
College Station, TX 77842
Re: Engineer's Cost Estimate
Brazos Fellowship Addition
226 Southwest Parkway East
College Station, Texas
Gessner Engineering Job No.: 11-0361
Dear Mr. Norton:
Based on current estimations for direct material and direct labor costs, the prime
cost of the public infrastructure for the above referenced project is estimated to
be $2,822.00. Values used to determine this estimate are included in the
attached table. This estimate does not include indirect costs due to overhead or
indirect manufacturing expenses.
Please contact us if you have any questions or if we can be of further assistance.
Sincerely,
GESSNE.
N EERING, F-7451
—,�gOfTF 11
l
Jere
Peers, P.E., C.F.M.
i II
Or �4... j
�..................
Gessner
iP JEREMY N. PETERS /
...........................;....,
Engineering
^ 2�
f. 100217 i
(s
Kyle M. Zapalac, M.E., E.I.T.
!CENSEaG���r�
1 SIONAI.E -
2501 A hlurd Drive
```��"�
Suite 102
Attached:
Estimated Cost Table
College Station,'[exas 77840
CO. Box 10763,77842-0763
979.680.8840
FAX 979.680.8841
2204 S. Chappell Hill St.
Drenham,"Iexas 77833
979.836.6855
FAX 979.836,6847
Probable Estimate of Public Sitework Construction Costs
Brazos Fellowship Addition
Gessner Engineering, LLC
GE Job # 11-0361
SANI7ARl(SEWl;F2= -`;"
,
Item
Quantity
Units
Unit Cost
Total
6" Commercial Service
1
EA
$
1,000.00
$
1,000.00
6" PVC SS
7
LF
$
45.00
$
315.00
6" Cleanout
1
EA
$
1,500.00
$
1,500.00
Trench Safety
7
EA
$
1.00
$
7.00
Total
$
2,822.00