HomeMy WebLinkAboutOversize Participation EstimateSONOMA SUBDIVISION OFFSITE 8" WATER LINE ESTIMATE FOR OVERSIZE PARTICIPATION July 2, 2007 Item No. 1.00 MBESI NO. 10530005 Description WATER LINE IMPROVEMENTS 1.01 Mobilization and Stormwater Pollution Prevention Plan (includes installation and maintenance of erosion control structw"es throughout the entire project) 1.02 8" A WW A C909, CL 200 PVC Water Line (includes installation, testing, and clean-up) 1.03 16" Steel Encasement w/Wet Bore Construction (3/8" thick) (includes painting, casing spacers, and end seals) 1.04 8" Gate Valve 1.05 8"x45 deg Bend 1.06 8"x22.5 deg Bend 1.07 8"x8" Tee 1.08 2" Blow-off Assembly 1.09 Connect to Existing Water Line 2.00 MISCELLANEOUS 2.01 Silt Fence 2.02 Hydro Seeding with Fiber Mulch Estimated Estimated Quantity U . C mt ost 1.00 LS $5,000.00 1,229 LF $15.50 60 LF $250.00 EA $950.00 2 EA $300.00 1 EA $300.00 EA $400.00 EA $850.00 EA $1 ,000.00 Subtotal Item 1.00: Estimated Total Cost $5,000.00 $19,049.50 $15,000.00 $950.00 $600.00 $300.00 $400.00 $850.00 $1,000.00 $43,149.50 1,100 LF $2.50 $2,750.00 2,444 SY $0.75 ____ $1 .... ,8_3_3._00_ Subtotal Item 2.00: ____ S;....4..:..,5_8_3_.o_o CONSTRUCTION COST: $47,732.50 The above construction estimate is based on the engineer's opinion of probable construction costs. This estimate constitutes our best judgment at this time. Please note that the engineer does not have any control over contractor or supplier workloads and the degree to which inflation may affect project costs between now and the bid date. During design and construction, additional featw"es may become apparent as the work progresses, which will result in an increase or decrease in cost. Prepared by: ~~::::::::::~-L:lll~==:::::::.___.!7~~_/_ Jeffi M n,P. rowne Engineering/Surveying, Inc. ........ , ....... ,,,,,,, ---""..'\ ~ OF r€ \\\ .? t:.:J"'° ~ .... * ............ ::-1'5' ,,, ... .... •• •• .M ,, ,,, "'.· ·. ~ ,, ~...... \*~ i' ....................................... l ~ JEFFERY L. ROBERTSON ~ ~·····:························ .. ·:·····~ ~ -0 \ 94745 /$ t .. ,~... .:y:;~ 111 ~··.~(CENS~~_..-0· ~_E '•''&s ··········~~ ..:-,\,,,~ONAL ~---'''''''"' SONOMA SUBDIVISION OFFSITE 24" WATER LINE ESTIMATE FOR OVERSIZE PARTICIPATION July 24, 2007 MBESI NO. 10530005 Item No. Description Estimated Quantity Estimated Estimated Total 1.00 WATER LINE IMPROVEMENTS 1.01 Mobilization and Stormwater Pollution Prevention Plan (includes installation and maintenance of erosion control structures throuliliout the entire project) 1.02 24" ANSUAWWA CI51/A21.5, CL 200 DIP Water Line (includes installation. ~ and clean-up) 1.03 36" Steel Encasement w/Dry Bore Construction (3/8" thick) (includes paintinJZ. cas~ spacers, and end seals) 1.04 36" Steel Encasement (3/8" thick), Str. Backfill 1.05 24" Butterfly Valve 1.06 24 "x22.5 deg Bend 1. 07 24 "xl 1.25 deg Bend 1.08 24"x8" Tee 1.09 6" Blow-off Assembly 1.10 Connect to Existing Water Line 2.00 MISCELLANEOUS 2.01 Silt Fence 2.02 Hydro Seeding with Fiber Mulch Unit Cost Cost 1.00 LS $5,000.00 $5,000.00 1,229 LF $95.00 $116,755.00 70 LF $575.00 $40,250.00 75 LF $250.00 $18,750.00 I EA $7,500.00 $7,500.00 4 EA $1 ,000.00 $4,000.00 1 EA $1 ,000.00 $1,000.00 EA $1,250.00 $1,250.00 EA $1,250.00 $1,250.00 I EA $1,000.00 $11000.00 Subtotal Item 1.00: $196,755.00 1,100 LF $2.50 $2,750.00 2,444 SY $0.75 $11833.00 Subtotal Item 2.00: $4,583.00 CONSTRUCTION COST: $201,338.00 The above construction estimate is based on the engineer's opinion of probable construction costs. This ~te constitutes our best judgment at this time. Please note that the engineer does not have any control over contractor or supplier workloads and the degree to which inflation may affect project costs between now and the bid date. During design and construction, additional features may become apparent as the work progresses, which will result in an increase or decrease in cost. ~ey~ Jefti Ro P . M ~~Smveying, Inc. ~''''"'''' ---"":_"'\~OF 7"1:-~\\ .,Z' " "' .......... '-r~ ,,, ; io' . ...-*·· ... -~IS' I I */ ···.~'' * ! · .. * ~ I-···········--·················· .. ·····~ ~ JEFFERY L. ROBERTSON ~ J.·································1·····i'. l 1\ 94745 .//fi J '10·. (. .·y;~ ··.~~·-f.C:.~~.~~?.··&~; '''' SJONAL ~f--..:-'''''"''"'"' SONOMA SUBDIVISION OFFSITE 24" WATER LINE ESTIMATE FOR OVERSIZE PARTICIPATION July 24, 2007 MBESI NO. 10530005 Item No. Description Estimated Quantity Estimated Estimated Total 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 WATER LINE IMPROVEMENTS Mobilization and Stormwater Pollution Prevention Plan (includes installation and maintenance of erosion control structures throughout the entire project) 24" ANSJ/AWWA Cl51/A21.5, CL 200 DIP Water Line (includes installation, t~, and clean-up) 36" Steel Encasement w/Dry Bore Construction (3/8" thick) (includes pain~, cas~ spacers, and end seals) 36" Steel Encasement (3/8" thick), Str. Backfill 24" Butterfly Valve 24"x22.5 deg Bend 24"xl 1.25 deg Bend 1.08 24"x8" Tee 1.09 6" Blow-off Assembly 1.10 Connect to Existing Water Line 2.00 MISCELLANEOUS 2.01 SiltFence 2.02 Hydro Seeding with Fiber Mulch Unit Cost Cost 1.00 LS $5,000.00 $5,000.00 1,229 LF $95.00 $116,755.00 70 LF $575.00 $40,250.00 75 LF $250.00 $18,750.00 EA $7,500.00 $7,500.00 4 EA $1 ,000.00 $4,000.00 EA $1 ,000.00 $1,000.00 EA $1 ,250.00 $1 ,250.00 EA $1 ,250.00 $1 ,250.00 EA $1 ,000.00 $1 000.00 Subtotal Item 1.00: $196,755.00 1,100 LF $2.50 $2,750.00 2,444 SY $0.75 $1 ,833.00 Subtotal Item 2.00: $4,583.00 CONSTRUCTION COST: $201,338.00 The above construction estimate is based on the engineer's opinion of probable construction costs. This estimate constitutes our best judgment at this time. Please note that the engineer does not have any control over contractor or supplier workloads and the degree to which inflation may affect project costs between now and the bid date. During design and construction, additional features may become apparent as the work progresses, which will result in an increase or decrease in cost. ~by~[Vb Jeffi Ro n, P . M~ ~e Engineering/Surveying, Inc. '""''''"'''' ---"":_~e. OF r€ ''' .:r '\Ii'-••·•····•• ~ ..... 1,, ;~ .. ···*·· ... -'<S' I ., * ... · ..• ,, ~..... .....~ ~·········· ...................... : ...... ~ ~ JEFFERY L. ROBERTSON ~ l '''·•:····· .. ·········· .. ··•··· .. , ..... .,. ~ ~\ 94745 /It J .,,o·. < ,.·!ii~ la1"Ji·· .. (.CENS'i:-_?.··&~ ~ ''\~8'6'NAL. ~~--5 ,,,,,,, ........... ""