HomeMy WebLinkAboutCost EstimateESTIMATE OF PROBABLE COST
City of College Station - Central Park Improvements
Public Waterline Improvements
JC PROJECT NO. C0088-001
Estimated
ITEM NO.
DESCRIPTION
UNIT PRICE
AMOUNT
Quantity
BASE BID - WATERLINE
General Overhead for all Work Including
1
1 LS
Mobilization, Bonds, Insurance, and Related
$4,000.00
$4,000.00
Items
6" Water Line, AWWA C900 Class 200 PVC with
2
304 IF
Detector Tape and Tracer Wire in Trench (48"
$23.00
$6,992.00
Min Cover)
3
100 LF
6" Water Line, AWWA C900 Class 200 PVC by
$65. 00
$6,500.00
Bore with Detector Tape and Tracer Wire
4
2 EA
6"X6" DI Tee
*350.00
$700.00
5
1 EA
6" Isolation Gate Valve wth AMINO use, LL526
$1,250.00
$1,250.00
Lockable Lid or Equivalent Approved by City
6
1 EA
Tie into Existing Waterline
$1,500.00
$1,500.00
7
2 EA
Fire Hydrant Assembly
$3,200.00
$6,400.00
8
2,200 SF
Block Sod Disturbed Areas in grass with
$1.50
$3,300.00
common Bermuda
9
1 LS
Infield Gravel/Clay Mixture
$500.00
$500.00
1
p_4E OF TE,Ygs �1++ TOTAL: $31,142.00
*: . /
51EVE E. DU. FAN 00
..................
83252 . _ i 1
1. This estimate represents my best judgment as a design professional
familiar with the construction industry. Jones & Carter, Inc, has
no control over the cost of labor, materials, or equipment; over
the Contractor's methods of determining bid prices; or over
competitive bidding or market conditions. Accordingly, we cannot
and do not guarantee that bide will not vary from this cost
estimate.