Mr. Alan Gibbs, P.E.
Senior Assistant City Engineer, Public Works
City of College Station
3 00 Krenek Tap Road
College Station, Texas 77842
Re: Factory Apartments
Offsite Drainage Evaluation
Klotz Project No. 0731.001.000
Dear Mr. Gibbs:
k I o t z 4~~ a s s o c 1 a t e s
Klotz Associates has reviewed the options for offsite detention for the Factory multi-family
development in College Station, Texas. The project site is located on the eastern corner of
College Main Street and Cherry Street in College Station, Texas. The proposed development
consists of a multi-story building and a parking garage. The project was designed by Binkley &
Barfield and plans were dated October 2006.
The approved plans for the development included an underground detention system. As an
option, Klotz Associates analyzed the option of providing offsite detention. The proposed
detention location is within the existing drainage channel located approximately 900 feet
downstream to the northeast of the site along Inlow Blvd. Our engineering evaluation included
the following services:
• Preliminary Analysis -This phase consists of a review of the detention requirement
calculations that were prepared by Binkley and Barfield. Based on that volume that was
calculated for the site; determine proposed geometry for the expanded downstream
channel to provide in-line detention.
• Detailed Analysis -In order to route the storm flow to the channel, an analysis of the
storm system on the adjacent roadway was necessary. This analysis would show the
impact of the additional flow on the system. Klotz Associates designed improvements to
Cherry Street in 2002. Winstorm was used for that analysis and included analysis of the
10 year and 100 year storm event.
The analysis of the storm sewer drainage system shows that the proposed offsite detention to be
feasible. The drainage system of Cherry Street has sufficient capacity to convey the 100-year
Mr. Alan Gibbs, P.E.
July 3, 2007
Page 2 of 4
k I o t z -~~ a s s o c i a t e s
storm event due to the requirement and use of minimum pipe sizes and limited local drainage
areas. It appears that existing channel along Inlow Blvd. can be expanded to provide detention
volume equal to that required for the site as shown in Binkley & Barfield's calculations. The
calculations are outlined in more detail below. During the initial review of the project, the plans
for Cherry Street dated August 2001 showed that the majority of the site drained to College
Main. The site plan prepared by Binkley & Barfield, routes the majority of the flow through an
underground detention facility and discharges into the Cherry Street drainage system.
Original Design
The following information was provided by Binkley & Barfield by utilizing the Rational
Method. The formula used is Q = CiA in which Q equals the peak rate of runoff in cubic feet per
second (cfs), C equals the dimensionless coefficient ofrunoff, i equals the average intensity of
rainfall in inches per hour for a period of time equal to the time of concentration (TC) for the
drainage area, A equals the area in acres contributing runoff, and TC equals the time of
concentration in minutes.
• Existing storm drainage peak flow: Q(lOyr) = 7.70 cfs, C = 0.65 A = 1.42 AC, TC = 10
min, i = 8.35 in/hr
• Proposed storm drainage peak flow: Q(lOOyr) = 15.66 cfs, C = 0.75, A = 1.44 AC, TC =
10 min, i = 12.5 in/hr
• Detained Detention Volume = 7,164 cubic feet (CF)
• The proposed drainage system has a drainage area of 1.15 AC which will discharge 5.55
cfs through an underground detention system that discharges through an 18-in HDPE into
an existing inlet on the west side of Tauber Street & Cherry Street. The remaining
drainage is of 0.285 AC which will discharge 2.15 cfs is directly discharged into a
drainage system along College Main.
Based on the current storm water design guidelines and the calculation that 0.4 acres of the
proposed development will discharge directly into the drainage system along College Main, a
further analysis of the drainage system along Cherry Street was necessary. Utilizing Winstorm,
the existing drainage system down Cherry Street to the ditch along Inlow Blvd was re-evaluated.
Once the existing system was verified, an analysis of the proposed additional runoff from the
Factory site was evaluated for the designed 10 yr storm event and evaluated the 100 yr storm
event. See Exhibit 1. The 10 year storm event was the basis of the design of the Cherry Street
Improvements.
Mr. Alan Gibbs, P.E.
July 3, 2007
Page 2 of 4
k I o t z -~~ a s s o c i a t e s
storm event due to the requirement and use of minimum pipe sizes and limited local drainage
areas. It appears that existing channel along Inlow Blvd. can be expanded to provide detention
volume equal to that required for the site as shown in Binkley & Barfield's calculations. The
calculations are outlined in more detail below. During the initial review of the project, the plans
for Cherry Street dated August 2001 showed that the majority of the site drained to College
Main. The site plan prepared by Binkley & Barfield, routes the majority of the flow through an
underground detention facility and discharges into the Cherry Street drainage system.
Original Design
The following information was provided by Binkley & Barfield by utilizing the Rational
Method. The formula used is Q = CiA in which Q equals the peak rate of runoff in cubic feet per
second (cfs), C equals the dimensionless coefficient ofrunoff, i equals the average intensity of
rainfall in inches per hour for a period of time equal to the time of concentration (TC) for the
drainage area, A equals the area in acres contributing runoff, and TC equals the time of
concentration in minutes.
• Existing storm drainage peak flow: Q(lOyr) = 7.70 cfs, C = 0.65 A = 1.42 AC, TC = 10
min, i = 8.35 in/hr
• Proposed storm drainage peak flow: Q(lOOyr) = 15.66 cfs, C = 0.75, A = 1.44 AC, TC =
10 min, i = 12.5 in/hr
• Detained Detention Volume = 7,164 cubic feet (CF)
• The proposed drainage system has a drainage area of 1.15 AC which will discharge 5.55
cfs through an underground detention system that discharges through an 18-in HDPE into
an existing inlet on the west side of Tauber Street & Cherry Street. The remaining
drainage is of 0.285 AC which will discharge 2.15 cfs is directly discharged into a
drainage system along College Main.
Based on the current storm water design guidelines and the calculation that 0.4 acres of the
proposed development will discharge directly into the drainage system along College Main, a
further analysis of the drainage system along Cherry Street was necessary. Utilizing Winstorm,
the existing drainage system down Cherry Street to the ditch along Inlow Blvd was re-evaluated.
Once the existing system was verified, an analysis of the proposed additional runoff from the
Factory site was evaluated for the designed 10 yr storm event and evaluated the 100 yr storm
event. See Exhibit 1. The 10 year storm event was the basis of the design of the Cherry Street
Improvements.
Mr. Alan Gibbs, P.E.
July 3, 2007
Page 3 of 4
The following is a summary of the results of analysis:
The Existing conditions for the site are as follows:
k I o t z 4~· a s s o c i a t e s
• Q (lOyr) = 4.49 cfs, TC= 10 min., C=0.50, i = 8.63 in/hr, A=l.04 AC.
• Q (lOOyr) = 6.05 cfs, TC= 10 min., C=0.50, i = 11.64 in/hr, A=l.04 AC.
The Proposed conditions for the site are as follows:
• Q (lOyr) = 8.08 cfs, TC= 10 min., C=0.90, i = 8.63 in/hr, A=l.04 AC.
• Q (lOOyr) = 10.89 cfs, TC= 10 min., C=0.90, i = 11.64 in/hr, A=l.04 AC.
The 1 OOyr hydraulic grade line CHOL) was below the pavement elevations along Cherry and
Tauber Street. See attached WINSTORM calculations. The HGL was 338.47 ft and the top of
inlet is 34 7. 7 5. Therefore the 100 year flows off of the Factory Apartment site are contained and
conveyed within the existing storm sewer system all the way to the open ditch along Inlow Blvd
and detention could be provided in that open ditch.
Detention in Inlow Ditch
The ditch geometry along Inlow Blvd was evaluated. See Exhibit 3. Based on the location of
the existing power poles, five areas could be utilized. Each area would decrease the side slopes
from 2: 1 or less to approximately 4: 1 and yield approximately 2,500 CF of mitigation volume for
a total increased volume of 12,5 00 CF. See Exhibit 4. Each area has a length of about 200 feet.
The location of existing sanitary manholes needs to be verified and could affect the available
volumes. Also, it appears that the City limits of College Station and Bryan are located along the
ditch. This added detention will be useful to the entire upper drainage for all storm events. We
understand that Cherry Street LP plans to excavate all the length of the ditch on the south side
only. The side slopes would be hydromulched and stabilized similar to what is existing there
today. This excavation would produce approximately 12,500 CF. Cherry Street LP would
document the amount of excavation by measuring the amount of dirt hauled away in each dump
truck by tape measurement. A minimum of 7 ,500 CF will be constructed. This excavation
would be in excess of the volume needed for the Factory apartments. Radakor, LLC,
Development GP of Cherry Street LP may use that excess detention volume for future projects in
the area with the review and approval by the city.