HomeMy WebLinkAboutCost EstimateEWING IRRIGATION PRODUCTS SITE PLAN
MBESI PROJ #: 1000-0136
Engineer's Estimate of Construction Costs (Public Infrastructure)
April 8, 2009
Item # I Description Unit Quantity Unit Price Total
Sidewalk Construction
Colored Sidewalk Ram s EACH 2 615.00 1,230
Pavin Subtotal $1 30
Wt St C t t' a er •YS em ODS rue IOD
2 8" PVC, C909 Cl 200, Water Line, Str. Backfill L.F. 80 25.00 2,000
3 16" Steel Casing with Dry Bore installation L.F. 65 280 .00 18,200
4 Fire Hydrant Assembly EACH 1 2,800.00 2,800
5 12"x8" Tee EACH 1 750.00 750
6 12" Gate Valve EACH 1 1,200.00 1,200
7 8" Gate Valve EACH 1 800.00 800
Water System Subtotal $25,750
Total Construction Cost $26,980
The above construction estimate is based on the engineer's preliminary opinion of probable construction costs. This
estimate constitutes our best judgment at this time. Please note that the engineer does not have any control over contractor
or supplier workloads and the degree to which inflation may affect project costs between now and the bid date. During
construction, additional features may become apparent as the work progresses, which will result in an increase in cost.