RE: Co.st Estimate
NAVARRO WEST CENTER, COLL.EGE SI ATlON, TEXAS
Dear Mike.,
The estimated co.sts for the proposed utility improvements,, wh'ich include a new fire
hy.drant, are as follows.
Quart'tity
40 LF
1
1
Desctiption
6" PVC Water Pipe Cl~$S 200 or 6" D.I. Pip:e
Fire Hydrant
6" G~te Vi;ilve & aox
Unit Cost Total Cost
$40 $1,600
$2,500 $2,500
Sl,900 $1,900
Grand Total $6,000
All costs include materiar and labor. All materials and installation per city standards.
•'