Public Utility - Water Line Cost Estimate
The Stack
Project Information
Project Name: The Stack
Project Location: College Station, Texas
KHA Job #: 66078000
Construction Cost Projection
Item Description
Notes:
Quantity
11Unit
I Unit Price
Item Cost
6" C909 PVC WATERLINE wl STRUCTURAL BACKFILL
350
If
$ 32.00
$
11,200
8" C909 PVC WATERLINE wl STRUCTURAL SACKFILL
279
If
$ 41.00
$
11,439
FITTINGS
1.4
ton
$ 3,500.00
$
4,900
6" GATE VALVE
1
as
$ 1.000.00
$
1,000
8" GATE VALVE
3
ea
$ 1,200.00
$
3,600
12" GATE VALVE
1
ea
$ 2,000.00
$
2,000
CONNECT TO EXISTING WATERLINE
2
ea
$ 1,500.00
$
3,000
10" SANITARY SEWER LINE
217
If
$ 40.00
$
8,680
4'SANITARY SEWER MANHOLE
4
ea
$ 3.500.00
1 $
14,000
Project Cost Summary
Pre -Allowance Subtotal:
$
59,819
Item Description Notes:
Item Cost
Project Construction Subtotal:
$
59,819
Total Project Cost:
$
59,819
n e cngmeor,us no on. over at. cast or iaoor, matenais, equipmenp or over Ina GonVacts, methods
of determtning prices or over competitive bidding or mallet conditions. Opinions of probable cos%provided herein are
based on the information known to Engineer at this time and represent only the Engineer's judgment as a design
prpfess ithid familiar with the consVugiop industry. The Engineer cannot and does not guarantee that proposals,
bids, or aqua) construction costs will not vary from Its opinions of probable costs.