DATE: July 14, 2014
TO: Joe Johnson, via; joejohnson1889Ahotmail.com,
FROM: Jason Schubert, ACIP, Principal Planner
SUBJECT: WILLIAMS LAKE (REZ)
I reviewed the above-mentioned Rezoning application and determined it to be incomplete. The
following is the preliminary list of items needed to complete the submittal. Please submit the
following information so this application can be forwarded for review:
Please submit proof of authority documents for the Johnson's to sign the
application on behalf of Joe & Janet Johnson Land & Investment, LP.
Please be aware that if this application is not completed before Tuesday, September 2, 2014, it
will expire and a new application and fees will be necessary to continue the rezoning process.
If you have any questions or need additional information, please call me at 979.764.3570.
PC: Joe Schultz, Schultz Engineering, LLC, via; joeschultz84[a@verizon.net
P&DS Project No. 14-00900172
Planning 6'Development Services
P.O.BOX 9960 • 1101 TEXAS AVENUE•COLLEGE STATION •TEXAS •77841
TEL 979.764.3570 7 FAX. 979.764.3496
0
CITY OF COLLEGE STATION "' '
Home of Texas Ae7M University.
MEMORANDUM
DATE: July 16, 2014
TO: Joe Johnson, via; loeiohnson1889@hotmail.com
FROM: Jerry Cuaron, Staff Planner
SUBJECT: WILLIAMS LAKE (REZ)
Thank you for the submittal of the required documents for your Rezoning application. Kevin
Ferrer, Graduate Civil Engineer, and I have been assigned to review this project. It is anticipated
that the review will be completed and any staff comments returned to you on or before
Wednesday, July 30, 2014. If you have questions in the meantime, please feel free to contact
us.
PC: Joe Schultz, Schultz Engineering, LLC, via; joeschultz84@_verizon.net
P&DS Project No. 14-00900172
Planning es' Development Services
P.O.BOX 9960 • 1101 TEXAS AVENUE •COLLEGE STATION .TEXAS •77842
TEL.9,79.764.3570•FAX. 979.764.3496
Grir
CITY OF COLLEGE EGI STATION
Home of Texas AaFM University
( �. >
MEMORANDUM
DATE: July 30, 2014
TO: Joe Johnson, via; joejohnson1889hotmail.com
FROM: Jason Schubert, AICP, Principal Planner
SUBJECT: WILLIAMS LAKE (REZ) — Rezoning
Staff reviewed the above-mentioned final plat as requested. The following page is a list of staff
review comments detailing items that need to be addressed. Please address the comments and
submit the following information by Wednesday, August 6, 2014 for further staff review and for
this item to be scheduled for the Thursday, August 21, 2014 Planning & Zoning Commission
meeting at 7:00pm at College Station City Hall:
One (1) 24"x36" copy of the revised Rezoning Map; and
Thirteen (13) 11"x17" copies of the revised Rezoning Map.
Please note that this application will expire in 90 days from the date of this memo, if the
applicant has not provided written response comments and revised documents to the
Administrator that seek to address the staff review comments contained herein. If all required
items are not received, your project will be not be scheduled on the P&Z agenda. Your project
may be placed on a future agenda once all comments have been addressed and the
appropriate re-advertising fees paid.
Once your item has been scheduled for the P&Z meeting, the agenda and staff report can be
accessed at the following web site on Monday the week of the P&Z meeting.
http://www.cstx.gov/pz
If you have any questions or need additional information, please call me at 979.764.3570.
Attachments: Staff Review Comments
pc: Joe Schultz, Schultz Engineering, LLC, via; joeschultz84@verizon.net
Case file #14-00900172
Planning er Development Services
P.O.I30X 9960 • l 101.1},XAS AVENUE •COLLEGE ST:AEION •TEXAS •77842
TEL.979.764.3470•FAX. 979.764.3496
STAFF REVIEW COMMENTS NO. 1
Project: WILLIAMS LAKE (REZ) — (14-00900172)
PLANNING
1. Provide a north arrow for the Vicinity Map.
2. Provide the right-of-way width for Rock Prairie Road.
Reviewed by: Jason Schubert Date: July 30, 2014
ENGINEERING COMMENTS NO. 1
1. Please provide a written Verification that Wellborn SUD has sufficient water capacity and
is willing to serve the lots.
Reviewed by: Kevin Ferrer Date: July 21, 2014