January 13, 2015
Jerry Cuaron
Staff Planner
City of College Station
1101 Texas Avenue
College Station,TX 77840
Re: The Barracks II Subdivision—Ph 107—14-00900268
Dear Mr. Cuaron:
Attached are one (1) 24" x 36" copy of the revised Final Plat, 2 sets of revised
construction documents, the revised Engineer's Estimate, and the response to staff
comments.
If you have any questions,please do not hesitate to call.
Sincerely,
Schultz Engineering,LLC.
Joe Sc ltz,P.E.
Civil ngineer
P.O. Box 11995 • College Station,Texas 77842
schultzengineeringllc.com
OFFICI �YL,
CASE NO.:FOR USE
4c.ff DATE SUBMIT ED. ' A
CITY OF COLLEGE STATION TIME:
Home of Texas A&M University` STAFF: '^1_
PLANNING & DEVELOPMENT SERVICES
TRANSMITTAL LETTER
Please check one of the options below to clearly define the purpose of your submittal.
New Project Submittal
- Incomplete Project Submittal-documents needed to complete an application. Case No.:
n Existing Project Submittal. Case No.: 14-00900268
Project Name THE BARACKS II SUBDIVISION-Ph 107
Contact Name JOE SCHULTZ, P.E. Phone Number 979.764.3900
We are transmitting the following for Planning & Development Services to review and comment (check all that apply):
Comprehensive Plan Amendment ❑ Non-Residential Architectural Standards
Rezoning Application H Irrigation Plan
H Conditional Use Permit n Variance Request
Preliminary Plan ❑ Development Permit
Final Plat ❑ Development Exaction Appeal
❑ Development Plat ❑ FEMA CLOMA/CLOMR/LOMA/LOMR
H Site Plan [ Grading Plan
❑ Special District Site Plan M Other- Please specify below
Special District Building /Sign Civil Construction Plans
❑ Landscape Plan
INFRASTRUCTURE AND ENGINEERING DOCUMENTS
All infrastructure documents must be submitted as a complete set.
The following are included in the complete set:
Comprehensive Plan Amendment X Waterline Construction Documents
❑ TxDOT Driveway Permit ❑X Sewerline Construction Documents
❑ TxDOT Utility Permit [xj Street Construction Documents
❑ Drainage Letter or Report ❑ Easement Application
— Fire Flow Analysis ❑ Other- Please specify
Special Instructions:
10/10 Print Form
FOR OFFIC .E et.; Y
CASE NO.: / i /1) _
DATE SUB ITTED: lPIAII,p
TIME: ,
CITY OF COLLEGE STATION
Home of f Texas A6 M University" STAFF:
PLANNING & DEVELOPMENT SERVICES
TRANSMITTAL LETTER
Please check one of the options below to clearly define the purpose of your submittal.
New Project Submittal
I 1 Incomplete Project Submittal - documents needed to complete an application. Case No.:
lx1 Existing Project Submittal. Case No.: 14-00900268
Project Name THE BARACKS ll SUBDIVISION- Ph 107
Contact Name JOE SCHULTZ, P.E. Phone Number 979.764.3900
We are transmitting the following for Planning & Development Services to review and comment (check all that apply):
Comprehensive Plan Amendment LJ Non-Residential Architectural Standards
Rezoning Application I ) Irrigation Plan
Conditional Use Permit I I Variance Request
❑ Preliminary Plan ❑- Development Permit
�f Final Plat ❑- Development Exaction Appeal
n Development Plat ❑ FEMA CLOMA/CLOMR/LOMA/LOMR
I I Site Plan [j Grading Plan
n Special District Site Plan [ Other- Please specify below
Special District Building /Sign Civil Construction Plans
❑ Landscape Plan
INFRASTRUCTURE AND ENGINEERING DOCUMENTS
All infrastructure documents must be submitted as a complete set.
The following are included in the complete set:
n Comprehensive Plan Amendment ❑x Waterline Construction Documents
n TxDOT Driveway Permit IxI Sewerline Construction Documents
n TxDOT Utility Permit ❑X Street Construction Documents
I I Drainage Letter or Report I I Easement Application
n Fire Flow Analysis ❑ Other- Please specify
Special Instructions:
10/1 o Print Form
Schultz Engineering, LLC
Office: 979.764.3900
Fax: 979.764.3910
August 31, 2015
Jason Schubert, AICP
Principal Planner
City of College Station
1101 Texas Avenue
College Station, TX 77840
Re: The Barracks II Subdivision—Ph 107— 14-00900268
Dear Mr. Schubert:
Attached are the following items for the project referenced above:
• Mylar original of the Final Plat
• CAD file of plat on a CD
• An updated tax certificate
• A check for $39,375 for the Parkland Dedication
If you have any questions, please do not hesitate to call.
Sincerely,
Schultz Engineering, LLC.
Joe S ultz, P.E.
Manager/Civil Engineer
P.O. Box 11995 • College Station,Texas 77842
schultzengineeringllc.com
Schultz Engineering, LLC
Office: 979.764.3900
Fax: 979.764.3910
March 10, 2015
Jason Schubert,AICP
Principal Planner
City of College Station
1101 Texas Avenue
College Station, TX 77840
Re: The Barracks II Subdivision—Ph 107—14-00900268
Dear Mr. Schubert:
Attached are thirteen(13) 11"x 17" copies of the revised Final Plat, 1 set of revised
construction documents, the revised Engineer's Estimate, a revised page 2 of the
application and the response to staff comments.
If you have any questions,please do not hesitate to call.
Sincerely,
Schultz Engineering,LLC.
ci\
Joe S� ultz,P.E.
Civil Engineer
P.O. Box 11995 • College Station,Texas 77842
schultzengineeringllc.com
Schultz Engineering, LLC
Office: 979.764.3900
Fax: 979.764.3910
October 15, 2014
Alan Gibbs, P.E.
City Engineer
Development Services
City of College Station
College Station, Texas
RE: Letter Acknowledging City Standards—The Barracks II Subdivision
Phases 107
Dear Mr. Gibbs:
The-purpose of this letter is to acknowledge that the construction plans for the water,
sanitary sewer, streets and drainage for the above-referenced project, to the best of my
knowledge, do not deviate from the B/CS Design Guideline Manual.
I also acknowledge that, to the best of my knowledge, the details provided in the
construction plans are in accordance with the B/CS Standard Details.
Sincerely,
p.,94 _,. Or re_tts,
Jo ph P. Schultz, P.E. */'ff•....**.....*.\ii.*
Civil Engineer "IJOSEPH P SCHUL1Z
65889
I0ts
4t.
to-1.j f
F-12327
SCHULTZ ENGINEERING. LLC.
P.O. Box 11995 • College Station,Texas 77842
schultzengineeringllc.com
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
Barracks II Subdivision Phases 107
Engineer's Estimate of Construction
Item Description Unit Estimated Unit Price Total
Quantity
General Items
1 Mobilization,Overhead and Construction Staking LS 1 $ 20,000.00 $ 20,000.00
2 Topsoil Removal and Replacement,complete in place LS I $ 12,000.00 $ 12,000.00
3 Street Name Signs,complete in place EA 2 $ 350.00 $ 700.00
4 Stop Signs,complete in place EA 2 $ 400.00 $ 800.00
5 Pavement Striping and Markings,complete in place LS 1 $ 2,000.00 $ 5,000.00
6 Erosion&Sediment Control-SWPPP Implementation&Maintenance,Silt Fence,
Construction Exit,Rock Filter Dam,etc.,complete in place LS I $ 5,000.00 $ 5,000.00
7 Hydroseed and Hydromulch,complete in place SY 22,812 $ 0.50 $ 11,406.00
General Items Subtotal $ 54,906.00
Street Construction Items Concrete Pavement
8 Excavation&Grading,complete in place LS 1 $ 30,000.00 $ 30,000.00
9 Mixing&incorporation of lime,6"deep,complete in place SY 3,999 $ 2.30 $ 9,197.70
10 Mixing&incorporation of lime,8"deep,complete in place SY 3,663 $ 2.90 $ 10,622.70
I 1 Hydrated Lime,complete in place(27 Ib/sy for 6"deep&36 lb/sy for 8"deep) Ton 120 $ 180.00 $ 21,600.00
12 6"Reinforced Concrete Pavement w/Curb,complete in place SY 1,803 $ 32.00 $ 57,696.00
13 7"Reinforced Concrete Pavement w/Curb,complete in place SY 3,173 $ 35.00 $ 111,055.00
14 Reinforced Concrete Pavement-Aprons-6"Thick w/Monolithic Standard Curb,
complete in place SF 2,806 $ 4.50 $ 12,627.00
15 Reinforced Concrete Pavement-Alleys-6"Thick,complete in place SF 13,153 $ 4.10 $ 53,927.30
16 Concrete Sidewalk&Ramps-4"thick,complete in place SF 15,697 $ 3.60 $ 56,509.20
17 ADA Ramps-Detectable Warning Surfaces,complete in place EA 6 $ 500.00 $ 3,000.00
Street Construction Concrete Pavement Items Subtotal $ 366,234.90
Page 1 of 3
Barracks II Subdivision Phases 107
Engineer's Estimate of Construction
Item Descri tion Estimated
P Unit Unit Price Total
Quantity
Storm Sewer Construction Items
18 36"HDPE Pipe,complete in place-Structural Backfill,complete in place LF 16 $ 62.00 $ 992.00
19 36"HDPE Pipe,complete in place-Non-Structural Backfill,complete in place LF 1,354 $ 56.00 $ 75,824.00
20 30"RCP Pipe,complete in place-Structural Backfill,complete in place LF 991 $ 75.00 $ 74,340.00
21 30"HDPE Pipe,complete in place-Structural Backfill,complete in place LF 351 $ 75.00 $ 26,332.50
22 24"RCP Pipe,complete in place-Structural Backfill,complete in place LF 161 $ 55.00 $ 8,855.00
23 18"HDPE Pipe,complete in place-Structural Backfill,complete in place LF 59 $ 30.00 $ 1,770.00
24 18"RCP Pipe,complete in place-Structural Backfill,complete in place LF 220 $ 40.00 $ 8,800.00
25 Curb Inlet- 10'wide,complete in place EA 6 $ 3,500.00 $ 21,000.00
26 Curb Inlet-5'wide,complete in place EA 2 $ 2,500.00 $ 5,000.00
27 Inlet-3-V-4430 complete in place EA 1 $ 5,000.00 $ 5,000.00
28 Inlet-V-4330 complete in place EA 3 $ 3,500.00 $ 10,500.00
29 8'x5'Junction Box,complete in place EA 2 $ 3,500.00 $ 7,000.00
30 8'x4'Junction Box,complete in place EA 3 $ 3,000.00 $ 9,000.00
31 TV Testing and Inspection,complete in place LF 3,152 $ 2.00 $ 6,304.60
32 18"S.E.T.s 6H:1V,complete in place EA 2 $ 1,250.00 $ 2,500.00
33 Channel Grading LS 1 $ 6,000.00 $ 6,000.00
34 Ditch Grading,complete in place LS 1 $ 4,000.00 $ 4,000.00
Storm Sewer Construction Items Subtotal $ 273,218.10
Water Construction Items
35 12"C900 Water Pipe w/tracer wire-Structural Backfill,complete in place LF 253 $ 36.00 $ 9,108.00
36 6"C900 Water Pipe w/tracer wire-Structural Backfill,complete in place LF 1223 $ 24.00 $ 29,352.00
37 Connect to Existing 6"Water Line EA 1 $ 500.00 $ 500.00
38 Connect to Existing 12"Water Line EA 1 $ 500.00 $ 500.00
39 Fire Hydrant Assembly(w/valve,vert.extension),complete in place EA 2 $ 3,500.00 $ 7,000.00
40 6"x 6"M.J.Tee,complete in place EA 2 $ 500.00 $ 1,000.00
41 12"x 6"M.J.Reducer,complete in place EA 1 $ 500.00 $ 500.00
42 6"M.J.Gate Valve,complete in place EA 3 $ 900.00 $ 2,700.00
43 6"x 45°M.J.Bend,complete in place EA 10 $ 400.00 $ 4,000.00
44 1.0"Water Service,23 ft(6"Line) EA 1 $ 750.00 $ 750.00
45 1.5"Water Service,< 15 ft(avg length=2 ft)(6"Line) EA 10 $ 800.00 $ 8,000.00
46 1.5"Water Service,> 15 ft(avg length=48 ft)(6"Line) EA 15 $ 1,200.00 $ 18,000.00
47 1.5"Water Service,> 15 ft(avg length=48 ft)(12"Line) EA 4 $ 1,300.00 $ 5,200.00
Water Construction Items Subtotal $ 86,610.00
Page 2 of 3
Barracks II Subdivision Phases 107
Engineer's Estimate of Construction
Item Descri tion Estimated
P Unit Quantity Unit Price Total
Sanitary Sewer Construction Items
48 6"PVC Sewer Line-D3034-Structural Backfill,complete in place LF 584 $ 24.00 $ 14,016.00
49 8"PVC Sewer Line-D3034-Structural Backfill,complete in place LF 74 $ 24.00 $ 1,776.00
50 4"Sewer Service-Single(avg.length=4ft),complete in place EA 1 $ 300.00 $ 300.00
51 4"Sewer Service-Double(avg length=4 ft),complete in place EA 20 $ 400.00 $ 8,000.00
52 4"Sewer Service-Single(avg length=48 11),complete in place EA 5 $ 850.00 $ 4,250.00
53 4"Sewer Service-Double(avg length=48 ft),complete in place EA 8 $ 950.00 $ 7,600.00
54 Complete 4"Sewer Service-Single(avg length=4 ft),complete in place EA I $ 700.00 $ 700.00
55 Tie-In to Existing 12"PVC Sewer Line,complete in place EA 1 $ 1,000.00 $ 1,000.00
56 Concrete Manhole-4'Dia.-complete in place EA 3 $ 3,000.00 $ 9,000.00
57 TV Testing and Inspection,complete in place LF 658 $ 2.00 $ 1,316.00
58 Adjust Rim Elevation of existing Manhole,complete in place EA 2 $ 500.00 $ 1,000.00
Sanitary Sewer Construction Items Subtotal $ 48,958.00
General Items Subtotal $ 54,906.00
Street Construction Concrete Pavement Items Subtotal $ 366,234.90
Storm Sewer Construction Items Subtotal $ 273,218.10
Water Construction Items Subtotal $ 86,610.00
Sanitary Sewer Construction Items Subtotal $ 48,958.00
TOTAL CONSTRUCTION $ 829,927.00
OF
gtA . —yts
j
*"...'1\tii, '
Pi.
JOSEPH P. SCHULTZ
6588•
/o-/s
F-12327
SCHULTZ ENGINEERING, LLC.
Page 3 of 3
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
Barracks II Subdivision Phases 107
Engineer's Estimate of Construction
Item Description Unit Estimated Unit Price Total
Quantity
General Items
1 Mobilization,Overhead and Construction Staking LS 1 $ 20,000.00 $ 20,000.00
2 Topsoil Removal and Replacement,complete in place LS 1 $ 12,000.00 $ 12,000.00
3 Street Name Signs,complete in place EA 2 $ 350.00 $ 700.00
4 Stop Signs,complete in place EA 2 $ 400.00 $ 800.00
5 Pavement Striping and Markings,complete in place LS 1 $ 2,000.00 $ 5,000.00
Erosion&Sediment Control-SWPPP Implementation&Maintenance,Silt Fence,
6 Construction Exit,Rock Filter Dam,etc.,complete in place LS 1 $ 5,000.00 $ 5,000.00
7 Hydroseed and Hydromulch,complete in place SY 22,812 $ 0.50 $ 11,406.00
General Items Subtotal $ 54,906.00
Street Construction Items Concrete Pavement
8 Excavation&Grading,complete in place LS 1 $ 30,000.00 $ 30,000.00
9 Mixing&incorporation of lime,6"deep,complete in place SY 3,999 $ 2.30 $ 9,197.70
10 Mixing&incorporation of lime,8"deep,complete in place SY 3,663 $ 2.90 $ 10,622.70
11 Hydrated Lime,complete in place(27 Ib/sy for 6"deep&36 lb/sy for 8"deep) Ton 120 $ 180.00 $ 21,600.00
12 6"Reinforced Concrete Pavement w/Curb,complete in place SY 1,803 $ 32.00 $ 57,696.00
13 7"Reinforced Concrete Pavement w/Curb,complete in place SY 3,173 $ 35.00 $ 111,055.00
14 Reinforced Concrete Pavement-Aprons-6"Thick w/Monolithic Standard Curb, SF 2,806 $ 4.50 $ 12,627.00
complete in place
15 Reinforced Concrete Pavement-Alleys-6"Thick,complete in place SF 13,153 $ 4.10 $ 53,927.30
16 Concrete Sidewalk&Ramps-4"thick,complete in place SF 15,697 $ 3.60 $ 56,509.20
17 ADA Ramps-Detectable Warning Surfaces,complete in place EA 6 $ 500.00 $ 3,000.00
Street Construction Concrete Pavement Items Subtotal $ 366,234.90
Page 1 of 3
Barracks II Subdivision Phases 107
Engineer's Estimate of Construction
Estimated
Item Description Unit Unit Price Total
Quantity
Storm Sewer Construction Items
18 36"HDPE Pipe,complete in place-Structural Backfill,complete in place LF 16 $ 62.00 $ 992.00
19 36"HDPE Pipe,complete in place-Non-Structural Backfill,complete in place LF 1,354 $ 56.00 $ 75,824.00
20 30"RCP Pipe,complete in place-Structural Backfill,complete in place LF 991 $ 75.00 $ 74,340.00
21 30"HDPE Pipe,complete in place-Structural Backfill,complete in place LF 351 $ 75.00 $ 26,332.50
22 24"RCP Pipe,complete in place-Structural Backfill,complete in place LF 161 $ 55.00 $ 8,855.00
23 18"HDPE Pipe,complete in place-Structural Backfill,complete in place LF 59 $ 30.00 $ 1,770.00
24 18"RCP Pipe,complete in place-Structural Backfill,complete in place LF 220 $ 40.00 $ 8,800.00
25 Curb Inlet- 10'wide,complete in place EA 6 $ 3,500.00 $ 21,000.00
26 Curb Inlet-5'wide,complete in place EA 2 $ 2,500.00 $ 5,000.00
27 Inlet-3-V-4430 complete in place EA 1 $ 5,000.00 $ 5,000.00
28 Inlet-V-4330 complete in place EA 3 $ 3,500.00 $ 10,500.00
29 8'x5'Junction Box,complete in place EA 2 $ 3,500.00 $ 7,000.00
30 8'x4'Junction Box,complete in place EA 3 $ 3,000.00 $ 9,000.00
31 TV Testing and Inspection,complete in place LF 3,152 $ 2.00 $ 6,304.60
32 18"S.E.T.s 6H:1V,complete in place EA 2 $ 1,250.00 $ 2,500.00
33 Channel Grading LS 1 $ 6,000.00 $ 6,000.00
34 Ditch Grading,complete in place LS 1 $ 4,000.00 $ 4,000.00
Storm Sewer Construction Items Subtotal $ 273,218.10
Water Construction Items
35 12"C900 Water Pipe w/tracer wire-Structural Backfill,complete in place LF 253 $ 36.00 $ 9,108.00
36 6"C900 Water Pipe w/tracer wire-Structural Backfill,complete in place LF 1223 $ 24.00 $ 29,352.00
37 Connect to Existing 6"Water Line EA 1 $ 500.00 $ 500.00
38 Connect to Existing 12"Water Line EA 1 $ 500.00 $ 500.00
39 Fire Hydrant Assembly(w/valve,vert.extension),complete in place EA 2 $ 3,500.00 $ 7,000.00
40 6"x 6"M.J.Tee,complete in place EA 2 $ 500.00 $ 1,000.00
41 12"x 6"M.J.Reducer,complete in place EA 1 $ 500.00 $ 500.00
42 6"M.J.Gate Valve,complete in place EA 3 $ 900.00 $ 2,700.00
43 6"x 45°M.J.Bend,complete in place EA 10 $ 400.00 $ 4,000.00
44 1.0"Water Service,23 ft(6"Line) EA 1 $ 750.00 $ 750.00
45 1.5"Water Service,< 15 ft(avg length=2 ft)(6"Line) EA 10 $ 800.00 $ 8,000.00
46 1.5" Water Service,> 15 ft(avg length=48 ft)(6"Line) EA 15 $ 1,200.00 $ 18,000.00
47 1.5"Water Service,> 15 ft(avg length=48 ft)(12"Line) EA 4 $ 1,300.00 $ 5,200.00
Water Construction Items Subtotal $ 86,610.00
Page 2 of 3
•
Barracks II Subdivision Phases 107
Engineer's Estimate of Construction
Item Description Unit Estimated Unit Price Total
Quantity
Sanitary Sewer Construction Items
48 6"PVC Sewer Line-D3034-Structural Backfill,complete in place LF 584 $ 24.00 $ 14,016.00
49 8"PVC Sewer Line-D3034-Structural Backfill,complete in place LF 74 $ 24.00 $ 1,776.00
50 4"Sewer Service-Single(avg.length=4ft),complete in place EA 1 $ 300.00 $ 300.00
51 4"Sewer Service-Double(avg length=4 ft),complete in place EA 20 $ 400.00 $ 8,000.00
52 4"Sewer Service-Single(avg length=48 ft),complete in place EA 5 $ 850.00 $ 4,250.00
53 4"Sewer Service-Double(avg length=48 ft),complete in place EA 8 $ 950.00 $ 7,600.00
54 Complete 4"Sewer Service-Single(avg length=4 ft),complete in place EA 1 $ 700.00 $ 700.00
55 Tie-In to Existing 12"PVC Sewer Line,complete in place EA 1 $ 1,000.00 $ 1,000.00
56 Concrete Manhole-4'Dia.-complete in place EA 3 $ 3,000.00 $ 9,000.00
57 TV Testing and Inspection,complete in place LF 658 $ 2.00 $ 1,316.00
58 Adjust Rim Elevation of existing Manhole,complete in place EA 2 $ 500.00 $ 1,000.00
Sanitary Sewer Construction Items Subtotal $ 48,958.00
General Items Subtotal $ 54,906.00
Street Construction Concrete Pavement Items Subtotal $ 366,234.90
Storm Sewer Construction Items Subtotal $ 273,218.10
Water Construction Items Subtotal $ 86,610.00
Sanitary Sewer Construction Items Subtotal $ 48,958.00
TOTAL CONSTRUCTION $ 829,927.00
.(0.0-* ,.
JOSEPH P. SCHULTZ
11.11
658
'fi . •
t �a ;
F-12327
SCHULTZ ENGINEERING, LLC,
Page 3 of 3
Schultz Engineering, LLC
Office: 979.764.3900
Fax: 979.764.3910
January 13, 2015
Alan Gibbs, P.E.
City Engineer
Development Services
City of College Station
College Station, Texas
RE: Letter Acknowledging City Standards—The Barracks II Subdivision
Phases 107
Dear Mr. Gibbs:
The purpose of this letter is to acknowledge that the construction plans for the water,
sanitary sewer, streets and drainage for the above-referenced project, to the best of my
knowledge, do not deviate from the B/CS Design Guideline Manual except that there is a
1 foot clearance from the back of the curb to the sidewalk along Kimber Lane, Block 22.
The rest of the subdivision has this clearance, and the developer would like to continue
this alignment for the sake of continuity. No other alternate design or construction
methodology was used.
I also acknowledge that, to the best of my knowledge, the details provided in the
construction plans are in accordance with the B/CS Standard Details.
Sincerely,
OF rctii-
Jose P. Schultz, P.E. *
**".
Civil Engineer '"'•*"�•"'••••�•� �
ANN P. SCHULTZ
N.143,4049,
.ars •�a�drf�sQp•s�p+N•s�s�a Boa.
/? (?r/S
F-12327
SCHULTZ ENGINEERING. LLC.
P.O. Box 11995 • College Station,Texas 77842
schultzengineeringllc.com
` FOR OFFICE USE ONLY
CASE NO.: \ 1 2-016
DATE SUBMITTED:03 •2-3
TIME: 1'. 5
CITY OF COLLEGE STATION
Home ofTexasAea-[ll University' STAFF: KJ
PLANNING & DEVELOPMENT SERVICES
TRANSMITTAL LETTER
Please check one of the options below to clearly define the purpose of your submittal.
n New Project Submittal
H Incomplete Project Submittal -documents needed to complete an application. Case No.:
x Existing Project Submittal. Case No.: 14-00900268
Project Name THE BARACKS II SUBDIVISION-Ph 107
Contact Name JOE SCHULTZ, P.E. Phone Number 979.764.3900
We are transmitting the following for Planning & Development Services to review and comment (check all that apply):
�J Comprehensive Plan Amendment n Non-Residential Architectural Standards
U Rezoning Application n Irrigation Plan
❑ Conditional Use Permit ❑ Variance Request
U Preliminary Plan Development Permit
Final Plat ❑ Development Exaction Appeal
❑ Development Plat ❑ FEMA CLOMA/CLOMR/LOMA/LOMR
n Site Plan ❑X Grading Plan
❑ Special District Site Plan ❑X Other- Please specify below
n Special District Building /Sign Civil Construction Plans r
I I Landscape Plan
INFRASTRUCTURE AND ENGINEERING DOCUMENTS
All infrastructure documents must be submitted as a complete set.
The following are included in the complete set:
n Comprehensive Plan Amendment ❑X Waterline Construction Documents
❑ TxDOT Driveway Permit n Sewerline Construction Documents
I TxDOT Utility Permit ❑x Street Construction Documents
l I Drainage Letter or Report ❑ Easement Application
❑ Fire Flow Analysis ❑ Other- Please specify
Special Instructions:
10/10 PFit i7
Schultz Engineering, LLC
Office: 979.764.3900
Fax: 979.764.3910
March 23, 2015
Kevin Ferrer
Graduate Civil Engineer
City of College Station
1101 Texas Avenue
College Station, TX 77840
Re: The Barracks II Subdivision—Ph 107—14-00900268
Dear Mr. Ferrer:
Attached are four(4) full sets of construction documents for stamping.
If you have any questions, please do not hesitate to call.
Sincerely,
Schultz Engineering, LLC.
icky Flores
P.O. Box 11995 • College Station,Texas 77842
schultzengineeringllc.com
FOR OFFICE USE ONLY
CASE NO.:
*ffDATE SUBMITTED:11411111
TIME:
CITY OF COLLEGE STATION
Home of Texas A&M University' STAFF:
PLANNING & DEVELOPMENT SERVICES
TRANSMITTAL LETTER
Please check one of the options below to clearly define the purpose of your submittal.
(� New Project Submittal
Incomplete Project Submittal -documents needed to complete an application. Case No.:
I I Existing Project Submittal. Case No.:
Project Name THE BARACKS Il SUBDIVISION- Ph 107
Contact Name JOE SCHULTZ, P.E. Phone Number 979.764.3900
We are transmitting the following for Planning & Development Services to review and comment (check all that apply):
Comprehensive Plan Amendment I I Non-Residential Architectural Standards
Rezoning Application n Irrigation Plan
Conditional Use Permit ❑ Variance Request
❑ Preliminary Plan n Development Permit
❑x Final Plat H Development Exaction Appeal
I I Development Plat n FEMA CLOMA/CLOMR/LOMA/LOMR
Site Plan IXI Grading Plan
n Special District Site Plan ❑x Other- Please specify below
n Special District Building /Sign Civil Construction Plans
n Landscape Plan
INFRASTRUCTURE AND ENGINEERING DOCUMENTS
All infrastructure documents must be submitted as a complete set.
The following are included in the complete set:
n Comprehensive Plan Amendment ❑X Waterline Construction Documents
I I TxDOT Driveway Permit [ Sewerline Construction Documents
TxDOT Utility Permit ❑X Street Construction Documents
I I Drainage Letter or Report n Easement Application
Fire Flow Analysis I I Other- Please specify
Special Instructions:
10/10 I Print'Form