MEMORANDUM
DATE: February 2, 2015
TO: ESPA Manor LLC, via; espamanor(c�gmail.com
FROM: Rachel Lazo, Planning Technician
SUBJECT: SOUTHWEST PLACE LOTS 2A-4A&2A-1 BA, BLK 1
Staff reviewed the above-mentioned final plat as requested. The following page is a list of staff
review comments detailing items that need to be addressed. Please submit the following
information and address the attached list of staff review comments:
One (1) 24"x36" copy of the revised final plat;
One (1) Mylar original of the revised final plat; and
One (1) copy of the digital file of the final plat on diskette or e-mail to:
pdsdigitalsubmittalcstx.gov.
Upon receipt of the required documents, your project will be considered formally filed with the
City of College Station. Please note that this application will expire in 90 days from the date of
this memo, if the applicant has not provided written response comments and revised documents
to the Administrator that seek to address the staff review comments contained herein.
Please note that a Mylar original of the revised final plat will be required after Staff approval and
prior to the filing of the plat. If you have any questions or need additional information, please call
me at (979) 764-3570.
Attachments: Staff Review Comments
PC: Kerr Surveying LLC, via; louise.barker@suddenlinkmail.com
P&DS Project No. 15-00900016
Planning 6 Development Services
P.O.BOX 9960 • 1101 TEXAS AVENUE •COLLEGE STATION •TEXAS •77842
TEL.979.764.3570•FAX. 979.764.3496
STAFF REVIEW COMMENTS NO. 1
Project: Southwest Place Lots 2a-4a&2a-1 ba, Blk 1 (15-00900016)
PLANNING
1. Please note that any changes made to the plans, that have not been requested by the City
of College Station, must be explained in your next transmittal letter. Any additional changes
on these plans that the City has not been made aware of will constitute a completely new
review.
2. Please note that you may be required to submit paid tax certificates if they are not current
prior to the filing of your plat.
3. Please change the title block to say:
FINAL PLAT
of
LOTS 2A-4A & 2A-1 BA, BLOCK 1
SOUTHWEST PLACE
BEING AN AMENDING PLAT OF
LOT 2A-4, BLOCK 1, SOUTHWEST PLACE
AND
LOT 2A-1 B, BLOCK 1, SOUTHWEST PLACE
Reviewed by: Rachel Lazo Date: February 2, 2015
ENGINEERING COMMENTS NO. 1
1. FYI the survey plat is showing a rear tract of .964 acres. If in the future the plan is
to separate it from lot 2A-1B block 1, the tract will need to take into account for
sanitary sewer access.
Reviewed by: Kevin Ferrer Date: January 28, 2015
ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION
1. SITE PLAN/PLAT: Developer will provide CSU with a digital, AutoCAD dwg format,
version of plat and / or site plan as soon as it is available. Email to:
gmartinez@cstx.gov , sweido@cstx.gov , or wdavis@cstx.gov
2. LOAD DATA: The developer will provide load data to CSU as soon as it is available.
This information is critical for CSU to accurately determine the size and number of
transformers, and other equipment, required to provide service to the project. Failure
to provide load data will result in construction delays and, due to clearance
requirements, could affect the final building footprint. Delivery time for transformers
and other equipment not in stock is approximate 26 weeks.
3. EASEMENTS: Developer provides descriptive easements for electric infrastructure
as designed by CSU, as shown on plat or site plan.
4. If easements are existing, the developer will be responsible for locating easements
on site to insure that electrical infrastructure is installed within easement boundaries.
5. The following easements will be required:
• 15' PUE along Texas Avenue please
GENERAL ELECTRICAL COMMENTS
1. Developer installs conduit per CSU specs and design.
2. CSU will provide drawings for electrical installation.
3. Developer provides 30' of rigid or IMC conduit for each riser conduit. CSU installs
riser.
4. Developer will intercept existing conduit at designated transformers or other existing
devices and extend as required.
5. If conduit does not exist at designated transformer or other existing devices,
developer will furnish and install conduit as shown on CSU electrical layout.
6. Developer pours electric device pads or footings, i.e. transformers, pull boxes, or
other device, per CSU specs and design.
7. Developer installs pull boxes and secondary pedestals per CSU specs and design,
Pull boxes and secondary pedestals provided by CSU.
8. Final site plan must show all proposed electrical facilities necessary to provide
electrical service, i.e. transformers, pull boxes, or switchgears, all meter locations,
and conduit routing as designed by CSU.
9. To discuss any of the above electrical comments please contact Gilbert Martinez at
979.764.6255, Sam Weido at 979.764.6314, or Weldon Davis at 979.764.5027.
Reviewed by: Weldon Davis Date: January 20, 2015
SANITATION
1. Sanitation is ok with this project.
Reviewed by: Wally Urrutia Date: January 21, 2015
Noe irkli
( vow'
CITY OF COLLEGE STATION
,,, ,
Home of Texas AthM University'
MEMORANDUM C/'-)
DATE: January 16, 2015
TO: ESPA Manor LLC, via; espamanor(a�gmail.com \J
FROM: Rachel Lazo, Planning Technician
SUBJECT: SOUTHWEST PLACE LOTS 2A-4A&2A-1 BA, BLK 1
Thank you for the submittal of your Final Plat - Minor or Amending application. Kevin Ferrer,
Graduate Engineer I, and I have been assigned to review this project. It is anticipated that the
review will be completed and any staff comments returned to you on or before Monday,
February 2, 2015. If you have questions in the meantime, please feel free to contact us.