HomeMy WebLinkAboutDevelopment Permit DEVELOPMENT PERMIT
PERMIT NO. FP2015-900104
FOR AREAS OUTSIDE THE SPECIAL FLOOD HAZARD AREA
""
(*r.
ION RE: CHAPTER 13 OF THE COLLEGE STATION CITY CODE
SITE LEGAL DESCRIPTION: SITE ADDRESS:
Castlegate II Sec 107 Etonbury Ave. & Portland Ave.
DRAINAGE BASIN:
Spring Creek
DATE OF ISSUE: 5/29/2015 VALID FOR 24 MONTHS
OWNER: CONTRACTOR:
3-D Development, LLC
4490 Castlegate Dr.
College Station, TX 77845
TYPE OF DEVELOPMENT: Full Development Permit
CONDITIONS:
1. No work beyond limits covered in permit is authorized.
2. The permit may be revoked if any false statements are made herein. If revoked, all work must cease until permit is re-
issued.
3. The permit will expire if no significant work is progressing within 24 months of issuance.
4. Other permits may have been required to fulfill local, state and federal requirements. Construction will be in
compliance with all necessary State and Federal Permits.
5. Stormwater mitigation, including detention ponds will be constructed first in the construction sequence of the project.
6. In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall be taken to
insure that all debris from construction, erosion, and sedimentation shall not be deposited in city streets, or existing
drainage facilities. Construction Site Notice or Notice of Intent (NOI) along with Stormwater Pollution Prevention Plan
(SWP3) will be kept and maintained on-site during construction as per TPDES permitting requirements. If it is
determined that the prescribed erosion control measures are ineffective to retain all sediment on-site, it is the
Contractor's responsibility to implement measures that will meet City, State, and Federal requirements.
7. All disturbed areas will be re-vegetated prior to Letter of Completion or Certificate of Occupancy.
8. All trees required to be protected as part of the landscape plan must be completely barricaded in accordance with the
Landscaping and Tree Protection Section of the City's Unified Development Ordinance, prior to any operations of this
permit. The cleaning of equipment or materials within the drip line of any tree or group of trees that are protected and
required to remain is strictly prohibited. The disposal of any waste material such as, but not limited to, paint, oil,
solvents, asphalt, concrete, mortar, or other harmful liquids or materials within the drip line of any tree required to
remain is also prohibited.
9. All construction shall be in accordance with the stamped approved plans and specifications for the above-named
project and all of the codes and ordinances of the City of College Station, as well as State and Federal Regulations
that apply. Only those deviations from BCS Unified Design Guidelines, Specifications and Details specifically
requested and approved will be allowed.
10. Special Conditions:
I, tOelUncC S , the Contractor, hereby agree to comply with all conditions herein.
Contractor Signa*Gre Date
gR9-Las-o 154,-pk iz.(5 5-67e
Phone number E-mail
I hereby grant this permit for development. Contact rsRMEL /C01'TE 979) 777-6$7I , the Public Works
Inspector assigned to this project 24 hours prior to beginning construction for scheduling required Inspections.
�, ad/s
Ci er/Representative Date
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive,Suite A
College Station,Texas 77845
Firm No. 12327
Castlegate II Subdivision-Section 107
Engineer's Estimate of Construction
Item Description Unit Estimated Unit Price Total
Quantity
General Items
1 Mobilization,Overhead and Construction Staking LS 1 $ 17,500.00 $ 17,500.00
2 Topsoil Removal and Replacement,complete in place LS 1 $ 12,000.00 $ 12,000.00
3 Pavement Striping and Markings,complete in place LS 1 $ 8,000.00 $ 8,000.00
4 Install End of Street Signs,complete in place LS 3 $ 150.00 $ 450.00
Erosion&Sediment Control-SWPPP Implementation&Maintenance,Silt Fence,
5 LS 1 $ 5,000.00 $ 5,000.00
Construction Exit,Rock Filter Dam,etc.,complete in place
6 Hydroseed and Hydromulch,complete in place SY 4,727 $ 0.50 $ 2,363.50
General Items Subtotal $ 45,313.50
Street Construction Items Concrete Pavement
7 Excavation&Grading,complete in place LS 1 $ 20,000.00 $ 20,000.00
8 Mixing&incorporation of lime,6"deep,complete in place SY 4,108 $ 2.20 $ 9,037.60
9 Mixing&incorporation of lime,8"deep,complete in place SY 1,377 $ 2.80 $ 3,855.60
10 Hydrated Lime,complete in place(27 Ib/sy for 6"deep&36 lb/sy for 8"deep) Ton 80 $ 170.00 $ 13,600.00
11 6"Reinforced Concrete Pavement w/Curb,complete in place SY 3,631 $ 36.00 $ 130,716.00
12 7"Reinforced Concrete Pavement w/Curb,complete in place SY 1,237 $ 40.00 $ 49,480.00
13 Concrete Sidewalk&Ramps-4"thick,complete in place SF 22,620 $ 3.60 $ 81,432.00
Street Construction Concrete Pavement Items Subtotal $ 308,121.20
Storm Sewer Construction Items
14 30"RCP Pipe,complete in place-Structural Backfill,complete in place LF 230 $ 70.00 $ 16,100.00
15 24"RCP Pipe,complete in place-Structural Backfill,complete in place LF 46 $ 55.00 $ 2,530.00
16 24"HDPE Pipe,complete in place-Structural Backfill,complete in place LF 137 $ 40.00 $ 5,480.00
17 18"HDPE Pipe,complete in place-Structural Backfill,complete in place LF 171 $ 30.00 $ 5,130.00
18 18"RCP Pipe,complete in place-Structural Backfill,complete in place LS 64 $ 45.00 $ 2,880.00
19 Curb Inlet-10'wide,complete in place EA 3 $ 3,500.00 $ 10,500.00
20 Curb Inlet-5'wide,complete in place EA 5 $ 2,500.00 $ 12,500.00
21 4'x4'Junction Box,complete in place EA 1 $ 2,500.00 $ 2,500.00
22 TV Testing and Inspection,complete in place LF 648 $ 2.00 $ 1,296.00
Storm Sewer Construction Items Subtotal $ 58,916.00
Page 1 of 3
Castlegate II Subdivision-Section 107
Engineer's Estimate of Construction
Item Description Unit Estimated Unit Price Total
Quantity
Water Construction Items
23 8"C900 Water Pipe w/tracer wire-Structural Backfill,complete in place LF 613 $ 28.00 $ 17,164.00
24 8"C900 Water Pipe w/tracer wire-Non-Structural Backfill,complete in place LF 202 $ 23.00 $ 4,646.00
25 8"C900 Water Pipe w/tracer wire-Restrained Joint,Spacers&End Seals,complete in LF 60 $ 60.00 $ 3,600.00
place
26 6"C900 Water Pipe w/tracer wire-Non-Structural Backfill,complete in place LF 18 $ 22.00 $ 396.00
27 6"C900 Water Pipe w/tracer wire-Non-Structural Backfill,complete in place LF 10 $ 22.00 $ 220.00
28 4"C900 Water Pipe w/tracer wire-Non-Structural Backfill,complete in place LF 505 $ 16.00 $ 8,080.00
29 16"Casing,complete in place LF 52 $ 60.00 $ 3,120.00
30 Fire Hydrant Assembly(w/valve,vert.extension),complete in place EA 1 $ 3,500.00 $ 3,500.00
31 8"x 8"M.J.Cross,complete in place EA 1 $ 600.00 $ 600.00
32 6"x 6"M.J.Tee,complete in place EA 1 $ 450.00 $ 450.00
33 8"x 6"M.J.Reducer,complete in place EA 1 $ 300.00 $ 300.00
34 6"x 4"M.J.Reducer,complete in place EA 1 $ 300.00 $ 300.00
35 8"M.J.Gate Valve,complete in place EA 5 $ 1,250.00 $ 6,250.00
36 4"M.J.Gate Valve,complete in place EA 1 $ 800.00 $ 800.00
37 8"x 45°M.J.Bend,complete in place EA 2 $ 350.00 $ 700.00
38 4"x 45°M.J.Bend,complete in place EA 4 $ 200.00 $ 800.00
39 1"Water Service,<15 ft(avg length=2 ft)(8"Line) EA 3 $ 650.00 $ 1,950.00
40 1"Water Service,>15 ft(avg length=48 ft)(4"Line) EA 2 $ 850.00 $ 1,700.00
41 1"Water Service,>15 ft(avg length=48 ft)(8"Line) EA 4 $ 850.00 $ 3,400.00
42 1.5"Water Service,<15 ft(avg length=2 ft)(4"Line) EA 5 $ 800.00 $ 4,000.00
43 1.5"Water Service,<15 ft(avg length=2 ft)(8"Line) EA 4 $ 900.00 $ 3,600.00
44 1.5"Water Service,>15 ft(avg length=48 ft)(4"Line) EA 4 $ 1,100.00 $ 4,400.00
45 1.5"Water Service,>15 ft(avg length=48 ft)(8"Line) EA 3 $ 1,200.00 $ 3,600.00
46 2"Blowoff Assembly,complete in place EA 2 $ 1,000.00 $ 2,000.00
47 Connect to Existing 8"Water Line EA 2 $ 1,000.00 $ 2,000.00
48 Waterline Testing LS 1 $ 1,000.00 $ 1,000.00
Water Construction Items Subtotal $ 78,576.00
Page 2 of 3
Castlegate II Subdivision-Section 107
Engineer's Estimate of Construction
Estimated
Item Description Unit Quantity Unit Price Total
Sanitary Sewer Construction Items
49 8"PVC Sewer Line-D3034-Non-Structural Backfill,complete in place LF 482 $ 22.00 $ 10,604.00
50 6"PVC Sewer Line-D3034-Structural Backfill,complete in place LF 32 $ 20.00 $ • 640.00
51 6"PVC Sewer Line-D3034-Non-Structural Backfill,complete in place LF 476 $ 16.00 $ 7,616.00
52 6"PVC Sewer Line-ASTM D-2241-Structural Backfill,complete in place LF 20 $ 22.00 $ 440.00
53 4"Sewer Service-Single(avg.length=4ft),complete in place EA 2 $ 400.00 $ 800.00
54 4"Sewer Service-Double(avg length=4 ft),complete in place EA 8 $ 500.00 $ 4,000.00
55 4"Sewer Service-Single(avg length=48 ft),complete in place EA 3 $ 850.00 $ 2,550.00
56 4"Sewer Service-Double(avg length=48 ft),complete in place EA 10 $ 950.00 $ 9,500.00
57 Concrete Manhole-4'Dia.-complete in place EA 12 $ 2,950.00 $ 35,400.00
58 TV Testing and Inspection,complete in place LF 1,010 $ 2.50 $ 2,525.00
Sanitary Sewer Construction Items Subtotal $ 74,075.00
General Items Subtotal $ 4.5,313.50
Street Construction Concrete Pavement Items Subtotal $ 308,121.20
Storm Sewer Construction Items Subtotal $ 58,916.00
oftWater Construction Items Subtotal $ 78,576.00
of/AAe. r e k � Sanitary Sewer Construction Items Subtotal $ 74,075.00
Ilik
1 N.
*r •.*�' TOTAL CONSTRUCTION $ 565,001.70
DEVEN L. DOYEN vs
109835 tt
0
/� IF171719/gr
FIRM # 12327
SCHULTZ ENGINEERING, LLC
Page 3 of 3