CITY OF COLLBGI STATION
Home of 'Texus A&M University`
MEMORANDUM
November 4, 2013
TO: Travis Nance, via e-mail; travis.nance(a)-oldhamgoodwin.com
FROM: Jenifer Paz, Staff Planner
SUBJECT: ST. JOSEPH CLINIC (SP)
Staff reviewed the above-mentioned site plan as requested. The following page is a list of staff
review comments detailing items that need to be addressed. The next submittal will be the third
and final review by staff for this round of reviews. If all items have not been addressed on the
next submittal, another $932 processing fee will need to be submitted for the subsequent set of
three (3) reviews. Please address the comments and submit the following information by any
Monday at 10:00 a.m. for further staff review:
City of College Station Transmittal Letter
One (1) complete sets of site civil construction documents;
One (1) revised site plans
One (1) landscaping plan
One (1) grading and erosion control plan
Please note that this application will expire in 90 days from the date of this memo, if the
applicant has not provided written response comments and revised documents to the
Administrator that seek to address the staff review comments contained herein. If there are
comments that you are not addressing with the revised site plan, please attach a letter
explaining the details. If you have any questions or need additional information, please call me
at 979.764.3570.
Attachments: Staff review comments
PC: OGC Medical I, LLC, via e-mail; hunter.goodwin(a old hamgoodwin.com
Melissa Thomas, Gessner Engineering, via e-mail; mt as essneren ineerin .co
Robert Payne, via e-mail; rpayne _rlpayne.com
P&DS Project No. 13-00900202
Planning 6, Development Services
11.C). BOX. 9960 • 1 101 "1 EXA5 A1V h.NTA'. • C;C)I_LI (. 1'. ST1X10N • TEXAS • '?&12
TET. 1)-9.764_1570 • 1*,AX. 979.76�i.,J49G
cstx.Lyov/devservices
STAFF REVIEW COMMENTS NO. 2
Project: St. Joseph Clinic (SP) - 13-00900202
PLANNING
1. When parking is adjacent to single-family, a buffer wall is required the length of the
parking, including maneuvering space. Please provide screen wall and detail on site
plan. An appeal to this requirement can be made to the DRB. Please reference UDO
Section 12-7.7.H.
2. Provide a detail of dumpster screening & gate.
3. It is preferred that the dumpster and enclosure be located outside the PUE. If this is not
possible, please add a note that the property owner is responsible for the replacement of
the screens if it becomes necessary to remove them for utility construction and/or
maintenance.
4. Building elevations shows mechanical equipment screen wall (screening from Victoria
Ave). Show wall on site plan.
5. All signage will be permitted separately, please add to note 5.
6. Note 24 references 2009 International Plumbing Codes. The City is now under the 2012
Codes.
7. Revise building data summary. According to the elevations, to the peak of the roof, the
overall height is 28 feet.
8. The fire lane turn around, from center line, will need to at least 60'. It will require
extending the drive into Lot 2, within the shared access easement.
9. Please note that the site plan cannot be approved until the Final Plat is submitted for
filing.
10. Please note that any changes made to the plans, that have not been requested by the
City of College Station, must be explained in your next transmittal letter and "bubbled" on
your plans. Any additional changes on these plans that the City has not been made
aware of will constitute a completely new review.
LANDSCAPING
1. There are only 9 Bald Cypress shown on the landscape plan. Please revise legend and
points accordingly.
Reviewed by: Jenifer Paz
Date: November 1, 2013
ENGINEERING COMMENTS NO. 2
1. Please submit an easement application for the easement being proposed with the waterline.
2. Please do not locate trees within public utility easements where possible. It appears that the
Live Oaks near the proposed water line could be shifted away from the water line.
3. Please add a note or a detail stating that the concrete headwalls/wingwalls in the
detention area need to be aesthetically treated.
4. On sheet C5.0, the sanitary sewer service and storm sewer crossing needs to be
updated according to changes that have been made.
5. Please remove the note "Not for regulatory approval, permitting or construction"
before resubmittal.
Reviewed by: Danielle Singh Date: November 1, 2013
gra
CITY OF COIJ,F3GF. STATION
Home of Texas A&M Universit),'
MEMORANDUM
October 15, 2013
TO: Travis Nance, via e-mail; travis.nance(a�.oldhamgoodwin.co
FROM: Jenifer Paz, Staff Planner
SUBJECT: ST. JOSEPH CLINIC (SP)
Staff reviewed the above-mentioned site plan as requested. The following page is a list of staff
review comments detailing items that need to be addressed. Please address the comments and
submit the following information by any Monday at 10:00 a.m. for further staff review:
City of College Station Transmittal Letter;
Memo providing written responses to all of staff's comments (identify the specific
page that each comment was addressed on or the reason for not addressing the
comment);
One (1) complete sets of site civil construction documents;
One (1) 24"x36" revised site plans;
One (1) 24"x36" landscaping plan;
One (1) 24"x36" grading and erosion control plan;
Please note that this application will expire in 90 days from the date of this memo, if the
applicant has not provided written response comments and revised documents to the
Administrator that seek to address the staff review comments contained herein. If there are
comments that you are not addressing with the revised site plan, please attach a letter
explaining the details. If you have any questions or need additional information, please contact
Jenifer Paz at 979.764.3570.
Attachments: Staff Review Comments
PC: OGC Medical I, LLC, via e-mail; hunter.goodwin ED -i
Melissa Thomas, Gessner Engineering, via e-mail;
Robert Payne, via e-mail; rpayne(a)_rlpayne.com\,/
P&DS Project No. 13-00900202
Planning e Development Services
P.O. BOX,9960 - 110111 ,XAS !),VENUE � („C>1.,1.1C=�I3 S'].;1TIC>I�' • TEXAS • 77842
TE 979.764,34_0 • FAX. 979.764.3496
cstx.gov/devservices
STAFF REVIEW COMMENTS NO. 1
Project: St. Joseph Clinic (SP) 13-00900202
PLANNING
1. In SC Suburban Commercial, when a building is located within 50' of single-family
zoning/development the eave height of the building cannot exceed 12'.
2. Label the overall building height. In SC Suburban Commercial, the max building height is 35'
and a maximum eave height of 24'.
3. Please be aware that according to the LIDO Section 7.1.H Height, that all portions of the
structure must not penetrate the inclined plane from the property line adjacent to single
family. This would include eave and roof peak.
4. When parking is adjacent to single-family, a buffer wall is required the length of the parking,
including maneuvering space. Please provide screen wall and detail on site plan.
5. Label existing buffer fence.
6. Label the area of all end islands.
7. Show mechanical equipment enclosure on the site plan.
8. Four bicycle parking must be provided. Please provide location and detail on site plan.
9. FYI. In SC Suburban Commercial, consolidated sanitation service is required. When Lot 2
develops, it may locate a dumpster near the proposed dumpster location for this
development for ease of access by the City's Sanitation Department and achieve
consolidation. Please make adjustment as necessary.
10. Remove note 6. This site can be served by a 300 gallon (side loading) or 8 -yard container
(front loading).
11. Maneuvering dimensions for the sanitation truck will vary based on the type of dumpster.
Please reference the Site Design Standards.
12. Dumpster pad must be at least 10' wide x 10' deep for a 300 gallon or 12' wide x 12' deep
for a single 8 -yard container. Please revise accordingly.
13. Provide detail of dumpster screening & gate. Required screening may differ based on the
type container. Please reference Site Design Standards.
14. Add a note that Lot 1 & 2 of the Reatta Corner Subdivision is considered a building plot.
15. Add a note that Lot 1 & 2 will be responsible for the maintenance of the private access
easement.
16. Please provide a note on the site plan that addresses the buffer requirements for the
detention area. When the adjacent lot develops it will be the responsibility of the property
owner to install the necessary plantings to meet the buffer requirements from the
surrounding single-family development.
17. Provide a general note on the site plan that all roof and ground -mounted mechanical
equipment shall be screened from view or isolated so as not to be visible from any public
right-of-way or residential district within 150' of the subject lot, measured from a point five
feet above grade. Such screening shall be coordinated with the building architecture and
scale to maintain a unified appearance.
18. Provide a general note on the site plan that states the following: Exterior building and site
lighting will meet the standards of Section 7.11 of the Unified Development Ordinance. The
light source shall not project below an opaque housing and no fixture shall directly project
light horizontally. Fixtures will be mounted in such a manner that the projected cone of light
does not cross any property line.
19. Please note that any changes made to the plans, that have not been requested by the City
of College Station, must be explained in your next transmittal letter and "bubbled" on your
plans. Any additional changes on these plans that the City has not be made of aware of will
constitute a completely new review.
Reviewed by: Jenifer Paz
Date: October 11, 2013
LANDSCAPING/STREETSCAPING/BUFFER
1. Please show all easements, existing and proposed utilities on the landscape plan.
Streetscaping may be arranged throughout the frontage (within 50' of property line along the
street) to reduce conflict withding and proposed utilities.
3. In Suburban Commercial, a. buffer must be provided with double planting from the
existing single-family develop ent. Two canopy trees every 25' and two non -canopy trees
every 15' must be provided within the buffer. Please provide non -canopy and additional
canopy trees.
4. Buffer plantings do not count towards the required landscape points and streetscape trees
do not count towards buffer planting. Please note which trees are for buffering on the
legend.
5. Shrubs, less than a 5 -gallon, not for screening are worth 1 point. Shrubs used for parking
screening must be at least 5 -gallon (10 points). Please revise.
6. Additional planting is required based on the previous comments. Please revise landscape
plan and legend.
7. Please provide a note on the landscape plan that addresses the buffer requirements for the
detention area. When the adjacent lot develops it will be the responsibility of the property
owner to install the necessary plantings to meet the buffer requirements from the
surrounding single-family development.
Reviewed by: Jenifer Paz
Date: October 11, 2013
MISCELLANEOUS
1. Irrigation system must be protected by either a Pressure Vacuum Breaker, a Reduced
Pressure Principle Back Flow Device, or a Double -Check Back Flow Device, and installed
as per City Ordinance 2394.
2. All BackFlow devices must be installed and tested upon installation as per City Ordinance
2394.
ENGINEERING COMMENTS NO. 1
1. The fire land does not appear to be sufficient for a fire truck to turn around.
2. The vehicle lay of hose from the fire hydrant needs to be shown along the fire lane.
3. Fire hydrants need to be located at least 50' from the building.
4. Please label the boxes on the south side of the building.
5. Please show the public utility easement along Victoria Avenue.
6. Please move the private sanitary sewer service out of the public utility easement.
7. Please submit an easement application for the new water line.
8. Please submit a fire flow report.
9. Please add a note stating that the site lies within the Spring Creek Sanitary Sewer Impact
Fee area.
10. Please do not locate trees within public utility easements where possible. There appears to
be Live Oaks directly over the proposed water line.
11. Please show a temporary curb where the access easement is stubbed out for the adjacent
property. Please add a temporary curb detail to the detail sheet.
12. Any concrete over 6" in height in a detention area needs to be aesthetically treated to
replicate stone or wood. This would apply to the headwall and wingwalls.
13. Please provide a profile view for the proposed water line.
14. Please provide an engineer's estimate for the public infrastructure and a letter
acknowledging that the site was designed according to City Standards.
15. A tee is required for the proposed 8" water line connection to the existing 12" main. Please
add a tee on the south side of the tee on the 12" main.
16. On sheet C6.0, general utility notes, note 13, please specify that the water line is public.
Reviewed by: Danielle Singh
Date: October 14, 2013
ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION
1. SITE PLAN/PLAT: Developer will provide CSU with a digital, AutoCAD dwg format, version
of plat and / or site plan as soon as it is available. Email to: wdavis(a cstx.gov
2. LOAD DATA: The developer will provide load data to CSU as soon as it is available. This
information is critical for CSU to accurately determine the size and number of transformers,
and other equipment, required to provide service to the project. Failure to provide load data
will result in construction delays and, due to clearance requirements, could affect the final
building footprint. Delivery time for transformers and other equipment not in stock is
approximate 26 weeks.
3. EASEMENTS: Developer provides temporary blanket easement for construction purposes
and upon completion of project must provide descriptive easements for electric infrastructure
as designed by CSU.
4. EASEMENTS: Developer provides descriptive easements for electric infrastructure as
designed by CSU, as shown on plat or site plan.
5. The following easements will be required:
• 10' PUE along all property lines
GENERAL ELECTRICAL COMMENTS
1. Developer installs conduit per CSU specs and design.
2. CSU will provide drawings for electrical installation.
3. Developer provides 30' of rigid or IMC conduit for each riser conduit. CSU installs riser.
4. Developer will intercept existing conduit at designated transformers or other existing devices
and extend as required.
5. If conduit does not exist at designated transformer or other existing devices, developer will
furnish and install conduit as shown on CSU electrical layout.
6. Developer pours electric device pads or footings, i.e. transformers, pull boxes, or other
device, per CSU specs and design.
7. Developer installs pull boxes and secondary pedestals per CSU specs and design, Pull
boxes and secondary pedestals provided by CSU.
8. Final site plan must show all proposed electrical facilities necessary to provide electrical
service, i.e. transformers, pull boxes, or switchgears, all meter locations, and conduit routing
as designed by CSU.
9. To discuss any of the above electrical comments please contact Weldon Davis at
979.764.5027.
Reviewed by: Weldon Davis Date: October 8, 2013
SANITATION
1. Need to show a turn -around for sanitation vehicles.
Reviewed by: Wally Urrutia Date: October 9, 2013
MEMORANDUM
October 4, 2013
TO: Travis Nance; via; travis.nance@oldhamgoodwin.com
FROM: Molly Hitchcock, AICP, Assistant Director
SUBJECT: ST. JOSEPH CLINIC (Site Plan, Development Permit, & NRA)
Thank you for the submittal of your Site Plan, Development Permit, and Non -Residential
Architectural Standards applications. This project will be distributed to staff next week for their
review.
PC: Hunter Goodwin,
Melissa Thomas,
Robert Payne; via:
P&DS Project No
P&DS Project No.
OGC Medical I, LLC; via: hunter. goodwin(aoldhamgoodwin.com
Gessner Engineering; via: mthomas essneren ineerin .com
rpayne@rlpayne.com
13-00900202
13-00900203
25 October 203
Ms. Jennifer Paz
Staff Planner
Planning and Development Services
City of College Station
PO Box 9960
College Station, TX 77845
RE: Response to Review Dated 14 October 2013
St Joseph Clinic NRA Review - 13-00900203
College Station, Texas 77845
Dear Jennifer:
R.L. Payne & Associates, Inc.
want to thank you for meeting and communicating and providing clarification over this past
week. With you assistance I think we have successfully addressed the Suburban Commercial
Requirements as well as your comments on the original review. The entire drawing has been
reissued.
I respectfully submit the following responses along with the attached Revised NRA drawing.
1. In Suburban Commercial, flat roofs are prohibited. All roofs must resemble residential
roof types with a maximum of 8:12 and minimum 4:12 roof slope. Please reference UDO
7.10. B.4.
All roofs are now shown sloped with a minimum of 4:12 and maximum of 8:12 roof slope.
2. Per LIDO 7.2.H.2.e., in Suburban Commercial the maximum height of buildings is 24'
to the eave and 35' to the peak of the roof at the highest point. When the eave height
exceeds 15' it must resemble a two-story facade. When the building is located within 50' of
single-family development, the eave height cannot exceed 12' and limited to one-story.
The revised maximum heights of the new elevations provide a 12' eave height up to 50 feet for
the SFR property line and 14' eave height beyond the 50 foot. We have several raised areas a
entrances providing design elements. The maximum ridge height is 27 feet.
3. Pilasters, wall plane recessions, and decorative stormwater management design
fe a ture s cannot be used to meet the architectural relief requirement in Suburban
Commercial.
The new revised elevations reflect design elements approved for the new Suburban
Commercial zone.
1509 Emerald Parkway, Suite 104, College Station, Texas 77845 (979) 696-7272 Fax (979) 696-8114
R.L. Payne & Associates, Inc.
Page 2
4. Architectural relief elements in Suburban Commercial differ from those in other
non-residential zoning districts. The window canopies are considered a design
element. At least 2 different design elements are required every 45 -foot section of all
facades, including section less than 45' facing the ROW. Please reference UDO
7.10.B.3 for the list of architectural relief elements.
Design elements approved for Suburban Commercial have been provided at a minimum of 2
design elements every 45 feet and remaining portion or distance on each elevation.
5. Please provide a sample of the Facebrick material.
We will submit a Face Brick sample as soon as we get one delivered. We did provide the brick
manufacturer, brick name and number as well as the mortar for review on line.
6. Please add contact information for the owner/developer and applicant on the title
block.
Provided as requested.
LANDSCAPING/STREETSCAPING/BUFFER
Please show all easements, existing and proposed utilities on the landscape plan.
Response: complied
2. Streetscaping may be arranged throughout the frontage (within 50' of property line
along the street) to reduce conflict with existing and proposed utilities.
Response: complied
3. In Suburban Commercial, a 20' buffer must be provided with double planting from
the existing single-family development. Two canopy trees every 25' and two non -canopy trees
every 15' must be provided within the buffer. Please provide non -canopy and additional canopy
trees.
Response: The buffer is achieved with the existing wood fence, and double planting per planting
requirements. 2 canopy trees for every 25' (or 1 canopy tree every 12'-6") 2 non -canopy trees
for every 15' (1 canopy tree every 7'-6")
4. Buffer plantings do not count towards the required landscape points and streetscape
trees do not count towards buffer planting. Please note which trees are for buffering on the
legend.
Response: complied. For additional clarity, each canopy tree (Live Oak) and each non -canopy
tree (Italian Cypress) are also labeled in the buffer area on the landscape plan.
5. Shrubs, less than a 5 -gallon, not for screening are worth 1 point. Shrubs used for
parking screening must be at least 5 -gallon (10 points). Please revise.
Response: complied. All shrubs on the project are 5 gallon.
1509 Emerald Parkway, Suite 104, College Station, Texas 77845 (979) 696-7272 Fax (979) 696-8114
Comment Responses for SP13-00900202
Site Plan- St.Joseph Clinic
Comments dated: 10-15-13
Planning (Jennifer Paz):
• In SC Suburban Commercial, when a building is located within 50' of single-family zoning/development
the eave height of the building cannot exceed 12'.
Revised as noted.
Label the overall building height. In SC Suburban Commercial, the max building height is 35' and a
maximum eave height of 24'.
Building height noted in site plan
• Please be aware that according to the UDO Section 7.1.H Height, that all portions of the structure must
not penetrate the inclined plane from the property line adjacent to single family. This would include eave
and roof peak.
Revised as noted.
When parking is adjacent to single-family, a buffer wall is required the length of the parking, including
maneuvering space. Please provide screen wall and detail on site plan.
Existing 6' wood privacy fence now labeled in site plan.
Label existing buffer fence.
Fence Labeled.
•J Label the area of all end islands.
Noted. L �
•' Show mechanical equipment enclosure on the site plan. ;��G�j ,S"'11,�n� �ud
Enclosure not required as A/C units are less than 5' in height
Four bicycle parking must be provided. Please provide location and detail on site plan.
Noted.
• FYI. In SC Suburban Commercial, consolidated sanitation service is required. When Lot 2 develops, it may
locate a dumpster near the proposed dumpster location for this development for ease of access by the
City's Sanitation Department and achieve consolidation. Please make adjustment as necessary.
Noted.
Remove note 6. This site can be served by a 300 gallon (side loading) or 8 -yard container (front loading).
�Note removed.
Maneuvering dimensions for the sanitation truck will vary based on the type of dumpster. Please
reference the Site Design Standards.
Dumpster pad dimensions updated.
Dumpster pad must be at least 10' wide x 10' deep for a 300 gallon or 12' wide x 12' deep for a single 8 -
yard container. Please revise accordingly.
Dumpster pad dimensions updated.
Provide detail of dumpster screening & gate. Required screening may differ based on the type container.
Please reference Site Design Standards.
Note added.
Add a note that Lot 1 & 2 of the Reatta Corner Subdivision is considered a building plot.
Noted.
/ Add a note that Lot 1 & 2 will be responsible for the maintenance of the private access easement.
Noted.
Please provide a note on the site plan that addresses the buffer requirements for the detention area.
When the adjacent lot develops it will be the responsibility of the property owner to install the necessary
plantings to meet the buffer requirements from the surrounding single-family development.
Noted.
Provide a general note on the site plan that all roof and ground -mounted mechanical equipment shall be
•/� screened from view or isolated so as not to be visible from any public right-of-way or residential district
_wLt n 150' of the subject lot, measured from a point five feet above grade. Such screening shall be
coordinated with the building architecture and scale to maintain a unified appearance.
R.L. Payne & Associates, Inc.
Page 3
6 Additional planting is required based on the previous comments. Please revise
landscape plan and legend.
Response: complied.
7. Please provide a note on the landscape plan that addresses the buffer requirements
for the detention area. When the adjacent lot develops it will be the responsibility of the
property owner to install the necessary plantings to meet the buffer requirements from the
surrounding single-family development.
Response: The detention area and buffer is not in the scope of this project. The property Owner
has another design team (Mitchell Morgan) which is completing the Construction Documents for
the detention area.
I hope I have adequately addressed all of your concerns and questions.
Sincerely,
1::> Obert L. T>a U vue j r.
Robert L. Payne, Jr. AIA
R. L. Payne & Associates, Inc.
1509 Emerald Parkway, Suite 104
College Station, Texas 77845
(979) 696-7272r="
resat
Cc: Oldham Goodwin Group` " �(
Gessner Engineering
1509 Emerald Parkway, Suite 104, College Station, Texas 77845 (979) 696-7272 Fax (979) 696-8114
Comment Responses for SP13-00900202
Site Plan- St.Joseph Clinic
Comments dated: 10-15-13
Note added.
Provide a general note on the site plan that states the following: Exterior building and site lighting will
meet the standards of Section 7.11 of the Unified Development Ordinance. The light source shall not
project below an opaque housing and no fixture shall directly project light horizontally. Fixtures will be
mounted in such a manner that the projected cone of light does not cross any property line.
/ Note added.
Please note that any changes made to the plans, that have not been requested by the City of College
Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional
changes on these plans that the City has not be made of aware of will constitute a completely new
review.
Noted.
In Suburban Commercial, flat roofs are prohibited. All roofs must resemble residential roof types with a
maximum of 8:12 and minimum 4:12 roof slope. Please reference UDO 7.10.13.4.
Revised.
• Per UDO 7.2.H.2.e., in Suburban Commercial the maximum height of buildings is 24' to the eave and 35' to
the peak of the roof at the highest point. When the eave height exceeds 15' it must resemble a two-story
facade. When the building is located within 50' of single-family development, the eave height cannot
exceed 12' and limited to one-story.
Revised.
• Pilasters, wall plane recessions, and decorative stormwater management design features cannot be used
to meet the architectural relief requirement in Suburban Commercial.
Noted.
• Architectural relief elements in Suburban Commercial differ from those in other non-residential zoning
districts. The window canopies are considered a design element. At least 2 different design elements are
required every 45-foot section of all facades, including section less than 45' facing the ROW. Please
reference UDO 7.10.13.3 for the list of architectural relief elements.
Noted.
• Please provide a sample of the Facebrick material.
Noted.
• Please add contact information for the owner/developer and applicant on the title block.
Information added.
Landscaping/Streetscapine/BufferEngineering (Jennifer Paz):
Reference comments from RL Payne for Landscape and NRA Comments
Miscellaneous:
• Irrigation system must be protected by either a Pressure Vacuum Breaker, a Reduced Pressure Principle
Back Flow Device, or a Double -Check Back Flow Device, and installed as per City Ordinance 2394.
Noted.
• All BackFlow devices must be installed and tested upon installation as per City Ordinance 2394.
Noted.
Engineering Comments No.1(Danielle Singh):
• The fire land does not appear to be sufficient for a fire truck to turn around.
Fire lane dimensions clarified.
• The vehicle lay of hose from the fire hydrant needs to be shown along the fire lane.
Lay of hose added.
Fire hydrants need to be located at least 50' from the building.
Hydrant location adjusted.
Comment Responses for SP13-00900202
Site Plan- St.Joseph Clinic
Comments dated: 10-15-13
• Please label the boxes on the south side of the building.
Boxes labeled as A/C
• Please show the public utility easement along Victoria Avenue.
Shown.
• Please move the private sanitary sewer service out of the public utility easement.
Sewer line moved.
• Please submit an easement application for the new water line.
Noted.
• Please submit a fire flow report.
Noted.
• Please add a note stating that the site lies within the Spring Creek Sanitary Sewer Impact Fee area.
Note added.
• Please do not locate trees within public utility easements where possible. There appears to be Live Oaks
directly over the proposed water line.
Noted.
• Please show a temporary curb where the access easement is stubbed out for the adjacent property.
Please add a temporary curb detail to the detail sheet.
Curb shown.
• Any concrete over 6" in height in a detention area needs to be aesthetically treated to replicate stone or
wood. This would apply to the headwall and wingwalls.
Noted.
• Please provide a profile view for the proposed water line.
Noted.
• Please provide an engineer's estimate for the public infrastructure and a letter acknowledging that the
site was designed according to City Standards.
Noted.
• A tee is required for the proposed 8" water line connection to the existing 12" main. Please add a tee on
the south side of the tee on the 12" main.
Tee shown.
• On sheet C6.0, general utility notes, note 13, please specify that the water line is public.
Revised as noted
Electrical Comments Requiring Immediate Attention:
• SITE PLAN/PLAT: Developer will provide CSU with a digital, AutoCAD dwg format, version of plat and / or
site plan as soon as it is available. Email to: wdavis@cstx.gov
We have coordinated with CSU as required
• LOAD DATA: The developer will provide load data to CSU as soon as it is available. This information is
critical for CSU to accurately determine the size and number of transformers, and other equipment,
required to provide service to the project. Failure to provide load data will result in construction delays
and, due to clearance requirements, could affect the final building footprint. Delivery time for
transformers and other equipment not in stock is approximate 26 weeks.
We have coordinated with CSU as required and provided load data
• EASEMENTS: Developer provides temporary blanket easement for construction purposes and upon
completion of project must provide descriptive easements for electric infrastructure as designed by CSU.
Noted
• EASEMENTS: Developer provides descriptive easements for electric infrastructure as designed by CSU, as
shown on plat or site plan.
Noted
Comment Responses for SP13-00900202
- Site Plan- St.Joseph Clinic
Comments dated: 10-15-13
• The following easements will be required: 10' PUE along all property lines
Noted
General Electrical Comments (Weldon Davis):
• Developer installs conduit per CSU specs and design.
Noted
• CSU will provide drawings for electrical installation.
Noted
• Developer provides 30' of rigid or IMC conduit for each riser conduit. CSU installs riser.
Noted
• Developer will intercept existing conduit at designated transformers or other existing devices and extend
as required.
Noted
• if conduit does not exist at designated transformer or other existing devices, developer will furnish and
install conduit as shown on CSU electrical layout.
Noted
• . Developer pours electric device pads or footings, i.e. transformers, pull boxes, or other device, per CSU
specs and design.
Noted
• Developer installs pull boxes and secondary pedestals per CSU specs and design, Pull boxes and secondary
pedestals provided by CSU.
Noted
• Final site plan must show all proposed electrical facilities necessary to provide electrical service, i.e.
transformers, pull boxes, or switchgears, all meter locations, and conduit routing as designed by CSU.
Noted
• To discuss any of the above electrical comments please contact Weldon Davis at 979.764.5027.
Noted
Sanitation (Wally Urrutia):
• Need to show a turn -around for sanitation vehicles.
An alternate hammerhead has been provided per the site design standards and dimensioned on the
site plan
Comment Responses for SP13-00900202
Site Plan- St.loseph Clinic
Comments dated: 11-4-13
P annin lenifer Paz
• When parking is adjacent to single-family, a buffer wall is required the length of the parking, including
maneuvering space. Please provide screen wall and detail on site plan. An appeal to this requirement can
be made to the DRB. Please reference UDO Section 12-7.7.H.
Buffer wall added along lengths of parking areas adjacent to the single family as required.
Provide a detail of dumpster screening & gate.
Site plan note 33 added which addresses the dumpster screening & gate.
GIt is preferred that the dumpster and enclosure be located outside the PUE. If this is not possible, please
add a note that the property owner is responsible for the replacement of the screens if it becomes
necessary to remove them for utility construction and/or maintenance.
The dumpster pad is now 10'x10' clear to accommodate the smaller dumpster size and it has been
shifted out of the easement.
Building elevations shows mechanical equipment screen wall (screening from Victoria Ave). Show wall on
site plan.
Mechanical Equipment screen wall has been added to the site plan as noted.
All signage will be permitted separately, please add to note 5.
Note 5 revised as required.
Note 24 references 2009 International Plumbing Codes. The City is now under the 2012 Codes.
Note 24 revised as required.
Revise building data summary. According to the elevations, to the peak of the roof, the overall height is 28
feet.
Building data summary has been revised to state an overall height of 28' to match the elevations.
The fire lane turn around, from center line, will need to at least 60'. It will require extending the drive into
Lot 2, within the shared access easement.
The pavement for the firelane has been extended to allow for the 60' turn around as required.
• Please note that the site plan cannot be approved until the Final Plat is submitted for filing.
Noted.
• Please note that any changes made to the plans, that have not been requested by the City of College
Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional
changes on these plans that the City has not been made aware of will constitute a completely new review
Noted.
There are only 9 Bald Cypress shown on the landscape plan. Please revise legend and points accordingly. 'N
Reference comments from RL Payne for Landscape and NRA Comments�U
Engineering Comments No.2 (Danielle Singh):
• Please submit an easement application for the easement being proposed with the waterline.
The waterline easement will be added to the Final Plat by Mitchell and Morgan prior to filing. l `�
Please do not locate trees within public utility easements where possible. It appears that the Live Oaks
near the proposed water line could be shifted away from the water line.
Reference comments from RL Payne for Landscape and NRA Comments
Please add a note or a detail stating that the concrete headwalls/wingwalls in the detention area need to
be aesthetically treated.
Note added to the concrete headwall callouts at Sta 0+00 for both storm outfalls.
On sheet C5.0, the sanitary sewer service and storm sewer crossing needs to be updated according to
changes that have been made.
Crossing note adjusted as needed.
,/ • Please remove the note "Not for regulatory approval, permitting or construction" before resubmittal.
Comment Responses for SP13-00900202
Site Plan- St.Joseph Clinic
Comments dated: 11-4-13
This will be removed when signed sealed documents are submitted for city approval.