Jennifer Reeves - Gateway Phase 2-A Certificate of Completion
From: Jennifer Reeves
To: Gina Southerland; Kim Wolfe; Nicole Cochran
Date: 3/2/2007 11:27 AM
Subject: Gateway Phase 2-A Certificate of Completion
CC: Benjamin McCarty; Chris Haver; David Stone; Doug Patterson; Molly Hitchcock
The following Items will need to be addressed prior to a clean Certificate of Completion for the shell and a
Certificate of Occupancy:
1. Construction debris needs to be removed out of this phase.
2. The construction dumpster will need to be removed out of this phase.
3. Where this phase ends and Phase 2-B begins there need to be construction fence put up to not allow the
general public in this area (this includes: sidewalks, parking lot and all paved areas within this phase 2-A) . This
is a health and safety issue and will need to be addressed.
4. Remove Port a Cans
5. there will have to be 100% established ground cover on all non paved and non landscaped areas.
Please let me know if you have any questions.
Doug - Please give me a contact name and number so that I can go over the final Certificate of Occupancy
punch list with them as soon as possible.
Thanks,
Jennifer
Jennifer Reeves
Staff Planner
City of College Station
reeves cstx. oy
(979)764-3570
(979) 764-3496 FAX