STAFF REVIEW COMME 0- O. 1
Project: NAVARRO WEST CENTE-(_ - 08-00500075
PLAN9NG
V. Please label the proposed lot with a lot and block number and remove the words
"Restricted Reserve 'A.'"
t lease remove "Restricted to Commercial Use" from the plat.
Please provide FM2154 right-of-way width in this location.
,(The vicinity map is lacking information; specifically, the streets immediately to the
north are not shown.
lease remove the L.B. (landscape buffers) from the plat.
lease remove the building lines from the plat.
remove the City Council Certificate.
/lease
lease remove the "attest" line from the Planning & Zoning Commission 1rtificachte.
leasechange '`Harris County" to "Brazos County."
P ase provide documentation that David Cottrell is authorized to sign for
ellborn CS Plaza, Ltd.
1. ase show zoning lines and zoning of this and adjacent tracts.
0,ytease include the words "unplatted" on the Pena property.
g.The level of detail included on the Steeplechase Subdivision is not necessary,
lease remove. This may allow for a larger scale.
vir4.Please include definition of any abbreviations (ie: PUE), as was done on the
tyelreliminary.
F:lease note that any changes made to the plans, that have not been requested
by the City of College Station, must be explained in your next transmittal letter
and "bubbled" on your plans. Any additional changes on these plans that the City
Y / has not been made aware of will constitute a completely new review.
\,`°\ The construction documents and reports are still under review and may affect the
plat.
Reviewed by: Jennifer Prochazka Date: April 4, 2008
ENGINEERING COMMENTS NO. 1
'iNo additional comments.
Reviewed by: Erika Bridges/ Carol Cotter Date: 4/16/08
wilECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION
Developer provides temporary blanket easement for construction purposes.
Developer provides easements for electric infrastructure as installed for electric lines
(including street lights).
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be
explained in your next transmittal letter and -bubbled" on your plans. Any additional changes on these plans
that have not been pointed out to the City, will constitute a completely new review. 2 of 3
281 376 1726 04/17/2008 09: 00 RECEIVED FROM:
#1853-002
17/2008 8:53 AM GWFAX -> 281 376 1726
Page 3 of 3
GENERAL ELECTRICAL COMMENTS
1. Developer installs conduit per City specs and design.
2. City will provide drawings for conduit installation.
3. Developer provides 30' of rigid or IMC conduit for riser poles. City installs riser.
4. Developer to intercept existing conduit at designated transformers and extend as required.
5. If conduit does not exist at designated transformer, developer to furnish and install conduit
as shown on electrical layout.
6. Developer pours transformer pad(s) per City specs and design.
7. Developer installs pull boxes and secondary pedestals as per City specs and design (pull
boxes and secondary pedestals provided by the City).
8. Developer provides digital AutoCAD 2000 or later version of plat and/or site plan. Email to
breadta'�.cstx.aov.
9. Developer provides load data for project.
10. To discuss any of the above electrical comments please contact Brent Read at
979.764.5026.
Reviewed by: Brent Read
Date: April 1, 2008
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be
explained in your next transmittal letter and"bubbled' on your plans. Any additional changes on these plans
that have not been pointed out to the City,will constitute a completely new review.
3 of 3
281 376 1726 04/17/2008 09:01 RECEIVED FROM:
#1853-nn.1
STAFF REVIEW COMMENTS NO. 1
Project: NAVARRO WEST CENTER (PP) - 08-00500074
PLANNING
1. Please label the proposed lot with a lot number and remove the words "Restricted
Reserve 'A."
2. Please remove "Restricted to Commercial Use" from the plat.
3. Please provide FM2154 right-of-way width in this location.
4. The vicinity map is lacking information, specifically, the streets immediately to the
north are not shown.
5. Please remove the L.B. (landscape buffers) from the plat.
6. Please show zoning lines and zoning of this and adjacent tracts.
7. Please include the words "unplatted" on the Pena property.
8. The level of detail included on the Steeplechase Subdivision is not necessary,
please remove. This may allow for a larger scale.
9. The title block should read as the following example does:
FINAL PLAT
of the
`Smith' Subdivision
Lots 1-3, Block 1
Reviewed by: Jennifer Prochazka Date: April 4, 2008
ENGINEERING COMMENTS NO. 1
1. No additional comments.
Reviewed by: Erika Bridges/Carol Cotter Date: 4/16/08
ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION
1. Developer provides temporary blanket easement for construction purposes.
2. Developer provides easements for electric infrastructure as installed for electric lines
(including street lights).
GENERAL ELECTRICAL COMMENTS
1. Developer installs conduit per City specs and design.
2. City will provide drawings for conduit installation.
3. Developer provides 30' of rigid or IMC conduit for riser poles. City installs riser.
4. Developer to intercept existing conduit at designated transformers and extend as required.
5. If conduit does not exist at designated transformer, developer to furnish and install conduit
as shown on electrical layout.
6. Developer pours transformer pad(s) per City specs and design.
7. Developer installs pull boxes and secondary pedestals as per City specs and design (pull
boxes and secondary pedestals provided by the City).
8. Developer provides digital AutoCAD 2000 or later version of plat and/or site plan. Email to
bread@cstx.gov.
9. Developer provides load data for project.
10. To discuss any of the above electrical comments please contact Brent Read at
979.764.5026.
Reviewed by: Brent Read Date: April 1, 2008