HomeMy WebLinkAboutStaff Review STAFF REVIEW COMMENTS NO. 1 Project: DOVE CROSSING PH. 8 (FP) - 07-00500124 PLANNING 1. The metes and bounds description provided does not close. 2. Please include the total number of lots in the title block. The application indicates 51 lots, the title block implies only 50. Is this because of the A/B lots you have proposed? 3. Each lot should have a unique lot number. Please renumber your lots to remove the NB lot names proposed. This generally implies a replat or amended plat and can be confusing. 4. Need temporary turn around and the northern end of White Dove Trail. 5. 20' P.U.E.s required adjacent to unplatted property. 6. Remove note #2 if it does not affect this tract. 7. Note #4 is un-necessary. 8. Please note that any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that the City has not been made aware of will constitute a completely new review. 9. The construction documents and reports are still under review and may affect the plat. Reviewed by: Jennifer Prochazka Date: May 23, 2007 FIRE 1. No Comments Reviewed by: Steve Smith Date: 05/23/07 SANITATION 1. Need to place a temporary turn-around at the north-end of White Dove Trail. Reviewed by: Wally Urrutia Date: May 25, 2007 ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION 1. Developer provides temporary blanket easement for construction purposes. 2. Developer provides easements for electric infrastructure as installed for electric lines (including street lights). 3. If applicable, the following easements will be required: City will follow up with required easements as needed for street lights and any additional easements for primary conduit. GENERAL ELECTRICAL COMMENTS 1. Developer installs conduit per City specs and design. 2. City will provide drawings for conduit installation. 3. Developer provides 30' of rigid or IMC conduit for riser poles. City installs riser. 4. Developer to intercept existing conduit at designated transformers and extend as required. NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. 2 of 3 5. If conduit does not exist at designated transformer, developer to furnish and install conduit as shown on electrical layout. 6. Developer pours transformer pad(s) per City specs and design. 7. Developer installs pull boxes and secondary pedestals as per City specs and design (pull boxes and secondary pedestals provided by the City). 8. Developer provides digital AutoCAD 2000 or later version of plat and/or site plan. Email to: sweido@cstx.gov. 9. Developer provides load data for project. 10. To discuss any of the above electrical comments please contact Sam Weido at 979.764.6314. Reviewed by: Sam Weido Date: 5-24-07 NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. 3 of 3 STAFF REVIEW COMMENTS NO. 2 Project: DOVE CROSSING PH. 8 (FP) - 07-00500124 PLANNING 1. Please include the total number of lots in the title block (ie: 51 lots). 2. Need temporary turn around and the northern end of White Dove Trail - please remove note # 8. The easement will either need to be secured off-site or the turn around will need to be provided within the plat boundaries (please reflect on construction documents). Reviewed by: Jennifer Prochazka Date: June 5, 2007 32 STAFF REVIEW COMMENTS NO. 1 Project: DOVE CROSSING PH. 8 (FP) - 07-00500124 PLANNING 1. Ti•re.ffietes and bounds description provided does not close. 2. Please include the total number of lots in the title block (ie: 51 lots). 3. Need temporary turn around and the northern end of White Dove Trail - please remove note # 8. The easement will either need to be secured off-site or the turn around will need to be provided within the plat boundaries (please reflect on construction documents). Reviewed by: Jennifer Prochazka Date: June 5, 2007 ENGINEERING COMMENTS NO. 1 1. A temporary turnaround must be provided. Building permits cannot be held on platted lots. 2. The property on which the permanent detention pond will eventually be located is not platted. Platting and associated infrastructure will be required at the time the detention pond is submitted for construction. 3. You will need to certify that the lots abutting the detention pond were graded to the elevations shown on the grading plan once construction is complete. If not graded to plan, water could back up into lots along Emerald Drive. You might want to establish finished floor elevations on these lots. 4. Drainage Report checklist need to be completely filled out place NA in spaces where appropriate. It appears that some information is not provided that should be. 5. What are discharge velocities out of the detention pond for Pipe A, Pipe B and the 42" outlet pipe? Are appropriate velocity dissipation and/or erosion control measures provided? 6. Some of the public infrastructure proposed with this phase is outside bounds of plat and thus not in easement or ROW. Please verify that the temporary blanket utility easement filed in 2005 has not been released. 7. Revise plans to reflect changes indicated in response to previous staff comments. 8. Provide "Letter Acknowledging City Standards". 9. Submit Water design/fire flow report for this phase. Reviewed by: Carol Cotter Date: June 8, 2007 NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. 2 of 2