HomeMy WebLinkAboutCorrespondence 101
CIVILOPMENT,DE VE
L Ltd.
CIVIL ENGINEERING & DESIGN-BUILD SERVICES
TRANSMITTAL
Date: May 14, 2007
To: Alan Gibbs
Asst. City Engineer
City of College Station
From: Kent Laza, P.E. K L.
Civil Development, Ltd.
P.O. Box 11929
College Station, Texas 77842
Phone: (979) 764-7743
Subject: Aggieland Business Park, Phase 1
College Station, Texas
Remarks:
Included with this submittal are the following documents:
Final Plat for Aggieland Business Park, Ph 1 14 copies
Construction Plans—Roadway Improvements 2 copies
Construction Plans—Water Line Improvements 2 copies
Abbreviated Drainage Report for Brazos County 1 copy
You will notice that the construction plans include improvements for both Phase 1 and Phase 2
improvements. Only Phase 1 will be constructed at this time. The plans were originally
prepared as a single phased project, so there are elements of both phases on most pages. They
are also divided into two sets — one for the street improvements and one for the water line
improvements. They were divided this way before platting became necessary.
The drainage report is an abbreviated report prepared for Brazos County regarding the two
culverts that are being set along Jones Road. It was prepared as a part of the Driveway Permit
Application that Brazos County requires.
If you have any questions, please give me a call.
1101 Texas Avenue,P.O. Box 9960
College Station,Texas 77842
Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
May 23,2007
TO: Jim Jett—60 Jones,LLC dba Aggieland Business Park,via fax 764.7676
FROM: Jason Schubert,Staff Planner
SUBJECT: AGGIELAND BUSINESS PARK Ph. 1 (FP) - Final Plat
Staff reviewed the above-mentioned final plat as requested. The following page is a list of staff review
comments detailing items that need to be addressed. If all comments have been addressed and the following
information submitted by Monday, June 4, 10:00 a.m., your project will be placed on the next available
Planning and Zoning Commission meeting scheduled for Monday, June 18, 7:00 p.m. in the City Hall
Council Chambers, 1101 Texas Avenue.
One(1) 24"x36"copy of the revised final plat;
Sixteen (16) 11"x17"copies of the revised final plat;
One (1) copy of the digital file of the final plat on diskette or e-mail to sgriffin@cstx.gov and
awelsh@cstx.gov;and
The Mylar original of the revised final plat with the owner and County Judge's signatures
(will be required after the County's approval).
Upon receipt of the required documents for the Planning& Zoning meeting,your project will be considered
formally filed with the City of College Station. Please note that if all comments have not been addressed,your
project will not be scheduled for the Planning& Zoning Commission meeting. Your project may be placed
on a future agenda once all the revisions have been made and the appropriate fees paid. Once your item has
been scheduled for the P&Z meeting, the agenda and staff report can be accessed at the following web site
on Monday the week of the P&Z meeting.
http://www.cstx.gov/home/index.asp?page=2481
If you have any questions or need additional information,please call me at 979.764.3570.
Attachments: Staff Review Comments
cc: Joe Schultz,P.E.,Civil Development,Ltd.,via joe(a,cdlbcs.com
Gary Arnold,Brazos County Planning&Traffic,via fax 775.0453
Case file#07-00500118
Jk1iO1
01 <a
CIVIL DEVELOPMENT, Ltd.*
CIVIL ENGINEERING&DESIGN-BUILD SERVICES
TRANSMITTAL
Date: November 19, 2007
To: Deborah Grace
Development Services
City of College Station
From: Ginger Urso, P.E.
Civil Development;Ltd.
P.O. Box 11929
College Station, Texas 77842
Phone: (979) 764-7743
Subject: Signed Myar of Final Plat
Aggieland Business Park, Phase 1
Brazos County, Texas
Remarks: Attached is the signed mylar of the Final Plat for the above-referenced
project. Please file this plat at your earliest convenience.
Let me know if you need anything else.
1I11��7711 �/1
4#114% AACi
CO
UV \yid
CIVIL DEVELOPMENT, Ltd.
CIVIL ENGINEERING&DESIGN-BUILD SERVICES
TRANSMITTAL
Date: June 4, 2007
To: Jason Schubert
Staff Planner
Development Services
City of College Station
From: Kent Laza, P.E.
Civil Development, Ltd.
P.O. Box 11929
College Station, Texas 77842
Phone: (979) 764-7743
Subject: Aggieland Business Center, Phase 1
College Station, Texas
Remarks: Attached are the following documents:
Revised Final Plat(24"x 36") 1 copy
Revised Final Plat(11"x 17") 16 copies 041( 1
Response to Comments 1 copy l�
The mylar and digital copies will following once the plat has been approved.
Aggieland Business Park, Phase 1 — Final Plat
Response to Staff Review Comments No. 1
Planning comments dated 5/17/2007
Engineering comments dated 5/23/2007
Planning
1. As currently stated,Note 4 references a proposed driveway for the private alley that is not
shown on the Final Plat. Reconcile the note or provide an access easement to show the
driveway location.
Response: There is an access easement along the rear of Lot 1Block 1. There is a note
indicating that on the plat, but an additional note has been added near Jones Road to
clarify.
Engineering
1. Break up the construction plans by phase. Provide a blow-off at the end of the waterline
at approx Sta. 11+00.
Response: This item was discussed with Alan Gibbs by phone on May 31, 2007. The
plans clearly show which portions of the construction are in Phase 1 and Phase 2. Alan
indicated that it was unnecessary to provide a new set of plans that deleted everything in
Phase 2. The dividing line for the water system occurs at Station 13+50. A blow-off
valve is called for at that location.
2. Provide 2"blow-offs for flushing at Sta.—0+72.47 and 23+52.
Response: This item was also discussed with Alan Gibbs. There is little room for such a
device at these locations due to conflicts with the existing 8" line that we are designing
around. Also, it is our opinion that a flushing valve is unnecessary and that adequate
flushing can be achieved through the fire hydrant located a short distance down
Emperial Loop.
3. Provide a gate valve in the vicinity of Sta. 14+00.
Response: A valve has been added near Station 14+00.
L OPMENT Ltd.
CIviL DEVE ,
CIVIL ENGINEERING&DESIGN-BUILD SERVICES
P.O. Box 11929 • College Station, Texas 77842 Phone: 979-764-7743 Fax: 979-764-7759
September 26, 2006
Mr. Richard Vance, P.E.
County Engineer
Brazos County Road & Bridge Dept.
2617 Hwy 21 West
Bryan, TX 77803
RE: Request to Construct Driveways and Waterline Crossing
Aggieland Business Park on Jones Road
Brazos County, Texas
Dear Mr. Vance:
The developer of the Aggieland Business Park, 60-Jones, LLC (Jim Jett), 526 University
Drive, Suite 101-B, College Station, Texas, 77840, request permission to construct two
driveways with the associated culverts in the Jones Road right-of-way near its
intersection with FM 60. In addition, they will install an 8" water line across Jones Road
by boring and installing an encasement pipe beneath the roadway pavement. The
attached exhibits show the general location of the project, and the plan/profile view of the
proposed roadway waterline crossing.
If you have any questions or need additional information, please give me a call at (979)
764-7743.
Sincerely Yours,
/e4,4
17--
Kent
Laza P.E.
Project Manager
attachments
CIVILDEVELOPMENT Ltd.
, q4.2
CIVIL ENGINEERING&DESIGN-BUILD SERVICES 01 . el 1(4
P.O. Box 11929 • College Station, Texas 77842 - Phone: 979-764-7743 - Fax: 979-764-7759 (J
November 13, 2007
Mr. Jason Schubert
City of College Station
P.O. Box 9960
College Station, TX 77842
RE: Aggieland Business Park
Water System Report—Addendum#2
Dear Jason:
Accompanying this letter is Addendum #2 to the Water System Report for Aggieland Business Park.
This addendum was prepared in conjunction with Phase 1 construction in that development. It includes a
Fire Hydrant Flow Test and accompanying computer model data to demonstrate that the system is capable
of meeting minimum requirements for the development. It is our understanding that this report is the last
remaining requirement by the City of College Station necessary for the plat to be filed. If you have
questions regarding the addendum or the flow test, please contact me at your convenience. Upon
completion of your review,we request that the plat be filed as soon as possible.
Sincerely,
4,,,z_l _
cerKent Laza,P.E.
Project Manager
attachment
xc: Jim Jett, 60-Jones, LLC
Steven Cast, Brushy Creek Water District