HomeMy WebLinkAboutStaff Review STAFF REVIEW COMMENTS NO. 1 Project: NINFA'S MEXICAN RESTAURANT (SP)— 07-00500095 PLANNING 1. The 4 parking spaces east of the proposed building do not have the required size. To qualify for 18' spaces, they would need to be adjacent to a 6' sidewalk. Please revise. 2. The end island adjacent to space #29 is not at least 180 square-feet. Please revise. 3. Part of main drive isle goes beyond the length of the joint access easement by almost 50' and is solely on the neighboring property. This is considered an offsite improvement and is not permitted. Please extend the easement to include the additional length or revise the site plan. The easement must be filed at the Courthouse before the site plan can be approved. 4. The detail for the dumpster enclosure in Site & Parking Details (C3.1) appears to conflict with the Civil Site Plan (C.1.1). The 12' minimum clearance applies to the narrowest portion of the enclosure, in this case, the front where gates would typically be placed. 5. Provide building elevations and color/material samples for compliance with the Non- residential Architecture Standards found in Unified Development Ordinance (UDO) Section 7.9. FYI, while this is not required for site plan approval, this approval must be obtained prior to issuance of a building permit. 6. FYI, the driveway permit has been submitted to TxDOT and is under review. Reviewed by: Jason Schubert Date: May 4, 2007 LAN DSCAPI NG/STREETSCAPING/BUFFER 1. For trees to qualify as streetscaping, they must be placed within 50' of the property line along the respective ROW. Please revise landscape plan accordingly. Reviewed by: Jason Schubert Date: May 4, 2007 TEXAS DEPARTMENT OF TRANSPORTATION 1. Access driveways to SH 6 EFR must meet TxDOT's current "Regulations for Access Driveways to State Highways". Regulations are primarily based on posted speed limits and distances between proposed & adjacent access points. Where the posted speed limit is 50 MPH or more the required spacing between access points is 425'. Where access spacing is insufficient joint access will be required or access to internal/external streets. Appropriate data will be required for any future work/permits in the ROW @ this development site, which should include drainage data, etc. Reviewed by: Karl Nelson, TxDOT Date: April 30, 2007 ENGINEERING COMMENTS NO. 1 1. Provide Easement Dedication Sheet and supporting document for the PUE required for the water line. You can dedicate actual easement or blanket. 2. What is the building construction type used to determine the fire flow requirement? 3. Fire suppression line is required. Provide design information including isolation valve and lockable lid. Revise fire flow report to include this additional flow. NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans. Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 2 of 4 4. What impact does the grading on your site have on the off-site drainage through your property. It appears some of your final grades are higher than the surrounding adjacent ground, blocking flow. 5. Is a driveway culvert not necessary? Where is upstream flow routing to? 6. Will you be able to maintain the 4:1 slope of the banks of the drainage swale, or will retaining walls be required in certain areas? 7. Revise tap note to show provided by COOS instead of COB. 8. Note regarding deflection of water pipe needs to clarify that deflection cannot be at the joint. (Sheet C2.1) 9. Provide "Letter Acknowledging City Standards". 10. Your details don't quite match BCS/Unified. Please use standard or provide letter why yours is better. Also, no detail is provided for structural backfill. 11. Unless you are providing a copy of the BCS Unified Design Details to the Contractor on this project I don't think referencing them in the notes is sufficient. Include applicable details with plan set. (Our Inspectors note that many of the contractors do not have copy during construction.) Reviewed by: Carol Cotter Date: May 8, 2007 FIRE 1. The fire lane shall be at least 20 feet wide, the telephone pedestal island needs to be reconfigured or removed so that you can maintain the 20 feet wide fire lane. 2. Fire lane needs to continue thru the parking lot so that there is no need for a turn-around. 3. One of the fire hydrants needs to be within 150 feet of the fire department connection, needs to be shown for the fire sprinkler system as the truck lays the hose. 4. Knox box location needs to be shown. Reviewed by: Jerry Duffey, Deputy Fire Marshal Date: May 4, 2007 SANITATION 1. Sanitation is ok with this project, just want to stress that the dumpster enclosure is strictly for the garbage dumpster. Reviewed by: Wally Urrutia Date: May 3, 2007 ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION 1. Developer provides temporary blanket easement for construction purposes. 2. Developer provides easements for electric infrastructure as installed for electric lines. 3. Any existing overhead lines that will need to move or be taken out of service may have to be done at the owner's expense. Owner shall contact College Station Utilities to coordinate this work as early as possible to avoid any construction delays. GENERAL ELECTRICAL COMMENTS 1. Developer installs conduit per City specs and design. 2. City will provide drawings for conduit installation. NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 3 of 4 STAFF REVIEW COMMENTS NO. 1 Project: NINFA'S MEXICAN RESTAURANT (SP)—07-00500095 PLANNING The 4 parking spaces east of the proposed building do not have the required size. To Tualify for 18' spaces, they would need to be adjacent to a 6' sidewalk. Please revise. he end island adjacent to space#29 is not at least 180 square-feet. Please revise. Part of main drive isle goes beyond the length of the joint access easement by almost 50' and is solely on the neighboring property. This is considered an offsite improvement and is Ta not permitted. Please extend the easement to include the additional length or revise the site ,plan. The easement must be filed at the Courthouse before the site plan can be approved. fol The detail for the dumpster enclosure in Site & Parking Details (C3.1) appears to conflict with the Civil Site Plan (C.1.1). The 12' minimum clearance applies to the narrowest portion of the enclosure, in this case, the front where gates would typically be placed. ' Provide building elevations and color/material samples for compliance with the Non- residential Architecture Standards found in Unified Development Ordinance (UDO) Section 7.9. FYI, while this is not required for site plan approval, this approval must be obtained prior to issuance of a building permit. 't a ov t v)F—icz> Te>`I kC TSc-T K1ir FYI, the driveway permit has been submitted to TxDOT and is under review. Reviewed by: Jason Schubert Date: May 4, 2007 LANDSCAPING/STREETSCAPING/BUFFER 1. For trees to qualify as streetscaping, they must be placed within 50' of the property line along the respective ROW. Please revise landscape plan accordingly. Reviewed by: Jason Schubert Date: May 4, 2007 TEXAS DEPARTMENT OF TRANSPORTATION 1. Access driveways to SH 6 EFR must meet TxDOT's current "Regulations for Access Driveways to State Highways". Regulations are primarily based on posted speed limits and distances between proposed & adjacent access points. Where the posted speed limit is 50 MPH or more the required spacing between access points is 425'. Where access spacing is insufficient joint access will be required or access to internal/external streets. Appropriate data will be required for any future work/permits in the ROW © this development site, which should include drainage data, etc. }-2_4;avvi ' v rvtc-r.r Reviewed by: Karl Nelson, TxDOT Date: April 30, 2007 ENGINEERING COMMENTS NO. 1 L1! Provide Easement Dedication Sheet and supporting document for the PUE required for the ,� .A"T water line. You can dedicate actual easement or blanket. What is the building construction type used to determine the fire flow requirement? j,"Fire suppression line is required. Provide design information including isolation valve and lockable lid. Revise fire flow report to include this additional flow. 1 2`I ��F---- t An r_._4=> vTtL.t NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 2 of 4 What impact does the grading on your site have on the off-site drainage through your property_ It appears some of your final grades are higher than the surrounding adjacent ground, blocking flow. J Is a driveway culvert not necessary? Where is upstream flow routing to? you be able to maintain the 4:1 slope of the banks of the drainage swale, or will retaining walls be required in certain areas? Revise tap note to show provided by COOS instead of COB. jfi/Note regarding deflection of water pipe needs to clarify that deflection cannot be at the joint. Sheet C2.1) Provide "Letter Acknowledging City Standards". ,l92four details don't quite match BCS/Unified. Please use standard or provide letter why yours v is better. Also, no detail is provided for structural bl!Unless you are providing a copy of the BCS Unified Design Details to the Contractor on this project I don't think referencing them in the notes is sufficient. Include applicable details with plan set. (Our Inspectors note that many of the contractors do not have copy during construction.) Reviewed by: Carol Cotter Date: May 8, 2007 ARE t1 :The fire lane shall be at least 20 feet wide, the telephone pedestal island needs to be configured or removed so that you can maintain the 20 feet wide fire lane. Fire lane needs to continue thru the parking lot so that there is no need for a turn-around. ,One of the fire hydrants needs to be within 150 feet of the fire department connection, needs to be shown for the fire sprinkler system as the truck lays the hose. NVA,t • - . .- • - a .. Reviewed by: Jerry Duffey, Deputy Fire Marshal Date: May 4, 2007 SANITATION 1. Sanitation is ok with this project,just want to stress that the dumpster enclosure is strictly for the garbage dumpster. 66 F 514. -i G t-l - 61\111_ 3I7 F- f-hrit Reviewed by: Wally Urrutia Date: May 3, 2007 ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION tVA•1. Developer provides temporary blanket easement for construction purposes. OA 2. Developer provides easements for electric infrastructure as installed for electric lines. Any existing overhead lines that will need to move or be taken out of service may have to be done at the owner's expense. Owner shall contact College Station Utilities to coordinate this work as early as possible to avoid any construction delays. 5f-E C CI.O --PW-mo i t - GENERAL ELECTRICAL COMMENTS �\,4„ 1. Developer installs conduit per City specs and design. 2. City will provide drawings for conduit installation. NOTE: Any changes made to the plans,that lam-not been requested by the City of College Station,must be explained in your next transmittal letter and`bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 3 of 4 3. Developer provides 30' of rigid or IMC conduit for riser poles. City installs riser. 4. Developer to intercept existing conduit at designated transformers and extend as required. 5. If conduit does not exist at designated transformer, developer to furnish and install conduit as shown on electrical layout. 6. Developer pours transformer pad(s) per City specs and design. 7. Developer installs pull boxes as per City specs and design (pull boxes provided by the City). 8. Developer provides digital AutoCAD 2000 or later version of plat and/or site plan. Email to: sweido@cstx.gov 9. Developer provides load data for project. This information needs to be addressed as early as possible since transformer lead time is extensive. 10. To discuss any of the above electrical comments please contact Sam Weido at 979.764.6314, Weldon Davis 979.764.5027. Reviewed by: Sam Weido Date: May 2, 2007 NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 4 of 4 3. Developer provides 30' of rigid or IMC conduit for riser poles. City installs riser. 4. Developer to intercept existing conduit at designated transformers and extend as required. 5. If conduit does not exist at designated transformer, developer to furnish and install conduit as shown on electrical layout. 6. Developer pours transformer pad(s) per City specs and design. 7. Developer installs pull boxes as per City specs and design (pull boxes provided by the City). 8. Developer provides digital AutoCAD 2000 or later version of plat and/or site plan. Email to: sweido@cstx.gov 9. Developer provides load data for project. This information needs to be addressed as early as possible since transformer lead time is extensive. 10. To discuss any of the above electrical comments please contact Sam Weido at 979.764.6314, Weldon Davis 979.764.5027. Reviewed by: Sam Weido Date: May 2, 2007 NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans. Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 4 of 4 STAFF REVIEW COMMENTS NO. 2 Project: NINFA'S MEXICAN RESTAURANT (SP) - 07-00500095 PLANNING 1. A response comment stated that the building elevations, etc will be provided by the architect. If they are not submitted prior to site plan approval, then the recently created "Non-residential Architecture Standards" application will need to be submitted before a Building Permit can be approved. 2. All other Planning comments have been addressed. However, please note that the site plan will not be able to be stamp approved until the Replat and TxDOT driveway permits have been approved. Reviewed by: Jason Schubert Date: May 15, 2007 ENGINEERING COMMENTS NO. 2 1. Submit revised driveway permit drawings for TxDOT. Provide sizing design for culvert. 2. Now that the fire lane is continued to the rear of the parking lot, is the stream bank structurally sound to support the heavy sanitation and fire trucks? 3. I did not see a copy of the revised Utility Letter that was listed with items submitted. Please provide copy of this letter. Reviewed by: Carol Cotter Date: May 23, 2007 STAFF REVIEW COMMENTS NO. 2 Project: NINFA'S MEXICAN RESTAURANT (SP) - 07-00500095 PLANNING �`� 1. A response comment stated that the building elevations, etc will be provided by the architect. If they are not submitted prior to site plan approval, then the recently created "Non-residential Architecture Standards" application will need to be submitted before a Building Permit can be approved. D k(___. 2. All other Planning comments have been addressed. However, please note that the site plan will not be able to be stamp approved until the Replat and TxDOT driveway permits have been approved. Reviewed by: Jason Schubert Date: May 15, 2007 ENGINEERING COMMENTS NO. 2 "-I Co- -1ZACA}F.• rAc:%. 1. Submit revised dnveway permit drawings for TxDOT. Provide sizing design for culvert. Now that the fire lane is continued to the rear of the parking lot, is the stream bank .Istructurally sound to support the heavy sanitation and fire trucks? � A77 li LFz TTE.A2. did not see a copy of the revised Utility Letter that was listed with items submitted. Please provide copy of this letter. Reviewed by: Carol Cotter Date: May 23, 2007 /crr 11<_4 x c 1F.. --f le--F--PT i Lc. z41✓ ( r 't F S . STAFF REVIEW COMMENTS NO. 3 Project: NINFA'S MEXICAN RESTAURANT (SP) - 07-00500095 ENGINEERING COMMENTS NO. 3 1. Due to proximity of the fire lane and sanitation routes to the creek bank, we believe that additional study on the bank stabilization should be done to include a geotechnical study. (The upstream property had to construct a sheet piling retaining wall to handle the erosive nature of the stream.) 2. Some sort of permanent fencing along the creek bank should be installed as a safety measure. 3. I still do not see a copy of the revised Utility Letter that was listed with items submitted. Please provide copy of this letter. Reviewed by: Carol Cotter Date: June 5, 2007 STAFF REVIEW COMMENTS NO.3 Project: NINFA'S MEXICAN RESTAURANT (SP) -07-00500095 ENGINEERING COMMENTS NO. 3 )Due to proximity of the fire lane and sanitation routes to the creek bank, we believe that additional study on the bank stabilization should be done to include a geotechnical study_ (The upstream property had to construct a sheet piling retaining wall to handle 0 .;e erosive nature of the stream.) Some sort of permanent fencing along the creek bank should be installed as a safety easure. . I still do not see a copy of the revised Utility Letter that was listed with items submitted. Please provide copy of this letter. .-7-Z -[.. Reviewed by: Carol Cotter Date: June 5, 2007 STAFF REVIEW COMMENTS NO. 4 Project: NINFA'S MEXICAN RESTAURANT (SP) - 07-00500095 PLANNING 1. The series of parking spaces 75-84 and 85-94 are 1' too narrow (with back to back curb dimensions). Please revise. FYI, the new connection between the drive aisles only has to be fire lane width, not 23' (24' back to back) since it does not have head in parking. 2. In the rear parking area, connect the Fire Lane striping across the drive aisle from the outside edges to the eastern interior end island to emphasize that it curves. 3. Please revise the Landscape Plan to reflect the new parking and end island configurations (front and rear). 4. Extend the fence along the entire eastern property line. 5. If it is the intent, please label the 420 and 475 sq. ft areas as outdoor seating areas. Reviewed by: Jason Schubert Date: June 14, 2007 ENGINEERING COMMENTS NO. 4 1. Add note to plans that the section of parking lot in the drainage easement will not impeded the flow of water nor adversely affect access to the drainage easement. Provide design that ensures this. Reviewed by: Carol Cotter Date: June 15, 2007 STAFF REVIEW COMMENTS NO. 4 Project: NINFA'S MEXICAN RESTAURANT (SP) -07-00500095 PLANNING p!#The series of parking spaces 75-84 and 85-94 are 1' too narrow (with back to back curb - dimensions). Please revise. FYI, the new connection between the drive aisles only has to be fire lane width, not 23' (24' back to back) since it does not have head in parking. a/In the rear parking area, connect the Fire Lane striping across the drive aisle from the outside edges to the eastern interior end island to emphasize that it curves. 3. Please revise the Landscape Plan to reflect the new parking and end island configurations (front and rear). V Extend the fence along the entire eastern property p5if it is the intent, please label the 420 and 475 sq. ft areas as outdoor seating areas. Reviewed by: Jason Schubert Date: June 14, 2007 ENGINEERING COMMENTS NO. 4 1. Add note to plans that the section of parking lot in the drainage easement will not impeded the flow of water nor adversely affect access to the drainage easement. Provide design that ensures this. '56-E,E-t CA-2 Watt.. 1,S 0tE. -rots i .Pr Reviewed by: Carol Cotter Date: June 15, 2007 4. I N 740V F.aQ.1 L`( Dl maKi v»,4£0 T-3424m Th oP C Q 13 -r t ' HC c,2YI�._c-tom