HomeMy WebLinkAboutStaff Report STAFF REPORT
Project Manager: Jason Schubert, Staff Planner Report Date: May 7, 2007
Email: jschubert@cstx.gov Meeting Date: May 17, 2007
Project Number: 07-00500090
Item: Presentation, possible action, and discussion on a Preliminary Plat for Aggieland
Business Park consisting of 22 lots on 117.48 acres located at 5942 Raymond Stotzer Pkwy
generally located at the northwest corner of FM 60 and Jones Road in the College Station ETJ.
Applicant: Jim Jett, Agent for 60-Jones, LLC dba Aggieland Business Park, Property Owner
Staff Recommendations: Staff recommends approval of the preliminary plat with the condition
that the attached Staff Review Comments are addressed.
ETJ Plats - Brazos County's comments and recommendations: None.
Item Summary: This item is for the consideration of a Preliminary Plat for Aggieland Business
Park, which is proposed in four phases.
Comprehensive Plan Considerations: The location of this Preliminary Plat at the northwest
corner of FM 60 and Jones Road is in the College Station ETJ or Extra-territorial Jurisdiction.
The land use plan projects Single-family Residential Low Density for this area, but the City has
no authority over land use in the ETJ. On the Thoroughfare Plan, FM 60 is shown as Freeway.
Jones Road extends from FM 60 north to Villa Maria immediately west of SH 47 but is not
classified as a thoroughfare. Currently, the water supplier for this development is Brushy Water
Supply and sewer will be on-site septic. Parkland Dedication requirements do not apply in the
ETJ.
Item Background:
The Master Plan for this development was approved by the Planning & Zoning Commission on
March 2, 2006.
Budgetary & Financial Summary: N/A
Related Advisory Board Recommendations:
Parks Board: N/A
Commission Action Options: The Commission has final authority over the preliminary plat.
The options regarding the preliminary plat are:
■ Approval
■ Denial
INFRASTRUCTURE AND FACILITIES
Water required for plat: Water is in Brushy Water Supply's CCN and is provided by
their existing 10 inch line along Jones Road and 6 inch line along F.M. 60. Phases 1
and 2 propose extension of an 8 inch line with fire hydrants. Phases 3 and 4 propose
additional fire hydrants along Jones Road.
Sewer required for plat: All lots are proposed at least 1 acre in size and will have an
on-site and will have an on-site private septic systems meeting all the requirements of
Brazos County Health Department.
Street(s) required for plat: The subdivision has frontage on both F.M. 60 and Jones
Road. Phases 1 and 2 propose a County section open-ditch roadways.
Off-site Easements required for plat: N/A
Streets/Drainage: To be designed, constructed, and inspected to Brazos County
Standards.
Flood Plain: No portion of this subdivision is within the 100 yr Flood Plain according
to FEMA FIRM Panel Nos. 48041c181-c and 48041c200-c, effective date July 2, 1992.
Oversize request: N/A
Impact Fees: N/A
Parkland Dedication Fees: N/A
Supporting Materials:
1. Small Area Map (SAM) and Aerial Map
2. Application
3. Staff Review Comments
4. Copy of Preliminary Plat (provided in packet)